Berkshire Warehouse Co. v. Hilger & Co.

268 Ill. 463
CourtIllinois Supreme Court
DecidedJune 24, 1915
StatusPublished
Cited by3 cases

This text of 268 Ill. 463 (Berkshire Warehouse Co. v. Hilger & Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berkshire Warehouse Co. v. Hilger & Co., 268 Ill. 463 (Ill. 1915).

Opinion

Mr. Justice Carter

delivered the opinion of the court:

This is an appeal, on a certificate of importance, by the Edward Hines Lumber Company from a judgment of the Appellate Court affirming a decree of the superior court of Cook county denying appellant a mechanic’s lien against the property of appellee, the Berkshire Warehouse Company, and dismissing the intervening petition of appellant for want of equity.

In July, 1909, appellee made a contract with Hilger & Co., a general contractor in Chicago, to construct certain improvements for $75,000 on the premises owned by appellee. Work was begun under this contract July 8, 1909, and continued, various sub-contractors furnishing labor and material. Hilger & Co. was paid by appellee on this contract on August 9, 1909, $2500, August 20, $2500, and September 4, $5000, without requiring, at the time these payments were made, statements to be furnished by Hilger & Co., as provided by section 5 of the Mechanic’s Lien law of 1903. August 16, 1909, appellant entered into an agreement with Hilger & Co. to furnish lumber and building material for use in the erection of the improvement on said premises, no particular quantity being ordered at that time and no definite price being fixed therefor, except that the orders were to be given from time to time as the materials were needed, at the then market price. September 28, 1909, appellee received from Hilger & Co. a sworn statement in accordance with said section 5 of the Mechanic’s Lien law, and thereafter, under this statement, paid $17,000. On October 22 Hilger & Co. furnished another sworn statement, under which it was paid $15,000; and on November 16 it made another statement, as required by the Mechanic’s Lien act, under which it was paid, November 18, $16,000. The name of appellant did not appear on either of these three statements as furnishing material or doing work on the contract. The total cost of the building, as per original contract, was $75,000, plus $10,000 allowed by the architect for extras. When the $16,000 was paid, under the November 16 statement, to Hilger & Co. it had received on the contract $58,000, leaving in the hands of appellee, still unpaid under the contract, $27,000. In said statement of November 16, 1909, it was set forth that there was due or to become due and owing for material and labor to contractors a balance of $23,874.08. Hilger & Co. did not complete the contract but it was completed by appellee. As that, however, has no bearing on the question here involved the details need not be discussed.

Counsel for appellant argue that the payments of August 9, August 20 and September 4, aggregating $10,000, having been made without complying with the provisions of the Mechanic’s Lien law as to statements, were wrongfully paid, and that therefore appellant is entitled to a mechanic’s lien on the premises for the amount of its claim; while counsel for the appellee argue that no statements on the above mentioned dates could have properly been made which showed any amount due appellant, as at the time of the first payment no contract had been entered into between Hilger & Co. and appellant and no definite amounts were due or to become due at the time of the last mentioned payments. When statements were made by the contractor on September 28, October 22 and November 16 the owner retained sufficient funds to pay all sub-contractors mentioned in those statements. It is conceded by counsel for appellee that the warehousé company should have required a statement to be made before paying out these three sums in question, but counsel argue that appellant was in no way injured.

The principal question requiring our consideration is whether the failure to make the statements required by the statute, before the said payments of August 9 and 20 and September 4 were made, renders the property of appellee subject to a mechanic’s lien up to $10,000,—the amount of those payments. Counsel for appellant argue that appellee not having required Hilger & Co. to comply with the statute before these payments were made, this violation of the statute cannot subsequently be corrected by any act of appellee or the contractor, or both,—and this, as we understand the argument, regardless of the consequences to the contractor or sub-contractor. This precise question has. never been before us for consideration or decision. Decisions by other courts in this State, or courts in other States, necessarily are not controlling and need not be considered in discussing the proper construction of this statute.

Section 5 of the statute provides that the contractor shall give the owner, and the owner shall require before paying to said contractor or his order any money, a written statement under oath, giving “the names of all parties furnishing materials and labor, and of the amounts due or to become due each.” (Hurd’s Stat. 1913, p. 1561.) Section 22 provides for the giving to the owner or contractor of a statement by the sub-contractor of the labor or material furnished by him. Section 24 states how a subcontractor or party furnishing labor or material may cause written notice of his claim and the amount due to be served on the owner or his representative, “provided, such notice shall not be' necessary when the sworn statement of the contractor or sub-contractor provided for herein shall serve to give the owner notice of the amount due and to whom due, but where such statement is incorrect as to the amount, the sub-contractor or material-man named shall be' protected to the extent of the amount named therein as due or to become due to him,” etc. Section 32 provides that no payments by the owner shall be regarded as rightfully made, as against the sub-contractor, laborer or party furnishing labor or materials, if made by the owner without exercising and enforcing the rights conferred upon him in sections 5 and 22. While there are other provisions of the statute which show the general plan and intention of the legislature, these are the chief sections that bear on the question here under consideration.

Under a mechanic’s lien statute very similar in its provisions to the ones heretofore quoted, this court held in Keeley Brewing Co. v. Decorating Co. 194 Ill. 580, that the lien of á sub-contractor being a direct lien, its existence did not depend upon the existence or non-existence of a contractor’s lien, but that the notice by the sub-contractor under section 25 was not necessary where the sworn statement of the contractor made under section 5 gave the owner notice of the amount due or to become due. Practically to the same effect, under an earlier mechanic’s lien statute containing practically the same provisions, was the holding of this court in Shaw v. Chicago Sash, Door and Blind Co. 144 Ill. 520. In the recent decision of Knickerbocker Ice Co. v. Halsey Bros. Co. 262 Ill. 241, this court, in construing said section 5 of the Mechanic’s Lien statute, held that said section did not limit a contractor to one sworn statement to be made to the owner; that the conditions of the contract may change between the time of payments; that “new sub-contracts may have been entered into in the meantime or payments may have been made upon sub-contracts existing at the time the'first payment was made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Contractors' Ready-Mix, Inc. v. Earl Given Construction Co.
611 N.E.2d 529 (Appellate Court of Illinois, 1993)
Decatur Bridge Co. v. Standart
208 Ill. App. 592 (Appellate Court of Illinois, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
268 Ill. 463, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berkshire-warehouse-co-v-hilger-co-ill-1915.