Weather-Tite v. University of St. Francis

CourtAppellate Court of Illinois
DecidedJune 16, 2008
Docket3-07-0402, 3-07-0462 cons. Rel
StatusPublished

This text of Weather-Tite v. University of St. Francis (Weather-Tite v. University of St. Francis) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weather-Tite v. University of St. Francis, (Ill. Ct. App. 2008).

Opinion

No. 3-07-0402 consolidated with No. 3-07-0462 _________________________________________________________________ Filed June 16, 2008 IN THE

APPELLATE COURT OF ILLINOIS

THIRD DISTRICT

A.D., 2008

WEATHER-TITE, INC., an ) Appeal from the Circuit Court ILLINOIS CORPORATION, ) of the 12th Judicial Circuit ) Will County, Illinois Plaintiff, ) ) v. ) ) UNIVERSITY OF ST. FRANCIS, ) STONITSCH CONSTRUCTION, INC., ) QUAKER WINDOW PRODUCTS ) COMPANY, EXCEL ELECTRIC, INC.,) LAFORCE, INC., SCOTT KARLI ) d/b/a SK SALES, MIDWEST ) ARCHITECTURAL GLASS, INC., ) UNKNOWN OWNERS AND NON-RECORD ) CLAIMANTS, ) ) Defendants. ) ______________________________) No. 06-CH-1131 ) 06-CH-1135 EXCEL ELECTRIC, INC., an ) ILLINOIS CORPORATION, ) ) Counter-Plaintiff- ) Appellant, ) ) vs. ) ) UNIVERSITY OF ST. FRANCIS, ) STONITSCH CONSTRUCTION, INC., ) WEATHER-TITE, INC., QUAKER ) WINDOW PRODUCTS COMPANY, ) LAFORCE, INC., SCOTT KARLI ) d/b/a SK SALES, MIDWEST ) ARCHITECTURAL GLASS, INC., ) UNKNOWN OWNERS AND NON-RECORD ) CLAIMANTS, ) ) Honorable Counter-Defendants- ) Bobbie Petrungaro Appellees. ) Judge Presiding. _________________________________________________________________

JUSTICE LYTTON delivered the Opinion of the court: _________________________________________________________________

Excel Electric, Inc. filed a complaint to foreclose a

mechanic’s lien against University of St. Francis. St. Francis

filed a motion for summary judgment, and Excel filed a cross-motion

for summary judgment. The trial court granted University’s motion

and denied Excel’s motion. We reverse and remand.

BACKGROUND

In March 2005, St. Francis hired Stonitsch Construction, Inc.

to be its general contractor on a project to renovate a residence

hall. Stonitsch hired many subcontractors to complete the

renovation project, including Excel Electric, Inc.. According to

the contract between Stonitsch and Excel, Excel was to provide

electrical labor, materials and services for the project. From May

2005 to November 2005, Excel provided the necessary labor,

materials and services to Stonitsch.

On four occasions during the course of the renovation project,

Stonitsch submitted documents to St. Francis entitled "Application

and Certificate for Payments." In these documents, Stonitsch

requested payment from St. Francis in the following amounts: (1)

$123,703.20 on May 26, 2005, (2) $532,475.10 on June 16, 2005, (3)

$1,204,333.10 on June 15, 2005, and (4) $1,081,999.69 on August 18,

2005. Each of the payment certificates listed Excel as the

electrical subcontractor and showed the amount that it was due.

St. Francis provided Stonitsch payments in the amounts requested in

each "Application and Certificate for Payments." After St. Francis

paid Stonitsch, Stonitsch paid Excel the amount it was due as set

forth in each payment certificate.

2 Stonitsch completed its renovation work in November 2005. On

December 6, 2005, Stonitsch issued its final "Application and

Certificate for Payments" to University. According to that

document, St. Francis owed Stonitsch $458,237.56, of which

$130,948.48 was due Excel. St. Francis made its final payment of

$458,237.56 on January 20, 2006. That amount was wire transferred

into Stonitsch’s account at Harris Bank. Upon receiving the

payment, Harris Bank exercised its right of set off and applied the

funds received to partially satisfy a debt Stonitsch owed Harris.

Excel received no payment from Stonitsch with respect to the final

payment certificate.

On February 22, 2006, Excel served a Notice and Claim for

Mechanic’s Lien on University, claiming it was owed $140,547.09 for

its work on the renovation project. Other subcontractors, including

Weather Tite, Inc., served St. Francis with notices and claims for

mechanics’ liens.

In May 2006, Weather Tite filed a complaint for foreclosure of

its mechanic’s lien. One month later, Excel filed a counter-

complaint to foreclose its mechanic’s lien. St. Francis filed a

motion for summary judgment, arguing that Excel did not have an

enforceable mechanic’s lien. Excel filed a cross-motion for

summary judgment, arguing that it had a valid and enforceable

mechanic’s lien against St. Francis in the amount of $130,948.48.

The trial court entered an order granting University’s motion

for summary judgment and denied Excel’s cross-motion for summary

judgment. In its order, the trial court relied on Luczak Bros.,

Inc. v. Generes, 116 Ill. App. 3d 286, 451 N.E.2d 1267 (1983),

3 which "seemed factually similar to this case." The trial court

summarized that case as follows: "[T]he subcontractor was entitled

to a lien only in the amount show to become due on the last

statement for which payment was made and the subcontractor must

look to the contractor for payment." (Emphasis by trial court),

citing Luczak, 116 Ill. App. 3d at 303, 4512 N.E.2d at 1281. The

trial court concluded that because St. Francis did not receive

Excel’s notice of lien and claim until after it made final payment

to Stonitsch, Excel did not have a valid and enforceable mechanic’s

lien against St. Francis and must look for Stonitsch for payment.

ANALYSIS

Excel argues that it is entitled to a lien of $130,948.48

because that amount was shown to be due Excel in the final payment

certificate Stonitsch provided to St. Francis. St. Francis

responds that Excel is not entitled to a lien because Excel did not

serve its lien notice until after St. Francis made its final

payment to Stonitsch and all work on the project was complete.

The purpose of the Mechanics Lien Act (Act), 770 ILCS 60/1 et

seq. (West 2004), is to protect those who in good faith furnish

material or labor for the construction of a building. State Bank

of Lake Zurich v. Winnetka Bank, 245 Ill. App. 3d 984, 994, 614

N.E.2d 862, 869 (1993). The Act attempts to balance the rights and

duties of owners, contractors and subcontractors. Alliance Steel,

Inc. v. Piercy, 277 Ill. App. 3d 632, 635, 660 N.E.2d 1341, 1343

(1996).

Under section 5 of the Act, it is the owner’s duty, before

making any payments, to require the general contractor to provide

4 a sworn written statement listing the subcontractors and the

amounts due or to become due to each one. 770 ILCS 60/5(a) (West

2004). If a subcontractor’s name is omitted from the contractor’s

statement or the subcontractor is owed an amount different from

what is provided in the statement, the subcontractor must give the

owner written notice of its claim no later than 90 days after its

completion of the contract. 770 ILCS 60/24(a) (West 2004).

When an owner is notified of a subcontractor’s claim, he must

retain from any money due the contractor an amount sufficient to

pay the subcontractor. 770 ILCS 60/27 (West 2004); see

Knickerbocker Ice Co. v. Halsey Bros. Co, 262 Ill. 241, 246, 104

N.E. 665 (1941). If an owner pays a contractor and does not retain

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alliance Steel, Inc. v. Piercy
660 N.E.2d 1341 (Appellate Court of Illinois, 1996)
Contractors' Ready-Mix, Inc. v. Earl Given Construction Co.
611 N.E.2d 529 (Appellate Court of Illinois, 1993)
State Bank of Lake Zurich v. Winnetka Bank
614 N.E.2d 862 (Appellate Court of Illinois, 1993)
Capital Plumbing & Heating Co. v. Snyder
275 N.E.2d 663 (Appellate Court of Illinois, 1971)
Luczak Brothers, Inc. v. Generes
451 N.E.2d 1267 (Appellate Court of Illinois, 1983)
Butler & McCracken v. Gain
21 N.E. 350 (Illinois Supreme Court, 1889)
Knickerbocker Ice Co. v. Halsey Bros.
104 N.E. 665 (Illinois Supreme Court, 1914)
Gilbert v. Croshaw
178 Ill. App. 10 (Appellate Court of Illinois, 1913)
Hall v. Harris
242 Ill. App. 315 (Appellate Court of Illinois, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
Weather-Tite v. University of St. Francis, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weather-tite-v-university-of-st-francis-illappct-2008.