Lake County Grading Company v. Village of Antioch

2013 IL App (2d) 120474, 985 N.E.2d 638
CourtAppellate Court of Illinois
DecidedFebruary 20, 2013
Docket2-12-0474
StatusPublished
Cited by5 cases

This text of 2013 IL App (2d) 120474 (Lake County Grading Company v. Village of Antioch) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake County Grading Company v. Village of Antioch, 2013 IL App (2d) 120474, 985 N.E.2d 638 (Ill. Ct. App. 2013).

Opinion

ILLINOIS OFFICIAL REPORTS Appellate Court

Lake County Grading Co. v. Village of Antioch, 2013 IL App (2d) 120474

Appellate Court LAKE COUNTY GRADING COMPANY, LLC, Plaintiff-Appellee, v. Caption THE VILLAGE OF ANTIOCH, Defendant-Appellant (Neumann Homes, Inc., Defendant).

District & No. Second District Docket No. 2-12-0474

Filed February 20, 2013

Held In an action by plaintiff subcontractor to recover from defendant village (Note: This syllabus for work performed in connection with public improvements required by constitutes no part of the village for defendant contractor’s residential subdivisions, summary the opinion of the court judgment was properly entered for plaintiff on its counts alleging breach but has been prepared of contract under a third-party beneficiary theory, notwithstanding the by the Reporter of village’s contention that plaintiff had to proceed under the Public Decisions for the Construction Bond Act, since plaintiff was a third-party beneficiary of the convenience of the village’s agreement with the contractor, the village’s failure to obtain a reader.) payment bond from the contractor made the Bond Act inapplicable, and plaintiff’s breach-of-contract claims were timely.

Decision Under Appeal from the Circuit Court of Lake County, No. 08-L-329; the Hon. Review Margaret J. Mullen, Judge, presiding.

Judgment Affirmed. Counsel on Robert J. Long, of Daniels, Long & Pinsel, LLC, of Waukegan, and Appeal Lawrence R. Moelmann and Nancy G. Lischer, both of Hinshaw & Culbertson LLP, of Chicago, for appellant.

Bogdan Martinovich, of Ray & Glick, Ltd., of Libertyville, for appellee.

Panel PRESIDING JUSTICE BURKE delivered the judgment of the court, with opinion. Justices McLaren and Hudson concurred in the judgment and opinion.

OPINION

¶1 Defendant Neumann Homes, Inc., entered into two infrastructure agreements (the contract) with defendant the Village of Antioch (Village), to make certain public improvements in two residential subdivisions. Pursuant to the contract, Neumann provided four surety bonds that guaranteed performance for the benefit of the Village. The bonds did not also guarantee payment to subcontractors, which was required by section 1 of the Public Construction Bond Act (Bond Act). 30 ILCS 550/1 (West 2010). Neumann defaulted on its contract with the Village and also failed to pay plaintiff, Lake County Grading Co., LLC., a subcontractor that worked on the project. ¶2 Plaintiff filed a five-count second amended complaint to recover payment from the Village. The trial court granted plaintiff summary judgment on counts II and IV, in which plaintiff alleged breach of contract under a third-party-beneficiary theory. Plaintiff’s theory was that (1) section 1 of the Bond Act (see 30 ILCS 550/1 (West 2010)) required the Village to obtain from Neumann a payment bond for the benefit of subcontractors, (2) Neumann’s bonds were only performance bonds and not payment bonds, and (3) the Village’s noncompliance with section 1 of the Bond Act rendered it liable for third-party-beneficiary breach of contract. On appeal, the Village argues that under section 1 a payment bond provision was read into Neumann’s performance bonds, and therefore plaintiff’s recourse was to file an action on the bonds under section 2 of the Bond Act, which was barred by the 180-day limitations period set out therein (30 ILCS 550/2 (West 2010)). We affirm.

¶3 I. FACTS ¶4 This action arises from construction work performed in two residential subdivisions in Antioch, commonly known as the NeuHaven Subdivision and the Clublands Subdivision. Pursuant to the contract, Neumann agreed to construct certain public improvements for the Village’s benefit. Thereafter, Neumann and plaintiff entered into agreements for plaintiff to

-2- perform certain grading work required under the contract. The pleadings present no dispute that plaintiff completed the work in compliance with the contract but was not paid in full for its services. Neumann is not a party to this appeal. The Village issued two special service area (SSA) bonds to cover some of the costs. ¶5 The contract required Neumann to provide surety bonds, the amounts of which were based on the total cost of the improvements. Neumann provided four surety bonds, issued by Fidelity and Deposit Company of Maryland (Fidelity), to cover the work. The four bonds were substantively similar, each providing in part that “NOW THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that, if said principal [Neumann] shall perform and complete said improvement(s) to said development in accordance with either the plan(s)/specification(s)/agreement, then this obligation shall be void, otherwise to be and remain in full force and effect. THIS BOND WILL TERMINATE upon written acceptance of the improvements by the Obligee [Village] to the Principal [Neumann] and/or Surety [Fidelity].” While the bonds guaranteed performance by Neumann, they were silent regarding payments to subcontractors, like plaintiff. ¶6 Neumann was unable to complete the improvements or to pay plaintiff in full. On November 1, 2007, Neumann declared bankruptcy. On February 18, 2008, plaintiff served Neumann and the Village with notices of a lien claim on a public improvement (see 770 ILCS 60/23 (West 2010)) and notices of a bond claim (see 30 ILCS 550/1, 2 (West 2010)). Plaintiff last performed work on the NeuHaven Subdivision on April 16, 2007, which made the 180th day October 13, 2007. Plaintiff last performed work on the Clublands Subdivision on December 23, 2006, which made the 180th day June 4, 2007. The parties do not dispute that plaintiff made its notices of claims more than 180 days after last performing work or providing materials. Mark Reich, a managing member of plaintiff, testified that he handles lien and bond claims for plaintiff. Reich stated that plaintiff had delayed sending notices of its claims because plaintiff did not want to risk its good business relationship with Neumann and feared losing future work. ¶7 Plaintiff filed a five-count second amended complaint, seeking to recover payment from the Village. Counts I and III were lien claims for public funds (see 770 ILCS 60/23 (West 2010)) and count V was a claim for unjust enrichment, but these claims ultimately were dismissed and are not part of this appeal. ¶8 Counts II and IV alleged third-party-beneficiary breach of contract. Specifically, plaintiff alleged that section 1 of the Bond Act and section 3.2(a) of the contract conferred third-party- beneficiary status upon plaintiff. Plaintiff alleged that the Village has breached its duty to require from Neumann a sufficient payment bond for the benefit of plaintiff. ¶9 Following cross-motions for summary judgment, the trial court granted plaintiff summary judgment on counts II and IV. The Village timely appeals.

¶ 10 II. ANALYSIS ¶ 11 A. Standard of Review ¶ 12 The purpose of summary judgment is not to try a question of fact but, rather, to determine whether a genuine issue of material fact exists. Adams v. Northern Illinois Gas Co., 211 Ill.

-3- 2d 32, 42-43 (2004). Summary judgment is appropriate where the pleadings, affidavits, depositions, and admissions on file, when viewed in the light most favorable to the nonmoving party, show that there is no genuine issue of material fact and that the moving party is entitled to a judgment as a matter of law. 735 ILCS 5/2-1005(c) (West 2010); Klitzka v. Hellios, 348 Ill. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake County Grading Co. v. Village of Antioch
2014 IL 115805 (Illinois Supreme Court, 2014)
Feingold v. John Hancock Life Insurance Co
753 F.3d 55 (First Circuit, 2014)
Kelly v. Orrico
2014 IL App (2d) 130002 (Appellate Court of Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2013 IL App (2d) 120474, 985 N.E.2d 638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-county-grading-company-v-village-of-antioch-illappct-2013.