Pyramid Development, LLC v. Dukane Precast, Inc.

2014 IL App (2d) 131131
CourtAppellate Court of Illinois
DecidedDecember 22, 2014
Docket2-13-1131 NRel
StatusUnpublished
Cited by1 cases

This text of 2014 IL App (2d) 131131 (Pyramid Development, LLC v. Dukane Precast, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pyramid Development, LLC v. Dukane Precast, Inc., 2014 IL App (2d) 131131 (Ill. Ct. App. 2014).

Opinion

2014 IL App (2d) 131131 No. 2-13-1131 Opinion filed December 22, 2014 ______________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT ______________________________________________________________________________

PYRAMID DEVELOPMENT, LLC, ) Appeal from the Circuit Court ) of Du Page County. Plaintiff and Counterdefendant- ) Appellant, ) ) v. ) No. 09-L-113 ) DUKANE PRECAST, INC., and M.B. ) FINANCIAL BANK, INC., ) ) Honorable Defendants and Counterplaintiffs ) Terence M. Sheen, -Appellees. ) Judge, Presiding. ______________________________________________________________________________

JUSTICE ZENOFF delivered the judgment of the court, with opinion. Justices Burke and Spence concurred in the judgment and opinion.

OPINION

¶1 This appeal arises out of mechanic’s lien litigation stemming from construction of the

Bluff Townhomes in Hinsdale, Illinois. For the reasons that follow, we affirm the trial court’s

judgment.

¶2 I. BACKGROUND

¶3 In March 2007, Dr. Husam Aldairi and plaintiff, Pyramid Development, LLC, entered

into a written contract for plaintiff to construct eight townhome units, which became known as

the Bluff Townhomes, in unincorporated Hinsdale. The contract price was $3,030,000.

Plaintiff was a construction manager, owned no equipment, had no employees, and hired 2014 IL App (2d) 131131

subcontractors to do all of the work. Plaintiff’s principal was Ramy Saif. When plaintiff and

Aldairi contracted to build the Bluff Townhomes, they already had a working relationship.

Plaintiff was working, or had worked, on approximately seven different projects for Aldairi.

Regarding the Bluff Townhomes, Aldairi required plaintiff to submit sworn affidavits with each

draw. Broadway Bank was Aldairi’s lender. Defendant, M.B. Financial Bank, Inc. (Bank), is

Broadway Bank’s successor.

¶4 Plaintiff contracted with defendant, Dukane Precast, Inc. (Dukane), to furnish

prefabricated concrete slabs, which were to form the walls and floors of the townhomes. The

contract price with Dukane was $1,040,000. Dukane delivered the materials, and they were

incorporated into the townhomes. However, Saif noticed problems. The slabs were uneven;

there were gaps between the walls and the floors; the electrical boxes in the walls were not even

and straight; and the conduit between some of the walls was plugged with concrete.

¶5 Completion of the townhome development required the erection of retaining walls, which

held up dirt, on the property. The west wall was completed while plaintiff was still the general

contractor, but due to burgeoning difficulties between plaintiff and Aldairi, Aldairi had someone

else finish the contiguous north and east wall. Eventually that wall failed at the northeast

corner. In January 2009, Aldairi terminated plaintiff.

¶6 During lengthy litigation, Aldairi filed for bankruptcy protection. Aldairi entered into a

consent judgment with the Bank, and the Bank eventually sold the property to a party not

associated with the litigation. The Bank assumed the duty to pay plaintiff’s mechanic’s lien

claim, and the Bank claimed that it had paid to repair the failed retaining wall. In June 2012,

the trial court heard, in a single trial, plaintiff’s claim to foreclose its mechanic’s lien, Dukane’s

claim against plaintiff for breach of contract, plaintiff’s claim against Dukane for breach of

-2- 2014 IL App (2d) 131131

contract, and the Bank’s claim for a setoff against plaintiff for the repair of the retaining wall.

To aid in understanding the evidence, we treat the issues involving the mechanic’s lien and the

Bank separately from the issues involving plaintiff’s and Dukane’s breach-of-contract claims.

¶7 The Mechanic’s Lien Foreclosure

¶8 This phase of the trial presented two issues: plaintiff’s right to a mechanic’s lien and the

Bank’s right to a setoff against any award to plaintiff. Plaintiff filed a claim for a lien on May

6, 2009. The lien claim states that plaintiff’s last day of work was January 15, 2009, and that

$235,000 was owed for improvements on the premises.

¶9 Pursuant to Aldairi’s request as the owner of the property, plaintiff furnished a

contractor’s sworn statement with each draw. In all, plaintiff submitted six draws. Aldairi

approved the first five, and they were paid. Aldairi did not approve the sixth draw, which was

not paid.

¶ 10 A significant issue was what caused the retaining wall to fail. Saif testified that a cause

of the failure was Aldairi’s insistence on planting trees around it instead of the bushes called for

in the original plans. According to Saif, the tree roots damaged the wall. Saif also testified

that a heavy machine had fallen against the wall, causing damage. According to Dallas

Williams, an architect presented by the Bank, the wall was built incorrectly. Williams took the

wall apart and found that it contained too little of a material called geogrid, which was needed to

give the wall structure. In Williams’ opinion, the wall had to be rebuilt, and he testified that

$145,000 was a reasonable cost to fix the wall. That amount was purportedly reflected on an

invoice submitted by a contractor that had rebuilt the wall. Plaintiff’s expert testified that it

would cost approximately $70,000 to $80,000 to fix the wall.

-3- 2014 IL App (2d) 131131

¶ 11 Another issue was the accuracy of the contractor’s sworn affidavits that Saif prepared and

submitted to Aldairi pursuant to Aldairi’s request that such sworn statements accompany each

draw. Saif admitted that the sworn affidavits were not accurate. According to Saif, the

subcontractors’ names listed on the affidavits were not accurate, because “the names honestly

change all the time.” Saif testified that, for example, Tri-Star Electric did the electrical work,

but he did not list it on the affidavits for draws one through six. According to Saif, plaintiff did

none of the actual work; however, he listed plaintiff on the sworn affidavits as having done

various jobs. Saif testified that plaintiff did not keep any records of which subcontractors

performed work on the Bluff Townhomes. According to Saif, “none of the numbers [on the

sworn affidavits] are exact numbers.” He testified that the numbers on the sworn affidavits

were “estimates” and that the numbers reflected “large cushions on every single line item.”

Saif did not obtain lien waivers from any of the subcontractors.

¶ 12 Plaintiff offered exhibit number 32A to support its lien claim. The group exhibit

consisted of copies of canceled checks that Saif attributed to the construction of the Bluff

Townhomes. He testified that he placed check marks next to those checks that pertained to

plaintiff’s lien claim. He also testified that the checks were originally written for all of

Aldairi’s projects, not just the Bluff Townhomes, and that he had to “decipher” prior to trial

“what checks go where.” According to Saif, that was “hard to figure out.”

¶ 13 Dukane’s Concrete Work

¶ 14 After Saif noticed the problems with Dukane’s precast concrete slabs, Dukane

representatives met with Saif on May 7, 2008, at the Bluff Townhomes to resolve the issues.

One of Dukane’s proposed solutions was to cut the prefabricated concrete walls to run conduit

through them. Because those walls were load-bearing, Saif rejected that proposition.

-4- 2014 IL App (2d) 131131

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pyramid Development, LLC v. Dukane Precast, Inc.
2014 IL App (2d) 131131 (Appellate Court of Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2014 IL App (2d) 131131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pyramid-development-llc-v-dukane-precast-inc-illappct-2014.