Gunther v. O'Brien Bros. Construction Co.

16 N.E.2d 890, 369 Ill. 362
CourtIllinois Supreme Court
DecidedJune 20, 1938
DocketNo. 24612. Reversed and remanded.
StatusPublished
Cited by17 cases

This text of 16 N.E.2d 890 (Gunther v. O'Brien Bros. Construction Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gunther v. O'Brien Bros. Construction Co., 16 N.E.2d 890, 369 Ill. 362 (Ill. 1938).

Opinion

Mr. Justice Farthing

delivered the opinion of the court:

The Appellate Court for the Second District affirmed a decree of the circuit court of Knox county which established mechanics’ liens for materials, machinery, etc., furnished by appellees to the O’Brien Brothers Construction Company while that company was constructing sewers under a contract with the appellant, the Galesburg Sanitary District. The case is here by appeal, following the issuance of a certificate of importance.

Appellees proved claims totaling approximately $63,000, and the circuit court retained jurisdiction over the other claims for the purpose of taking proof as to them. The appellant does not dispute the fact that appellees furnished materials, machinery, etc., to the O’Brien Brothers Construction Company. It admits that they were entitled to liens on a balance of $38,612.21 out of the contract price of $692,230.62, which balance it has paid into court. The contention of appellant is that when the O’Brien Brothers Construction Company made default and ceased work, the district had a right to use the money retained by it out of monthly estimates, (fifteen per cent thereof,) amounting, at the time, to $87,288.41, in completing the project by reletting the contract. The appellees say that $87,288.41 is subject to their liens.

The sewer-construction contract was dated May 19, 1930. Article 11 provided that the construction company should be paid in monthly installments eighty-five per cent of the value of the work properly performed and of materials which were delivered for use therein, and paid for by the company, as “estimated and certified to by the engineer.” These materials were to be properly stored so that they would be free from damage and loss. It was provided, however, the engineer might waive payment for materials, but that payments to the contractor should not relieve it of the duty to furnish all equipment and materials necessary to the prosecution and completion of the work. This article also provided: “The remaining fifteen (15%) per cent will be due and payable upon the completion of the entire work in accordance with the terms hereof and its final inspection by the engineer and the filing with the clerk of the board of trustees of said sanitary district of the engineer’s certificate recommending final acceptanceetc.

Article 12 provided that no certificate given or payment made under the contract, except the final certificate or final payment, should be evidence of the performance of the contract, either wholly or in part, and that no payment should be construed to be an acceptance of defective work or improper materials.

Article 14 authorized the district to retain out of any payment then due or to become due the contractor, sufficient money to indemnify it against mechanics’ lien claims on account of failure of payment by the contractor or any of its subcontractors for work, services, materials, machinery, etc. It also provided that the contractor would, if requested, furnish the district satisfactory written evidence, before payments were made, that there were no mechanics’ or other liens or encumbrances on the premises, or upon any funds due or to become due to the contractor. The contractor agreed to pay the district any amounts it was compelled to pay to discharge liens and to reimburse it for its costs, damages and attorneys’ fees incurred in connection therewith. These provisions, and attempts to enforce them, were not to discharge its bondsmen from liability.

Article 20 empowered the district to forfeit the contract and terminate the employment of the contractor if the district’s engineer certified to its board of trustees that the refusal, neglect or failure of the contractor to comply with the terms of the contract furnished sufficient grounds for such action. The district was empowered to enter upon the premises, to take possession of the materials, machinery, etc., and to employ others to complete the work and to furnish the necessary materials: “In case of such discontinuance of the employment of the contractor, the contractor shall not be entitled to receive any further payment under this contract until said work shall be wholly finished, at which time, if the unpaid balance under this contract shall be more than the expense and liability incurred by the sanitary district in finishing the work, this difference over and above the cost of finishing said work shall be paid by the sanitary district to the contractor, but if such expense and liability shall exceed such unpaid balance, the contractor shall pay the difference to the sanitary district on demand.”

The construction company had received $494,293.97 in monthly payments under the contract before it made default on July 28, 1931. The district gave notice and passed all of the requisite resolutions and ordinances in connection with that default and in connection with the reletting of the sewer contract. In the interim, between the default and the date of reletting, December 1, 1931, the district expended $14,424.44 for attorneys’ and engineering fees, watchman’s services, keeping sewers and ditches open, building temporary bridges and in protecting the public against hazards occasioned by the unfinished sewer construction, etc. The work was completed under the new contract at a cost of $144,900. After payment of the three amounts listed, there remained $38,612.21 in the treasury of the sanitary district out of the original contract price of $692,230.62.

Notices of mechanics’ liens were given the district by appellees, and on January 20, 1932, H. H. Gunther and others filed their bill of complaint to establish their liens against the money, bonds or warrants due or to become due the O’Brien Brothers Construction Company, and, later, other lien claimants filed answers and were given leave to intervene. The district answered the petitions. Evidence was heard and the court found the issues for appellees and ordered the sanitary district to pay $22,989.43 principal and $2203.03 interest, in addition to the balance of $38,612.21 mentioned above.

The appellant contends that under section 23 of the Mechanics’ Lien act (Ill. Rev. Stat. 1937, chap. 82, par. 23) no part of the $87,288.41 retained by it out of monthly estimates was money due or to become due to the O’Brien Brothers Construction Company until the work was finally completed, and that it had the right to use all or any part of that money to complete the work. The appellees contend that this fund, so retained, must be applied towards discharging their liens before any part of the $87,288.41 could be used to complete the sewers.

Section 23 of the Mechanics’ Lien act provides in part: “Any person who shall furnish material, apparatus, fixtures, machinery or labor to any contractor having a contract for public improvement for any county, township, school district, city or municipality in this State, shall have a lien on the money, bonds or warrants due or to become due the contractor * * * under such contract.” These liens, under this section, are upon the money, bonds or warrants instead of the property improved. (Alexander Lumber Co. v. City of Farmer City, 272 Ill. 264, 276.) The statute does not prejudice or infringe upon the rights of the municipality, but the person affected is the contractor who owes the money to those furnishing materials, labor, etc. Standard Oil Co. v. Vanderboom, 326 Ill. 418, 424.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carroll Seating Company v. Verdico J.J.L. Inc.
Appellate Court of Illinois, 2006
Westcon/Dillingham Microtunneling v. Walsh Construction Co.
747 N.E.2d 410 (Appellate Court of Illinois, 2001)
A.Y. McDonald Manufacturing Co. v. State Farm Mutual Automobile Insurance
587 N.E.2d 623 (Appellate Court of Illinois, 1992)
Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
J&W Allen Construction Co. v. Kramer
41 Ill. Ct. Cl. 133 (Court of Claims of Illinois, 1989)
Northwest Water Commission v. Carlo v. Santucci, Inc.
516 N.E.2d 287 (Appellate Court of Illinois, 1987)
Emulsicoat, Inc. v. City of Hoopeston
425 N.E.2d 1349 (Appellate Court of Illinois, 1981)
Brady Brick & Supply Co. v. Lotito
356 N.E.2d 1126 (Appellate Court of Illinois, 1976)
Housing Authority v. Holtzman
256 N.E.2d 873 (Appellate Court of Illinois, 1970)
Board of Education of School District No. 108 v. Collom
222 N.E.2d 804 (Appellate Court of Illinois, 1966)
Consolidated Construction Co. v. Malan Construction Corp.
192 N.E.2d 263 (Appellate Court of Illinois, 1963)
BOARD OF EDUCATION, ETC. v. Swam
124 N.E.2d 554 (Appellate Court of Illinois, 1955)
Koenig v. McCARTHY CONSTR. CO., INC.
100 N.E.2d 338 (Appellate Court of Illinois, 1951)
Fodge v. Board of Education
32 N.E.2d 650 (Appellate Court of Illinois, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
16 N.E.2d 890, 369 Ill. 362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gunther-v-obrien-bros-construction-co-ill-1938.