Brady Brick & Supply Co. v. Lotito

356 N.E.2d 1126, 43 Ill. App. 3d 69, 1 Ill. Dec. 844, 1976 Ill. App. LEXIS 3260
CourtAppellate Court of Illinois
DecidedOctober 26, 1976
Docket75-534
StatusPublished
Cited by24 cases

This text of 356 N.E.2d 1126 (Brady Brick & Supply Co. v. Lotito) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brady Brick & Supply Co. v. Lotito, 356 N.E.2d 1126, 43 Ill. App. 3d 69, 1 Ill. Dec. 844, 1976 Ill. App. LEXIS 3260 (Ill. Ct. App. 1976).

Opinion

Mr. JUSTICE DIXON

delivered the opinion of the court:

A suit was brought by Brady Brick & Supply Co., supplier of 31,560 white bark Norman bricks and other material, to foreclose its mechanic’s hen against certain real estate in West Dundee owned by the National Bank of Albany Park in Chicago, as Trustee. Anthony N. Chirikos and Dolores Chirikos were the beneficial owners of the trust and are also defendants.

A separate suit was brought by Thomas Lotito and Brian Christiansen, partners doing business as Lakeview Masonry, to enforce their mechanic’s hen for labor and materials furnished to and incorporated into the same real estate.

The two cases were consolidated and after trial the Circuit Court of Kane County entered judgment in each case in favor of the plaintiffs and against the defendant owners who take this appeal.

The bricks furnished by Brady were ordered by Anthony Chirikos in March or April of 1974. Previous to this time Chirikos had built two other buildings in his Tonde Shopping Center using the same type of brick but laid by a mason by name of Schmidgall. In the case of the prior two buildings Chirikos had ordered the bricks, and the bill was sent by Brady to the mason who paid the bill. The testimony here was that because of a brick shortage Chirikos agreed that Brady should preorder the bricks and deliver them to the job site but that they would be invoiced to the successful bidder which would be either Schmidgall or Lakeview. Brady delivered bricks of a value of *5,003.87 by May 17. Other building materials were also supplied by Brady.

Lakeview submitted a written proposal to Chirikos in which Lakeview agreed “to furnish all material and perform all labor necessary” to construct the third building in the Tonde Shopping Center. The proposal included a clause that “payments to be made as job progresses.” Chirikos accepted the proposal and a binding contract was made May 8, 1974.

Brady sent a bill to Lakeview for the bricks on or about May 30,1974, and again on June 30,1974. It was conceded by Lotito that if Chirikos had paid Lakeview, Lakeview would have paid Brady’s bill for the bricks.

Brady was not paid, however, and Brady proceeded to perfect its mechanic’s lien rights against the property by following the steps required by the Mechanics’ Liens Act (Ill. Rev. Stat. 1973, ch. 82, pars. 1-39).

Brady’s complaint to foreclose its mechanic’s lien was filed November 6,1974. The owners’ answer admits that the bricks and building materials and supplies furnished by Brady constitute a permanent and valuable improvement on the real estate in question. There was testimony that the bricks and materials furnished by Brady and as installed enhance the value of the owners’ real estate by more than *5,000.

Unknown to Brady, Chirikos and Lakeview had a disagreement. Lakeview had begun the job in May and after about a month, on June 14, 1974, requested a first progress payment of *10,000 which payment was made about July 1,1974. On July 7 Lakeview requested a second progress payment of *7,000 which was not paid. Chirikos contended that there was not sufficient work done to warrant the payment and that it would not be approved by his lending institution. Lakeview by July 1 had paid out *7,836 in wages for labor on the job and had paid two material companies, Acme Brick & Supply Co. *907.73 and Valley Block Company *918.54, for material (a total pay out of *9,662.27). Acrimonious conversations between Lotito and Chirikos ensued. Chirikos refused to pay any amount. Lakeview walked off the job and refused to return only if the *7,000 was escrowed. About two weeks later Chirikos found another mason to complete the building and entered into a written contract on August 28, 1974 to complete the job for *9,500. Lakeview presented testimony that it had laid 25,074 bricks from of a total of 32-34,000. Chirikos’ witness did not challenge that statement but testified that he did 50% of the work since the last work was time consuming.

At the conclusion of all the evidence the trial judge found for Brady in the amount of *5,705.16 against all defendants except Lakeview, and in favor of Lakeview and against all defendants in the amount of *1,544.84.

I

The first contention on appeal is that the trial court erred in refusing to grant defendants’ motion for judgment at the close of plaintiffs’ cases. After denial of the motions defendants proceeded to adduce evidence in support of their defense.

Section 64(3) of the Civil Practice Act (Ill. Rev. Stat. 1973, ch. 110, par. 64(3)) provides for motions for a finding, judgment or decree at the close of plaintiff’s case in nonjury matters. The last sentence of the Act is as follows:

“If the ruling on the motion is adverse to the defendant he may proceed to adduce evidence in support of his defense, in which event the motion is waived.” (Emphasis supplied.)

Defendants introduced evidence after denial of their motion to dismiss. Introduction of such evidence is deemed to be a withdrawal or waiver of the motion to dismiss. (Havill v. Darch, 320 Ill. App. 667, 670.) The issue will not, therefore, be considered on appeal.

II

It is not contested that Brady Brick in establishing their right to a lien have complied strictly with all of the statutory requirements. Defendants argue that the evidence in support of Brady’s claim establishes that Lakeview is obligated to pay the material charges, that all billings were to Lakeview, the written agreement between Lakeview and the defendants provides that Lakeview pay for the material, the admission of Lotito that he would pay the Brady bill by mid-July and that if the judgments entered are permitted to stand defendants will have paid *26,750 to construct a building which should have only cost *21,000. The argument totally ignores the fact that this is a mechanic’s hen case. Chirikos admits that the bricks were furnished by Brady which were incorporated into and constitute an enhancement of the value of his building. He admits that the bricks had not been paid for and that the price was as agreed but says that Lakeview. owes the bill. It was precisely for this type of situation that the Mechanics’ Liens Act was enacted, to protect materialmen, who in good faith furnish materials for the construction of a building and to allow the materialman to collect his bill from the owner via a mechanic’s hen foreclosure suit, when the contractor, subcontractor, and or owner fail to pay the materialman. Gunther v. O’Brien Brothers Construction Co., 293 Ill. App. 28; Miles, The Mechanic’s Lien, 48 Ill. B. J. 736 (1960).

The Brady complaint and the defendants’ answer thereto proceeded on the theory that Brady was a subcontractor (rather than an original contractor) who furnished material to Lakeview for use on the owners’ property.

A person who furnishes material to an original contractor and who is sometimes called a materialman is a subcontractor in the truest sense. Decatur Bridge Co. v. Standart, 208 Ill. App. 592, 595.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GX Chicago, LLC v. Galaxy Environmental, Inc.
2015 IL App (1st) 133624 (Appellate Court of Illinois, 2015)
BX Chicago, LLC v. Galaxy Environmental, Inc.
2015 IL App (1st) 133624 (Appellate Court of Illinois, 2015)
Gerdau Ameristeel US, Inc. v. Broeren Russo Construction, Inc.
2013 IL App (4th) 120547 (Appellate Court of Illinois, 2013)
Bricks, Inc. v. C & F DEVELOPERS, INC.
836 N.E.2d 743 (Appellate Court of Illinois, 2005)
Bricks, Inc. v. C&F Developers, Inc.
Appellate Court of Illinois, 2005
Struebing Construction Co. v. Golub-Lake Shore Place Corp.
666 N.E.2d 846 (Appellate Court of Illinois, 1996)
Contract Development Corp. v. Beck
627 N.E.2d 760 (Appellate Court of Illinois, 1994)
A.Y. McDonald Manufacturing Co. v. State Farm Mutual Automobile Insurance
587 N.E.2d 623 (Appellate Court of Illinois, 1992)
Malesa v. Royal Harbour Management Corp.
543 N.E.2d 591 (Appellate Court of Illinois, 1989)
Fireman's Fund Mortgage Corp. v. Zollicoffer
719 F. Supp. 650 (N.D. Illinois, 1989)
J&W Allen Construction Co. v. Kramer
41 Ill. Ct. Cl. 133 (Court of Claims of Illinois, 1989)
Berra v. Papin Builders, Inc.
706 S.W.2d 70 (Missouri Court of Appeals, 1986)
Swansea Concrete Products, Inc. v. Distler
467 N.E.2d 388 (Appellate Court of Illinois, 1984)
Luczak Brothers, Inc. v. Generes
451 N.E.2d 1267 (Appellate Court of Illinois, 1983)
F. E. Holmes & Son Construction Co. v. Gualdoni Electric Service, Inc.
435 N.E.2d 724 (Appellate Court of Illinois, 1982)
Tennessee Asphalt Co. v. Purcell Enterprises, Inc.
631 S.W.2d 439 (Court of Appeals of Tennessee, 1982)
B & C Electric, Inc. v. Pullman Bank & Trust Co.
421 N.E.2d 206 (Appellate Court of Illinois, 1981)
Hemenover v. DePatis
408 N.E.2d 387 (Appellate Court of Illinois, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
356 N.E.2d 1126, 43 Ill. App. 3d 69, 1 Ill. Dec. 844, 1976 Ill. App. LEXIS 3260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brady-brick-supply-co-v-lotito-illappct-1976.