Sanaghan v. Lawndale National Bank

232 N.E.2d 546, 90 Ill. App. 2d 254, 1967 Ill. App. LEXIS 1457
CourtAppellate Court of Illinois
DecidedNovember 24, 1967
DocketGen. 51,090
StatusPublished
Cited by18 cases

This text of 232 N.E.2d 546 (Sanaghan v. Lawndale National Bank) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanaghan v. Lawndale National Bank, 232 N.E.2d 546, 90 Ill. App. 2d 254, 1967 Ill. App. LEXIS 1457 (Ill. Ct. App. 1967).

Opinion

MR. JUSTICE SCHWARTZ

delivered the opinion of the court.

This is an appeal from a summary decree dismissing a counterclaim for the enforcement of a mechanic’s lien by Sammy Grant, doing business as Sammy Grant Drywall Company, against property owned by the Lawndale National Bank (Lawndale) as trustee. The issue presented is whether a party may under the provisions of the Mechanics’ Lien Act enforce a lien for labor or material furnished to a subcontractor, notwithstanding the fact that the subcontractor had procured payment in full of the contract price by means of a false affidavit. Ill Rev Stats, c 82, §§ 1-39 (1965).

The Lawndale National Bank as trustee entered into a contract with Kavanagh Construction Company, Inc., as general contractor to erect a large apartment building on land owned by it in Harvey, Illinois. To finance the construction, Lawndale mortgaged the premises to Investors Savings and Loan Association (Investors). Investors, following customary practice in the construction industry, withheld the mortgage proceeds and disbursed them on behalf of the owner as construction progressed on the building.

On April 30, 1963, Kavanagh submitted to Investors a sworn statement setting forth the names of all subcontractors and the amounts due or to become due to them. The statement showed that the plastering contract (for which drywall was later substituted) had been let to Lucky Star Decorating, the trade name of one Keith Mel-horn, for $6,800. On May 8, 1963, Sammy Grant entered into an oral subcontract with Melhorn, by the terms of which Grant was to furnish drywall construction, labor, materials and tape for the sum of $6,800.

On June 24, 1963, while construction was progressing, a partial payment was made by Investors to Kavanagh, which included $2,800 on account of the drywall contract. Supporting this payout was a partial waiver of lien executed by Melhorn, acknowledging receipt of this amount. On August 1, 1963, Kavanagh requested further progress payments and authorized a final payment to Melhorn in the sum of $4,000. Supporting this payout was the sworn statement of Melhorn setting forth that all material for the performance of the contract had been furnished by Dolton Gypsum Supplies, Inc. and that all labor had been furnished by Lucky Star Decorating. This statement was accompanied by final waivers of lien from both Lucky Star and Dolton Gypsum. Relying upon the sworn statements and the waivers of lien, Investors paid $4,000, completing payments on the drywall contract.

The sworn statement of Melhorn was false in that it omitted the claim of the appellant Sammy Grant. On October 1, 1963, two months after payment had been made to Melhorn, Sammy Grant served on Lawndale, Investors and Kavanagh notice of his claim for lien, stating he completed work on the premises on September 16, 1963, and that there was a balance of $2,800 due him on his agreement with Melhorn. Payment was refused on the ground that full payment of the drywall contract had been made to Melhorn and that prior to the receipt of the notice of Grant’s claim, full payment had been made to the general contractor of all moneys due for construction of the building.

Grant’s claim for lien is not contractual, but rests entirely on the statute. The statute is comprehensive. It defines the rights and responsibilities of parties generally involved in construction contracts — the owner and his disbursing agent on one side and, on the other, in any project of considerable size, the general contractor, subcontractors and the more numerous class of those performing labor and providing material for the subcontractors. Many or all of these subcontractors and sub-subcontractors may be unknown to and undiscoverable by the owner. The statute recognizes this. Thus section 5 provides that the owner must demand a sworn statement from the general contractor, setting forth the names of all parties furnishing labor and materials and the amounts due or to become due to each, before any payment is made to the contractor. 1 Section 22 provides that any subcontractor shall, as often as requested by the owner, provide a statement of the persons furnishing labor and materials to him and how much is due or to become due to them. 2 Section 32 provides that no payment to the contractor shall be regarded as rightfully made as against subcontractors and parties furnishing labor or materials, if made by the owner without exercising the rights and powers conferred upon him by sections 5 and 22. If the subcontractors or persons furnishing labor or materials to them are not satisfied to rely upon the protection afforded by the foregoing sections, then section 24 authorizes direct notice to the owner at anytime after the making of the subcontract and requires such direct notice within 60 days after completion of the work. The sub and sub-subcontractors are given the opportunity to bring their claims to the attention of the owners — that is, by relying on those above them to give notice in the statements required by sections 5 and 22 or by direct notice.

On the other hand, the owner who complies with the provisions of the statute is protected. Section 21 provides that the owner shall not be required to pay a greater amount for the complete building than provided in the original contract, unless payments are made to the contractor in violation of the rights of other parties to be benefitted by the act. Section 27 provides that the owner shall not be liable to a laborer or subcontractor whose name is omitted from the statements required by sections 5 and 22 unless previous to his payment to the contractor, he is notified of such claim.

The appellant Grant, a sub-subcontractor, as disclosed by his pleadings and affidavit in opposition to the motion for a summary decree, made his contract with Mel-horn, not the general contractor, and falls within the class of those providing labor or materials to a subcontractor— the class most remote from the owner. His rights to a lien arise by virtue of section 22. The statement required by this section was requested by Investors acting for the owner and false though it was, it was presented by Melhorn prior to final payment of the drywall contract.

Appellant argues that Lawndale and Investors failed to comply with section 5 of the statute by not requiring from the general contractor a current sworn statement prior to making final payment on the drywall contract. He contends that a question of fact exists as to whether the general contractor knew or should have known that Sammy Grant was performing work on the premises, that this knowledge was chargeable to the owner, and that in any event if the general contractor knew of his presence and if the owner had required a current sworn statement, knowledge of his claim would have come to the attention of the owner. He does not contend that either Lawndale or Investors had actual knowledge of his claim prior to final payment on the contract. There is nothing in the Mechanics’ Lien Act which can be construed as providing that mere presence of a workman on a job will constitute notice to the owner on which a mechanic’s lien may be based. Nor can the knowledge of the contractor be imputed to the owner. They are essentially adverse parties under the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. JB Architecture Group, Inc.
2025 IL App (2d) 250143-U (Appellate Court of Illinois, 2025)
Pyramid Development, LLC v. Dukane Precast, Inc.
2014 IL App (2d) 131131 (Appellate Court of Illinois, 2014)
Gerdau Ameristeel US, Inc. v. Broeren Russo Construction, Inc.
2013 IL App (4th) 120547 (Appellate Court of Illinois, 2013)
Lazar Bros. Trucking, Inc. v. a & B Excavating, Inc.
365 Ill. App. 3d 559 (Appellate Court of Illinois, 2006)
Lazar Bros. Trucking v. a & B Excavating
850 N.E.2d 215 (Appellate Court of Illinois, 2006)
Bricks, Inc. v. C & F DEVELOPERS, INC.
836 N.E.2d 743 (Appellate Court of Illinois, 2005)
Bricks, Inc. v. C&F Developers, Inc.
Appellate Court of Illinois, 2005
Season Comfort Corp. v. Ben A. Borenstein Co.
655 N.E.2d 1065 (Appellate Court of Illinois, 1995)
Contractors' Ready-Mix, Inc. v. Earl Given Construction Co.
611 N.E.2d 529 (Appellate Court of Illinois, 1993)
Hill Behan Lumber Co. v. Irving Federal Savings & Loan Ass'n
459 N.E.2d 1066 (Appellate Court of Illinois, 1984)
Luczak Brothers, Inc. v. Generes
451 N.E.2d 1267 (Appellate Court of Illinois, 1983)
State v. Bennett
383 So. 2d 1236 (Supreme Court of Louisiana, 1980)
McCann Construction Specialties Co. v. Alan Construction Co.
12 Ill. App. 3d 206 (Appellate Court of Illinois, 1973)
McCANN CONST. SPECIALTIES CO. v. ALAN CONST. CO.
298 N.E.2d 222 (Appellate Court of Illinois, 1973)
Capital Plumbing & Heating Co. v. Snyder
275 N.E.2d 663 (Appellate Court of Illinois, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
232 N.E.2d 546, 90 Ill. App. 2d 254, 1967 Ill. App. LEXIS 1457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanaghan-v-lawndale-national-bank-illappct-1967.