Gerdau Ameristeel US, Inc. v. Broeren Russo Construction, Inc.

2013 IL App (4th) 120547, 992 N.E.2d 27
CourtAppellate Court of Illinois
DecidedMay 23, 2013
Docket4-12-0547
StatusPublished
Cited by3 cases

This text of 2013 IL App (4th) 120547 (Gerdau Ameristeel US, Inc. v. Broeren Russo Construction, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gerdau Ameristeel US, Inc. v. Broeren Russo Construction, Inc., 2013 IL App (4th) 120547, 992 N.E.2d 27 (Ill. Ct. App. 2013).

Opinion

ILLINOIS OFFICIAL REPORTS Appellate Court

Gerdau Ameristeel US, Inc. v. Broeren Russo Construction, Inc., 2013 IL App (4th) 120547

Appellate Court GERDAU AMERISTEEL US, INC., Plaintiff, and AHAL Caption CONTRACTING CO., INC., and BLAGER CONCRETE COMPANY, Plaintiffs-Appellees and Cross-Appellants, v. BROEREN RUSSO CONSTRUCTION, INC., and CAMPUS INVESTORS 309, LLC, Defendants-Appellants and Cross-Appellees, and JACOBSMEYER- MAULDIN CONSTRUCTION COMPANY; ROLAND REALTY, INC.; BROEREN RUSSO CONSTRUCTION, INC.; CAMPUS INVESTORS 309, LLC; RBS CITIZENS, N.A.; CHARTER ONE, a Division of RBS CITIZENS, N.A.; KLG CORPORATION; PENHALL COMPANY; AHAL CONTRACTING CO., INC.; BLAGER CONCRETE COMPANY; UNKNOWN OWNERS; and NONRECORD CLAIMANTS, Defendants. District & No. Fourth District Docket No. 4-12-0547

Filed May 23, 2013 Rehearing denied July 1, 2013

Held In a mechanics lien dispute arising from a construction project in which (Note: This syllabus defendant subcontractor submitted a waiver of lien and subcontractor’s constitutes no part of the affidavit showing that it owed more to subcontractors and suppliers than opinion of the court but it had previously shown on waivers and affidavits and plaintiff sub- has been prepared by the subcontractors and plaintiff supplier sought what they were still owed, the Reporter of Decisions for trial court’s judgment for the sub-subcontractors was reversed and the the convenience of the cause was remanded for an order granting the sub-subcontractors their reader.) pro rata share of the amount owed to the subcontractor minus any pro rata portion paid to plaintiff supplier, and the subcontractors’ appeal from the denial of their petition for attorney fees and costs was rendered moot, since the sub-subcontractors had to bear the risk from false statements made by subcontractors in the absence of timely notice to the owner or general contractor of money due. Decision Under Appeal from the Circuit Court of Champaign County, No. 09-CH-149; Review the Hon. Charles McRae Leonhard, Judge, presiding.

Judgment Reversed and remanded with directions.

Counsel on Rochelle A. Funderburg (argued), of Meyer Capel, PC, of Champaign, for Appeal appellants.

Joseph P. Chamley and Mark C. Palmer (argued), both of Evans, Froehlich, Beth & Chamley, of Champaign, for appellee Blager Concrete Company.

Carl E. Metz II (argued) and Bradley M. Arnold, both of Falk Metz, LLC, of Chicago, for appellee Ahal Contracting Company.

Panel JUSTICE TURNER delivered the judgment of the court, with opinion. Justices Knecht and Harris concurred in the judgment and opinion.

OPINION

¶1 In March 2009, plaintiff, Gerdau Ameristeel US, Inc. (Gerdau), filed a verified complaint for foreclosure of its mechanics lien and other relief against defendants, Jacobsmeyer- Mauldin Construction Company (JMC); Roland Realty, Inc.; Broeren Russo Construction, Inc. (Broeren Russo); Campus Investors 309, LLC (Campus); RBS Citizens, N.A., and Charter One, a Division of RBS Citizens, N.A.; KLG Corporation; Penhall Company; Ahal Contracting Co., Inc. (Ahal); Blager Concrete Company (Blager); and unknown owners and nonrecord claimants. Blager and Ahal later sought to enforce liens under the Mechanics Lien Act (Act) (770 ILCS 60/1 to 39 (West 2008)). ¶2 In December 2011, the trial court granted summary judgment in favor of Ahal and Blager. In April 2012, the court entered a judgment of foreclosure and sale. The court denied Ahal’s and Blager’s requests for attorney fees and deposition costs. ¶3 In the appeal of Campus and Broeren Russo, they argue the trial court erred in granting summary judgment in favor of Ahal and Blager. In their cross-appeals, Ahal and Blager argue the court abused its discretion in denying their petitions for attorney fees and claim costs of depositions should have been included as recoverable costs. In Campus and Broeren

-2- Russo’s appeal, we reverse and remand. Given our ruling herein, the issues raised in Ahal’s and Blager’s cross-appeals are rendered moot.

¶4 I. BACKGROUND ¶5 Initially, an introduction of the parties is necessary in this case. Campus is the owner of the subject property located at 309 East Green Street in Champaign. Broeren Russo is a general contractor. JMC is a subcontractor, and Ahal and Blager are secondary subcontractors. Gerdau is a material supplier. ¶6 Campus entered into a contract with or otherwise engaged the services of Broeren Russo to perform the construction of a high-rise apartment building, known as the Green Street Tower project, in Champaign. Broeren Russo then entered into a contract with or otherwise engaged the services of JMC to provide labor and materials for the project. JMC entered into a contract with or otherwise engaged the services of Ahal and Blager to provide labor and materials to the project. Blager acted at various times as a subcontractor under both JMC and Ahal. Over time, Broeren Russo paid $9,539,150 to JMC. ¶7 All of the materials and services provided by Blager and Ahal for the project were of excellent quality, delivered to, and accepted upon the property and were incorporated in and formed a part of the improvement and constitute a permanent and valuable improvement of the property. Ahal and Blager fully performed their obligations to the project in a timely, good and workmanlike manner. Ahal indicated it completed all work under the contract on August 22, 2008, and Blager stated it made its last delivery of concrete materials on September 2, 2008. ¶8 Broeren Russo submitted pay requests that were reviewed and then paid through Chicago Title & Trust Company (Chicago Title). In October 2008, JMC submitted its waiver of lien to date/subcontractor’s affidavit to Broeren Russo, indicating JMC owed more to its subcontractors and suppliers than it had shown on previous requests for payment and waiver of lien to date/subcontractor’s affidavits. Although $495,850 remained to be paid on the contract, JMC owed a total of $722,995.35. Broeren Russo froze all payments pending a resolution. ¶9 On November 18, 2008, Ahal timely mailed its notice of claim of subcontractor by United States mail certified return receipt requested, and delivery limited to addressee only, to all necessary parties. Ahal stated it had been employed by JMC to “pour and finish floor slabs,” as well as perform other work, and was due $385,096.44. Campus and Broeren Russo stipulated they received Ahal’s notice. On December 15, 2008, Ahal timely filed and recorded its subcontractor’s claim for lien in the office of the recorder of deeds in Champaign County. Campus and Broeren Russo stipulated Ahal’s lien was timely and properly recorded. ¶ 10 On November 26, 2008, Blager timely mailed its notice and claim for subcontractor/material provider’s liens by United States mail certified return receipt requested, and delivery limited to addressee only, to all necessary parties. Blager stated $78,431.44 remained unpaid. Campus and Broeren Russo stipulated they received Blager’s notice. On December 19, 2008, Blager timely filed and recorded its notice and claim for subcontractor liens in the recorder’s office. Campus and Broeren Russo stipulated Blager’s

-3- liens were timely and properly recorded. ¶ 11 In March 2009, Gerdau filed a verified complaint for foreclosure of a mechanics lien and other relief against various defendants with an interest in the property. Gerdau alleged it entered into a contract with JMC in July 2008 to furnish and supply rebar and related materials for the project. In August 2008, Gerdau completed the work and $658,590.54 was due and owing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Süd Family Ltd. Partnership v. Otto Baum Co.
2024 IL App (4th) 220782 (Appellate Court of Illinois, 2024)
Pyramid Development, LLC v. Dukane Precast, Inc.
2014 IL App (2d) 131131 (Appellate Court of Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2013 IL App (4th) 120547, 992 N.E.2d 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gerdau-ameristeel-us-inc-v-broeren-russo-construct-illappct-2013.