Gunther v. O'Brien Bros. Constr. Co.

12 N.E.2d 23, 293 Ill. App. 28, 1937 Ill. App. LEXIS 356
CourtAppellate Court of Illinois
DecidedDecember 2, 1937
DocketGen. No. 9,163
StatusPublished
Cited by6 cases

This text of 12 N.E.2d 23 (Gunther v. O'Brien Bros. Constr. Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gunther v. O'Brien Bros. Constr. Co., 12 N.E.2d 23, 293 Ill. App. 28, 1937 Ill. App. LEXIS 356 (Ill. Ct. App. 1937).

Opinion

Mr. Justice Wolfe

delivered the opinion of the court.

Sometime prior to May 19, 1930, the appellant, the Galesburg Sanitary District, a municipal corporation, in Knox county, Illinois, was organized pursuant to the statutes of the State of Illinois, for the creation of a sanitary district. The O’Brien Brothers Construction Company was an Illinois corporation, engaged in the contracting and construction business. On May 19, 1930, the Sanitary District and O’Brien Brothers entered into a written contract by which the O’Brien Brothers agreed to construct certain ditches, drains, sewers, bridges, and other related construction work for the Sanitary District. O’Brien Brothers performed a considerable portion of the work called for by the said contract. On July 28,1931, 0 ’Brien Brothers defaulted and ceased to do any further work upon the contract. In accordance with the contract, notice of the default of the O’Brien Brothers was given by the proper parties to all persons and companies concerned. All necessary resolutions and ordinances were properly passed by the Sanitary District in connection with such default. Subsequent to said default and prior to reletting a formal contract for the completion of the work, the Sanitary District paid ont, on items of expense, for labor, etc., an amount aggregating- $14,424.44, which the court found was reasonable in amount and necessary for the completion of the work according to the contract. After the default of 0 ’Brien Brothers, the Sanitary District took necessary and appropriate steps, by means of advertising for bids, the passing of ordinances, etc., and on December 1, -1931, entered into a contract with Alexander & Rep ass Brothers for the completion of the work left unfinished by the 0 ’Brien Brothers. The total payments called for by the 0 ’Brien contract was $692,230.62. The total payments made to O’Brien Brothers for work done and materials furnished according to the contract, prior to the default, was $494,293.37. The total paid to Alexander & Repass Brothers under and pursuant to their contract for the completion of the work was $144,900.

On January 30, 1931, John C. Coberg served a written notice upon the trustees of the Sanitary District, that O’Brien Brothers Construction Company was indebted to him in the sum of $4,981.90; that he had furnished lumber and machinery to said O ’Brien Brothers, which was used in the construction of the sewer, etc., of the Sanitary District, and that he claimed a lien for the amount of such indebtedness upon any money, bonds, or warrants due, or to become due, to O’Brien Brothers from said Sanitary District on account of said contract between O’Brien Brothers and said Sanitary District.

Between January 30,1931 and December 1,1931, numerous other persons, who claimed they had furnished materials for the construction of the sewers, etc., or had worked for the O ’Brien Brothers Company on said sewer project, had not been paid for their materials and labors, served notice upon the Sanitary District that they claimed a lien on any money that was due or might become due from the Sanitary District to O’Brien Brothers on account of said contract. Later on, numerous other claims were filed with the Sanitary District. Each stated that they had a lien on the unexpended fund of the Sanitary District by reason of the claimants having furnished material, insurance, labor, etc., to the 0 ’Brien Brothers for use in said sewer construction.

On January 20,1932, H. H. Gunther et al., filed a bill of complaint in the circuit court of Knox county, setting forth that the Galesburg Sanitary District, a municipal corporation in Knox county, had entered into a contract with the O’Brien Brothers for the construction of a sewer system for said Sanitary District, and that each of the complainants had furnished to the O’Brien Brothers Construction Company work, materials, or service of some kind which had gone into the construction of said sewer system; that each of the complainants is asking to have the amount due them, respectively, made a lien on the funds in the hands of the Sanitary District, and asks that the same may be ordered paid in the amount found to be due each of them, respectively. Other lien claimants filed answers to the bill of complaint and were given leave to intervene, setting forth facts and circumstances upon which they claimed to have a lien on the funds in the hands of the Sanitary District, which were, or might come, due the 0 ’Brien Brothers.

The Sanitary District filed its answer to all petitions for liens, in which it neither admitted nor denied many allegations of the bill, and neither admitted nor denied the justness of the claim of the separate claimants. No quéstion is raised in this appeal in regard to the pleadings in the case, so it seems unnecessary to state anything further in regard to them.

The contract between the Sanitary. District and O’Brien Brothers provided that payments were to be made as work progressed, that is, 85 per cent of the value of the work done and material furnished was to be paid to the 0 ’Brien Brothers Company, and the remaining 15 per cent was to be held by the Sanitary District and was not due and payable until the completion of the work and final acceptance by the Sanitary District. The 15 per cent held by the Sanitary District, which had not been paid to the 0 ’Brien Brothers Company, amounted to $87,288.41.

The case was tried before Judges Loren Murphy, Biley E. Stevens, and George C. Hillyer, the judges of the Ninth Judicial Circuit, sitting in banc. The court found the issues in favor of the complainants and entered a decree, part of which is as follows: “And the Court finds and decrees that the Sanitary District is not entitled to credit for any part of said 15% fund expended in protecting or preserving the work, or in completing said work, until all claims for - labor and material allowed in the former decree or filed with the Sanitary District and may be hereafter allowed, are fully paid; and the Sanitary District had no right to use any part of said 15% fund for either of said purposes until all of said liens had been paid in full; that the lien claimants whose claims have been heretofore or are herein allowed, or filed and may be hereafter allowed, have a first and prior lien upon said 15% fund amounting to $87,288.41, to the extent of their several liens allowed or to be allowed, and that no part of said fund could, or can, be legally used or applied for any other purpose until all of said liens, together with Court costs, have been paid.”

The appellant, in its brief, has assigned seven reasons why the judgment of the lower court should be reversed, but the following paragraphs of the brief, which relate to the part of the decree of the court above quoted, states its position in a concise manner: “That holding of the Court is the nub of this case, and presents the main question for review. In making the aforesaid holding, the Court overruled the Master in Chancery, who, as above stated, found and held the amounts expended by the Sanitary District for the protection and completion of the work to be proper deductions and allowed the Sanitary District credit therefor.

“As indicated, there is no controversy about the facts. After the completion of the construction work, the Sanitary District had left as due the contractor, the sum of $38,612.21, which it paid to the Master in Chancery under order of court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
Brady Brick & Supply Co. v. Lotito
356 N.E.2d 1126 (Appellate Court of Illinois, 1976)
Armco Steel Corp. v. La Salle National Bank
335 N.E.2d 93 (Appellate Court of Illinois, 1975)
Miller v. Reed
302 N.E.2d 131 (Appellate Court of Illinois, 1973)
Wanzer v. Smorgas-Brickan Developers, Inc.
264 N.E.2d 435 (Appellate Court of Illinois, 1970)
Suddarth v. Rosen
224 N.E.2d 602 (Appellate Court of Illinois, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
12 N.E.2d 23, 293 Ill. App. 28, 1937 Ill. App. LEXIS 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gunther-v-obrien-bros-constr-co-illappct-1937.