Lake County Grading Co. v. Village of Antioch

2014 IL 115805
Illinois Supreme Court·Decided November 24, 2014·No. 115805·Published·Cited by 40 cases

Opinion

Illinois Official Reports

Supreme Court

Lake County Grading Co. v. Village of Antioch, 2014 IL 115805

Caption in Supreme LAKE COUNTY GRADING COMPANY, LLC, Appellee, v. THE Court: VILLAGE OF ANTIOCH, Appellant.

Docket No. 115805

Filed October 17, 2014

Held The Public Construction Bond Act protects subcontractors for whom (Note: This syllabus no right of mechanic’s lien exists against a public body by constitutes no part of the guaranteeing that labor and materials furnished to one who contracts opinion of the court but with a public body are paid for, even if such provisions are not has been prepared by the specifically included in the bonds provided under the Act. Reporter of Decisions for the convenience of the reader.)

Decision Under Appeal from the Appellate Court for the Second District; heard in that Review court on appeal from the Circuit Court of Lake County, the Hon.

Margaret M. Mullen, Judge, presiding.

Judgment Appellate court judgment reversed.

Circuit court judgment reversed. Cause remanded with directions.

Counsel on Robert J. Long, of Daniels, Long & Pinsel, LLC, of Waukegan, and Appeal Lawrence R. Moelmann and Nancy G. Lischer, of Hinshaw & Culbertson LLP, of Chicago, for appellant.

Bogdan Martinovich, of Ray & Glick, Ltd., of Libertyville, for appellee.

Brian Day and Roger Huebner, of Springfield, for amicus curiae The Illinois Municipal League.

Justices JUSTICE THEIS delivered the judgment of the court, with opinion.

Chief Justice Garman and Justices Thomas, Kilbride, and Karmeier concurred in the judgment and opinion. Justice Freeman dissented, with opinion, joined by Justice Burke.

OPINION

¶1 The circuit court of Lake County granted summary judgment to plaintiff, Lake County Grading Company, LLC, on its third-party beneficiary breach of contract claims against defendant, Village of Antioch (Village). The appellate court affirmed, holding that the Village breached the subject contracts by violating section 1 of the Public Construction Bond Act (Bond Act) (30 ILCS 550/1 (West 2008)). 2013 IL App (2d) 120474, ¶¶ 39-40. For the reasons that follow, we hold that the Village did not violate section 1 of the Bond Act, and, therefore, reverse the judgments of the appellate and circuit courts.

¶2 BACKGROUND

¶3 This cause of action arises from construction work performed in two residential subdivisions located in Antioch, Illinois, known as the NeuHaven subdivision (formerly the Deercrest subdivision), and the Clublands subdivision. Neumann Homes, Inc. (Neumann), was the developer of both subdivisions.1

¶4 The Village entered into two infrastructure agreements (the contracts) with Neumann to make certain public improvements in the subdivisions for the benefit of the Village. Pursuant to the contracts, and based upon section 1 of the Bond Act, Neumann was required to provide surety bonds, the amount of which was based on the total cost of the improvements.

¶5 Section 1 of the Bond Act provides, inter alia, that a political subdivision of the State, such as the Village, contracting for public works above a specific dollar amount shall require the contractor, as part of the agreement, to supply and deliver a bond. 30 ILCS 550/1 (West 2008). Each such bond is “deemed” to contain certain provisions, even if they are not expressly

1

Neumann is not a party to this appeal.

included in the bond, and must provide for the completion of the contract, the payment of materials used in the work, and all labor performed in the work, including work completed by subcontractors. Id.

¶6 Neumann provided four surety bonds issued by Fidelity and Deposit Company of Maryland (Fidelity) that were substantively identical. Each bond provided, in pertinent part:

“[The P]rincipal [Neumann] shall perform and complete *** improvement(s) to *** development in accordance with either the plan(s)/specification(s)/agreement [prepared by Pearson Brown & Associates, Inc. or Manhard Consulting], then this obligation shall be void ***. This bond will terminate upon written acceptance of the improvements by the obligee [Village] to the principal [Neumann] and/or surety [Fidelity].”

The four surety bonds totalled $18,128,827.

¶7 It is undisputed the bonds provided by Neumann did not contain specific “payment bond” language that expressly guaranteed payment to subcontractors for labor or materials. A payment bond generally provides that if the contractor does not pay its subcontractors and material suppliers, the surety will pay them. See Western Waterproofing Co. v. Springfield Housing Authority, 669 F. Supp. 901, 903 (C.D. Ill. 1987). In contrast, a “completion bond” (also known as a “performance bond”) provides that if the contractor does not complete a project, the surety will pay for its completion. Id.

¶8 Plaintiff and Neumann also entered into agreements for plaintiff to provide certain labor and materials for the public improvements required under the contracts. Plaintiff completed the work, but was not paid in full. Neumann later defaulted on its contract with the Village and declared bankruptcy on November 1, 2007. Plaintiff last performed work on the Clublands subdivision on December 23, 2006. Plaintiff last performed work on the NeuHaven subdivision on April 16, 2007. On February 18, 2008, plaintiff served Neumann and the Village with notices of a lien claim for the work it had completed on the project.

¶9 Plaintiff ultimately filed a five-count second amended complaint seeking to recover payment from the Village. In counts II and IV, the only counts at issue here, plaintiff alleged breach of contract claims related to the work performed by plaintiff in the NeuHaven and Clublands subdivisions. Specifically, plaintiff alleged the Village breached the contracts because the surety bonds provided by Neumann did not contain actual language guaranteeing payment to subcontractors as mandated by the first paragraph of section 1 of the Bond Act. Plaintiff further alleged that by virtue of this provision in section 1, it became a third-party beneficiary of the contracts between the Village and Neumann because the requirements contained therein are read into every public works contract for the benefit of subcontractors such as itself.

¶ 10 The parties filed cross-motions for summary judgment. The Village in its motion also relied upon section 1. It asserted that based upon the “deeming language” contained in the statute, the bonds procured by Neumann were sufficient because they contained both completion and payment provisions as a matter of law and covered all of the site improvements which plaintiff constructed. The Village argued that plaintiff’s only cause of action was against the bonds themselves, but because plaintiff gave notice of its claims more than 180 days after last working on the project, the claims were barred by the limitations period found in section 2 of the Bond Act (30 ILCS 550/2 (West 2008)).

¶ 11 In response to the Village’s motion for summary judgment, plaintiff did not dispute that it made its notices of claims more than 180 days after last performing work or providing materials, but argued that the limitations period applied only to a suit on the bond. Plaintiff claimed that the 180-day limitations period was inapplicable to its breach of contract claims because in a case such as this where no payment bond was procured, a suit on the bond is impossible.

¶ 12 The issue before the trial court was therefore whether the surety bonds provided by Neumann to the Village conformed with the relevant requirements of section 1 of the Bond Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Lake County Grading Co. v. Village of Antioch, 2014 IL 115805 (Ill. 2014).

2014 IL 115805 (Lake County Grading Co. v. Village of Antioch) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Neely v. Senne
2025 IL App (1st) 231162-U (Appellate Court of Illinois, 2025)
Cagwin v. Flynn
2023 IL App (3d) 230086-U (Appellate Court of Illinois, 2023)
In re S.J.
2023 IL App (5th) 230421-U (Appellate Court of Illinois, 2023)
McHenry Savings Bank v. Daniel
2021 IL App (1st) 210070-U (Appellate Court of Illinois, 2021)
Arbogast v. Schaub
2021 IL App (3d) 200235-U (Appellate Court of Illinois, 2021)
Shannon Court Condominium Ass'n v. Armada Express, Inc.
2020 IL App (1st) 192341 (Appellate Court of Illinois, 2020)
Floyd v. Hill Funding, LLC
2020 IL App (1st) 192353-U (Appellate Court of Illinois, 2020)
Hernandez v. Lifeline Ambulance, LLC
2020 IL 124610 (Illinois Supreme Court, 2020)
Baillie v. Raoul
2019 IL App (4th) 180655 (Appellate Court of Illinois, 2019)
People ex rel. Department of Human Rights v. Oakridge Nursing & Rehab Center
2019 IL App (1st) 170806 (Appellate Court of Illinois, 2019)
Boucher v. 111 East Chestnut Condominium Ass'n
2018 IL App (1st) 162233 (Appellate Court of Illinois, 2019)
Oak Lawn Professional Firefighters Ass'n, Local 3405 v. Village of Oak Lawn
2018 IL App (1st) 172079 (Appellate Court of Illinois, 2018)
Boucher v. 111 East Chestnut Condominium Assoc.
2018 IL App (1st) 162233 (Appellate Court of Illinois, 2018)
Cuevas v. Berrios
2017 IL App (1st) 151318 (Appellate Court of Illinois, 2017)
In re M.M.
2016 IL 119932 (Illinois Supreme Court, 2016)
Valfer v. Evanston Northwestern Healthcare
2016 IL 119220 (Illinois Supreme Court, 2016)
1010 Lake Shore Association v. Deutsche Bank National Trust Company
2015 IL 118372 (Illinois Supreme Court, 2016)
Founders Insurance Co. v. Walker
2015 IL App (1st) 141301 (Appellate Court of Illinois, 2015)
Young v. Alden Gardens of Waterford, LLC
2015 IL App (1st) 131887 (Appellate Court of Illinois, 2015)