Granite City Lime & Cement Co. v. Board of Education

203 Ill. App. 134, 1916 Ill. App. LEXIS 1058
CourtAppellate Court of Illinois
DecidedNovember 13, 1916
StatusPublished
Cited by12 cases

This text of 203 Ill. App. 134 (Granite City Lime & Cement Co. v. Board of Education) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Granite City Lime & Cement Co. v. Board of Education, 203 Ill. App. 134, 1916 Ill. App. LEXIS 1058 (Ill. Ct. App. 1916).

Opinion

Mr. Justice McBride

delivered the opinion of the court.

A decree was rendered in favor of the complainant against the defendants in the Circuit Court of Madison county, to reverse which the defendant J. R. Beale prosecutes this appeal.

It appears from the record in this case that on May 2, 1913, J. R. Beale entered into a contract with the Board of Education of School District No. 126 Union, Township 3, Ranges 9 and 10, for the erection and completion of a high school building. That thereafter J. R. Beale entered into a subcontract with the defendants H. S. Mettlen & Company to furnish the building material and do the brickwork upon said building for an expressed consideration of $10,500, to be paid for as the work progressed, and payments were to be based upon the estimates of the architect and be made to the amount of eighty-five per cent, of such estimates. At the time that Mettlen & Company were endeavoring to secure this subcontract, they obtained prices of building material from the appellee upon which prices it appears that their bid was partly based. After Mettlen & Company had been awarded the subcontract for doing the brickwork, they then placed an order with the appellees for the necessary brick and other building materials, and in this order was included the prices theretofore quoted by appellees to them. At the time of the making of the contract between Beale and Mettlen & Company, it was agreed that Mettlen & Company should give to Beale a bond, the exact nature and condition of this bond does not appear from the evidence, but Mettlen & Company were unable to give the bond and were unable to prosecute the work upon the payment of eighty-five per cent, of the estimated prices; that they would require more money than that per cent, would bring to them. Thereupon an arrangement was made between Beale and Mettlen & Company that Beale was to take care of all bills for material furnished and put in the building and would give a check upon Saturday for the amount of labor performed during that week. Beale denies that he undertook absolutely to pay all bills, but says that he had an understanding with Mettlen that he would pay the men for their labor and would pay for materials upon orders from Mettlen & Company out of what was due them. As the building progressed, payments were made by Beale to the men for their labor and sums were paid upon the building material furnished from time to time, upon the order of Mettlen & Company. When the building was completed there was a balance due appellee of $1,212.05 for materials furnished and used in the erection of this building. It also appears from the testimony of appellees’ witnesses that after Mettlen & Company had placed their order with appellees and before any of the building máterial had been delivered, that the appellees learned that Mettlen & Company had failed to give a bond, as they had agreed to do, and thereupon Mettlen & Company called' upon Beale, and, as appellees claim, asked him what protection he would have if they would quit before the building was completed, or the material men would refuse to deliver the material, and he said he would see that the material used was paid for and that he was taking no chances. This is denied by Beale. It further appears that the McEwing & Thomas Clay Products Company furnished building material upon the promise of J. B. Beale to pay for them and that he did from time to time make payments by check upon orders given by Mettlen & Company, and that there is a balance due this corporation of $225.79. Beale denies he made any such an agreement with the McEwing & Thomas Clay Products Company as contended for.

The bill alleges J. B. Beale entered into a contract with the board of education to erect said high school building and that he authorized and employed H. S. Mettlen & Company to do the brickwork and to order the material, and made payments thereon from time to time at the request of Mettlen & Company but that there was a balance due appellees of $1,212.05, which remains unpaid. The bill also alleges that notices were given as required by the statute for the enforcement of liens.

It is contended by counsel for appellant that the appellee was a subcontractor and as such no right of lien existed in its favor under the statute, and maintains that appellee did not furnish materials to the contractor within the meaning of the statute, and that they could have no lien. The statute referred to (J. & A. fí 7161) is as follows: “Any person who shall furnish material, apparatus, fixtures, machinery or labor to any contractor for a public improvement in this State shall have a lien on the money, bonds or warrants due or to become due such contractor for such improvement: Provided, such person shall, before payment or delivery thereof is made to such contractor, notify the officials of the State, county, township, city or municipality, whose duty it is to pay such contractor of his claim by a written notice.”

The cause was referred to the master to take testimony and report conclusions, which was done, and the master recommended that a decree be entered in favor of the appellee and the McEwing & Thomas Clay Products Company for the amounts due them respectively. Exceptions were taken to this report and argued before the court, but the report was sustained and a decree rendered accordingly. It also appears from the evidence that the amount of $1,212.05 remains unpaid and in the hands of the board of education.

The claim of appellee is based upon the fact that before he furnished the materials to Mettlen & Company that Beale agreed with them that he would pay for the materials furnished. This is denied by Beale, but it is testified to by the witnesses A. W. Eir mmeyer, Jr. and A. W. Eisenmeyer, Sr., Louis Buenger and E. C. Mettlen. It appears to us that the chancellor was warranted in finding that Beale did agree before the material was delivered to pay for it and that the material was thereafter furnished and used in the building upon the strength of the promises of Beale. It is insisted by counsel for appellant that even if Beale did promise to pay for the building materials furnished and placed in the building that such promise was within the Statute of Frauds and could not under any consideration be construed as an obligation of Beale’s. If before the delivery of the materials the appellant promised the appellee to pay for such materials, and upon the strength of this promise the materials were delivered to Mettlen & Company, then the undertaking of the appellant was original and appellant was liable upon such original promise. Lusk v. Throop, 189 Ill. 127. “But, where the defendant promises the plaintiff to pay fór goods, which the plaintiff may thereafter deliver to a third person, and which, at the time of the promise, have not been delivered, no debt exists from such third person to the plaintiff, and, hence, the promise of the defendant to pay is an original undertaking, and not merely a promise to pay the debt of another.” Lusk v. Throop, supra. In a determination of a question similar to this one, the Supreme Court has said: “It is next claimed that the court erred in giving instructions for plaintiff. The first instruction merely directed the jury, if they believed-from the evidence that plaintiff and defendant entered into an agreement under which plaintiff agreed to furnish lumber on the order of D. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cirrincione v. Johnson
Appellate Court of Illinois, 1997
In Re Petroleum Piping Contractors, Inc.
211 B.R. 290 (N.D. Indiana, 1997)
WASILEVICH CONST. CO. v. LaSalle Nat. Bank
584 N.E.2d 499 (Appellate Court of Illinois, 1991)
Wasilevich Construction Co. v. La Salle National Bank
222 Ill. App. 3d 927 (Appellate Court of Illinois, 1991)
Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
A. J. Davinroy Plumbing & Heating v. Finis P. Ernest, Inc.
409 N.E.2d 372 (Appellate Court of Illinois, 1980)
Fluor Corporation v. United States
405 F.2d 823 (Ninth Circuit, 1969)
In Re H. G. Prizant & Co.
257 F. Supp. 145 (N.D. Illinois, 1965)
Gunther v. O'Brien Bros. Constr. Co.
12 N.E.2d 23 (Appellate Court of Illinois, 1937)
Duzenbery v. Nimmo
228 Ill. App. 448 (Appellate Court of Illinois, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
203 Ill. App. 134, 1916 Ill. App. LEXIS 1058, Counsel Stack Legal Research, https://law.counselstack.com/opinion/granite-city-lime-cement-co-v-board-of-education-illappct-1916.