Contractors' Ready-Mix, Inc. v. Earl Given Construction Co.

611 N.E.2d 529, 242 Ill. App. 3d 448, 183 Ill. Dec. 266
CourtAppellate Court of Illinois
DecidedApril 21, 1993
Docket4-92-0282
StatusPublished
Cited by13 cases

This text of 611 N.E.2d 529 (Contractors' Ready-Mix, Inc. v. Earl Given Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contractors' Ready-Mix, Inc. v. Earl Given Construction Co., 611 N.E.2d 529, 242 Ill. App. 3d 448, 183 Ill. Dec. 266 (Ill. Ct. App. 1993).

Opinions

JUSTICE GREEN

delivered the opinion of the court:

On April 1, 1991, plaintiff Contractors’ Ready-Mix, Inc. (Ready-Mix), filed suit in the circuit court of Logan County against Earl Given Construction Company, Inc. (Given), First Midwest Bank/West-em Illinois, N.A./Lincoln, as trustee of a certain land trust (owner), Guardian Life Insurance Company of America (INA), and unknown owners and nonrecord claimants. Count I was against all defendants seeking foreclosure of a mechanic’s lien for materials furnished by Ready-Mix to Given, a general contractor on a project to erect a WalMart store on premises of the owner at Lincoln. INA was alleged to be a mortgagee of those premises. Count II was solely against Given and sought a money judgment against Given for the amount unpaid for the furnishing of those materials.

Ready-Mix, the supplier of materials to Given, filed a motion for summary judgment as to both counts. The owner moved for summary judgment as to count I. On March 15, 1992, the circuit court denied the owner’s amended motion for summary judgment and entered a joint and several summary judgment in favor of Ready-Mix against both defendants as to count I providing for foreclosure upon and sale of the premises to satisfy a mechanic’s lien against the premises in the sum of $108,450.59, which included attorney fees and court costs. Section 28 of the Act requires that when a subcontractor or supplier of materials sues to foreclose a mechanic’s lien, both the owner and general contractor must be made parties and are jointly and severally liable. 111. Rev. Stat. 1989, ch. 82, par. 28.

This judgment did not rule upon count II. The court made a finding that no just reason existed to delay enforcement or appeal of the judgment upon count I. (134 111. 2d R. 304(a).) The owner and Given have appealed. We reverse the summary judgment in favor of Ready-Mix and remand for further proceedings.

A brief summary of various provisions of the Act is necessary to an understanding of the facts. Section 21 of the Act (111. Rev. Stat. 1989, ch. 82, par. 21) provides for a lien for subcontractors and suppliers of material for the unpaid amount of the value which they have furnished to the premises. That section also states that an owner shall not “be compelled to pay a greater sum for or on account of the completion of *** [an] improvement than the [contract price], unless payment be made to the contractor *** in violation of the rights and interests of the persons intended to be benefited by this [A]ct” (HI. Rev. Stat. 1989, ch. 82, par. 21). Section 32 of the Act similarly states:

“No payments to the contractor or to his order of any money or other considerations due or to become due to the contractor shall be regarded as rightfully made, as against the sub-contractor, laborer, or party furnishing labor or materials, if made by the owner without exercising and enforcing the rights and powers conferred upon him in sections 5, 21 and 22 of this act.” (111. Rev. Stat. 1989, ch. 82, par. 32.)

Section 27 of the Act provides that when an “owner or his agent is notified as provided in [the Act], he shall retain” from money to be paid the contractor enough to pay the subcontractor, supplier or worker to whom money is due. 111. Rev. Stat. 1989, ch. 82, par. 27.

Section 5 of the Act provides that before an owner makes payments to a contractor, the owner shall require the contractor to give the owner an affidavit setting forth “the names and addresses of all parties furnishing materials and labor, and of the amounts due or to become due [to] each.” (Emphasis added.) (111. Rev. Stat. 1989, ch. 82, par. 5.) Section 24 of the Act states that subcontractors, including those furnishing materials, “may at any time after making his or her contract with the contractor, and shall within 90 days after the completion thereof *** cause a written notice of his or her claim and the amount due or to become due thereunder, to be sent” in certain ways to the owner or its contractor. (Emphasis added.) (HI. Rev. Stat. 1989, ch. 82, par. 24.) We will discuss section 22 of the Act (111. Rev. Stat. 1989, ch. 82, par. 22) later.

The owner does not dispute the sufficiency of the record to support a summary judgment for Ready-Mix as long as that judgment is in the sum of $127.25 plus a reasonable amount for costs and attorney fees. The owner maintains it complied with all the pertinent statutory provisions which would absolve it of liability except that arising from a section 5 affidavit of Given in regard to amounts due to Ready-Mix which indicates $127.25 was due or would become due to Ready-Mix to complete the contract. Ready-Mix’s position is twofold. It first maintains that the owner did not take sufficient statutorily required steps to prevent its being required to pay sums over and above the contract price in the amount awarded by the trial court. Second, Ready-Mix asserts that if both parties met in full the requirements of the Act in order to protect themselves, the intent of the Act and the equities are with it. The circuit court’s decision was based on the latter contention of Ready-Mix. Given objects only to the amount of fees awarded Ready-Mix.

Summary judgment is permissible only when “the pleadings, depositions, and admissions on file, together with the affidavits, if any, show” all material elements of fact are conclusively shown to exist in favor of the party seeking summary judgment. (111. Rev. Stat. 1991, ch. 110, par. 2 — 1005(c).) The facts shown of record arise mostly from uncontested affidavits. The significant events begin with a contract being entered into between the owner and Given sometime prior to June 30, 1990, for erection of the Wal-Mart store on the owner’s premises. Given then entered into an oral contract with Ready-Mix to provide concrete materials for the project as required by Given. Given agreed to pay Ready-Mix a reasonable price, finance charges of 2% per month on all balances remaining unpaid for more than 30 days, and attorney fees or costs of collection on the account. Ready-Mix received two payments from Given of $62,888.12 and $83,465.75, respectively, for materials delivered through September 14,1990.

Ready-Mix did not receive payment of $77,102.77 for materials delivered September 14, 1990, through October 27, 1990, its last date of performance. Ready-Mix submitted monthly statements to Given indicating the amount unpaid plus finance charges. On October 25, 1990, Given served the owner with a document purporting to be a waiver of Given’s lien for $280,800 worth of work which Given had completed to that date. The lower portion of the document was an affidavit on behalf of Given, listing the sum of $127.25 as the amount due Ready-Mix. The affidavit stated “the items mentioned include all labor and material required to complete said work according to plans and specifications” (emphasis added). This affidavit met the requirements of section 5 of the Act.

Given’s section 5 affidavit also stated that the then balance on its contract with the owner was $308,800. On November 2, 1990, the owner paid Given $280,800, leaving $28,000 remaining on the total contract price. On November 22, 1990, the subject property was apparently sold, and the purchaser apparently paid Given $60,290 on November 30, 1990. An affidavit attached to the owner’s revised motion for summary judgment indicates that the $60,290 payment was intended to include the $28,000 due on the original contract for construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gerdau Ameristeel US, Inc. v. Broeren Russo Construction, Inc.
2013 IL App (4th) 120547 (Appellate Court of Illinois, 2013)
Weather-Tite v. University of St. Francis
Appellate Court of Illinois, 2008
Weather-Tite, Inc. v. University of St. Francis
892 N.E.2d 49 (Appellate Court of Illinois, 2008)
Lazar Bros. Trucking, Inc. v. a & B Excavating, Inc.
365 Ill. App. 3d 559 (Appellate Court of Illinois, 2006)
Lazar Bros. Trucking v. a & B Excavating
850 N.E.2d 215 (Appellate Court of Illinois, 2006)
Bricks, Inc. v. C & F DEVELOPERS, INC.
836 N.E.2d 743 (Appellate Court of Illinois, 2005)
Bricks, Inc. v. C&F Developers, Inc.
Appellate Court of Illinois, 2005
Struebing Construction Co. v. Golub-Lake Shore Place Corp.
666 N.E.2d 846 (Appellate Court of Illinois, 1996)
Alliance Steel, Inc. v. Piercy
660 N.E.2d 1341 (Appellate Court of Illinois, 1996)
Contractors' Ready-Mix, Inc. v. Earl Given Construction Co.
611 N.E.2d 529 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
611 N.E.2d 529, 242 Ill. App. 3d 448, 183 Ill. Dec. 266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contractors-ready-mix-inc-v-earl-given-construction-co-illappct-1993.