Fodge v. Board of Education

32 N.E.2d 650, 309 Ill. App. 109, 1941 Ill. App. LEXIS 919
CourtAppellate Court of Illinois
DecidedMarch 11, 1941
DocketGen. No. 40,800
StatusPublished
Cited by12 cases

This text of 32 N.E.2d 650 (Fodge v. Board of Education) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fodge v. Board of Education, 32 N.E.2d 650, 309 Ill. App. 109, 1941 Ill. App. LEXIS 919 (Ill. Ct. App. 1941).

Opinion

Mr. Justice John J. Sullivan

delivered the opinion of the court.

This case was consolidated for hearing in this court with Gen. No. 40,870, Fodge v. Board of Education of Village of Oak Park, Dist. No. 97, 309 Ill. App. 137 (Abst.), and Gen. No. 40,962, Fodge v. Board of Education of Village of Oak Park, Dist. No. 97, 309 Ill. App. 137 (Abst.).

Ceco Steel Products Corporation, cross complainant and appellant, is a subcontractor which was joined as a defendant in a complaint to enforce a mechanic’s lien claim against funds due from the defendant, Board of Education of the Village of Oak Park, Illinois (hereinafter for convenience referred to as the Board of Education), to F. & H. Construction Company, the principal contractor. Ceco Steel Products Corporation filed an answer by which it put the original lien claimant upon proof of his claim. At the same time it filed its cross complaint against the Board of Education, the principal contractor and others and by leave of court joined as a new party defendant to its cross complaint the Fidelity and Deposit Company of Maryland, surety on the bond taken by the Board of Education from the principal contractor.

The cross complaint alleged in substance that F. & H. Construction Company had entered into a contract with the Board of Education to erect an addition to a school building in the Village of Oak Park, Illinois; that said contractor and Fidelity and Deposit Company of Maryland as principal and surety, respectively, entered into a bond conditioned upon the payment by the principal of all persons furnishing material or performing labor for the completion of the building; that cross complainant had fully performed a subcontract, which it had entered into with the principal contractor, and that the surety was liable for an unpaid balance .due under the subcontract because said principal .contractor had not paid such balance and that, having been adjudicated bankrupt before completing the building, it was unable to pay any part thereof. Certain exhibits, including the bond and subcontract, were attached to and made part of the cross complaint.

The defendant Fidelity and Deposit Company .of Maryland, the surety on the bond, filed a motion to dismiss the cross complaint as to it upon the ground principally that the bond furnished by it was merely a performance bond naming the Board of Education as obligee, which could not be sued upon by persons performing labor for or furnishing material to the principal in the bond, F. & H. Construction Company.

After the motion to dismiss had been allowed an amendment to the cross complaint was filed to show that the action was brought on said cross complaint in the name of the Board of Education “for the use of” the cross complainant. The amendment also added an allegation that the cross complainant (by its former name) had been named in the principal contract as having been approved for employment as a subcontractor. The surety’s motion to dismiss was allowed to stand to the amended cross complaint and a final order was entered on the pleadings dismissing the cross complaint as to the surety and entering judgment for costs against the cross complainant. It is from that order that this appeal is taken by the said subcontractor, Ceco Steel Products Corporation. The Board of Education has joined in this appeal as a coparty.

The theory of cross complainant as stated in its brief is that “it is an obligee of the bond executed for the benefit of persons furnishing material or performing labor to the principal. This bond was executed pursuant to the requirements of ‘An Act in relation to bonds of contractors entering into contracts for Public Construction,’ approved June 20, 1931 (Chap. 29, Sec. [par.] 15, Illinois Revised Statutes 1937 . . . ). The cross complaint alleges the compliance with the statutory procedural steps contained in Section [par.] 16 of the same chapter, which gives to every person ‘furnishing material or performing labor, either as an individual or as a subcontractor for any contractor’ . . . the right to sue on such bond in the name of the board or political subdivision named as obligee. By amendment to the cross complaint, the Board of Education was added as the ‘use’ plaintiff. The contract, which is made a part of the bond, contains the direct promise of the principal ‘to pay subcontractors,’ and the' cross complainant is listed in the contract as one of the subcontractors to be employed. Accordingly, cross complainant contends that it has a cause of action and right to sue in the name of the board under the statute; but that if the bond proper, and the contract which is a part of the bond, do not constitute a compliance with Chapter 29, Section [par.] 15, then that it may recover on the bond and contract as a common law obligation.”

Defendant surety’s theory is “that the bond upon which cross complainant seeks to recover is simply an ordinary ‘performance bond’ and is solely for the benefit of and indemnifies only the Board of Education, the obligee named therein, against loss; that there is no allegation in the cross complaint that the Board of Education has sustained a loss or that there has been a breach of the bond; that the cross complainant, Ceco Steel Products Corporation, is neither a named nor a beneficial obligee in the bond and has no right of action thereon; that the bond is not a statutory bond within the provisions of Sections [pars.] 15 and 16, Chapter 29, Illinois Revised Statutes, 1937; that the Statute will not be read into the bond and affords cross complainant no right of action thereon.”

The contract entered into between the principal contractor and the Board of Education contained the following, among other provisions:

“Article IX. Unless otherwise stipulated, the contractor shall provide and pay for all materials, labor, water, tools, equipment, light, power, transportation and other facilities necessary for the execution and completion of the work. ( £
“Article XXXVII. Relations of Contractor and Subcontractor — The Contractor agrees to bind every subcontractor and every subcontractor agrees to be bound by the terms of the Agreement, the General Conditions, the Drawings and Specifications as far as applicable to his work, including the following provisions of this Article unless specifically noted to the contrary in a subcontract approved in writing as adequate by the Owner or Architect.
< (
“The Contractor agrees . . .
“(d) To be bound to the subcontractor by all the obligations that the Owner assumes to the Contractor under the Agreement, General Conditions, Drawings and Specifications, and by all the provisions thereof affording remedies and redress to the Contractor from the Owner.
“(e) To pay the Subcontractor, upon the payment of certificates, if issued under the schedule of values described in Article XXIV of the General Conditions, ■the amount allowed to the Contractor on account of the -Subcontractor’s work to the extent of the Subcontractor’s interest therein.
“(f) To pay the Subcontractor, upon the payment ,of certificates, if issued otherwise than as in (e), so that at all.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake County Grading Co. v. Village of Antioch
2014 IL 115805 (Illinois Supreme Court, 2014)
Carroll Seating Company v. Verdico J.J.L. Inc.
Appellate Court of Illinois, 2006
Young v. General Insurance Co. of America
337 N.E.2d 739 (Appellate Court of Illinois, 1975)
Housing Authority v. Holtzman
256 N.E.2d 873 (Appellate Court of Illinois, 1970)
Neenah Foundry Co. v. National Surety Corp.
197 N.E.2d 744 (Appellate Court of Illinois, 1964)
Board of Education Ex Rel. Palumbo v. Pacific National Fire Insurance
153 N.E.2d 498 (Appellate Court of Illinois, 1958)
BOARD OF EDUCATION, ETC. v. Swam
124 N.E.2d 554 (Appellate Court of Illinois, 1955)
Logsdon v. Logsdon
104 N.E.2d 622 (Illinois Supreme Court, 1952)
Vilter Mfg. Co. v. Loring
136 F.2d 466 (Seventh Circuit, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
32 N.E.2d 650, 309 Ill. App. 109, 1941 Ill. App. LEXIS 919, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fodge-v-board-of-education-illappct-1941.