Carroll Seating Co. JJL Inc. v. Verdico

861 N.E.2d 1045, 308 Ill. Dec. 480, 369 Ill. App. 3d 724
CourtAppellate Court of Illinois
DecidedDecember 21, 2006
Docket1—04—3026, 1—04—3457 cons.
StatusPublished
Cited by4 cases

This text of 861 N.E.2d 1045 (Carroll Seating Co. JJL Inc. v. Verdico) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carroll Seating Co. JJL Inc. v. Verdico, 861 N.E.2d 1045, 308 Ill. Dec. 480, 369 Ill. App. 3d 724 (Ill. Ct. App. 2006).

Opinion

PRESIDING JUSTICE QUINN

delivered the opinion of the court:

Defendant-intervenors are the owners of a construction company, PB. Verdico, Inc. (Verdico), that was hired by School District 87 in Berkeley, Illinois, to renovate and build additions to several school buildings. Plaintiffs Carroll Seating Company, 1 J.J.L., Inc., d/b/a American Roofing and Repair Co., Lombardi Electric, Inc., and Team Mechanical, Inc., were subcontractors hired by Verdico for the project.

As required by section 1 of the Public Construction Bond Act (Bond Act) (30 ILCS 550/1 (West 2002)), Verdico posted a payment bond for the project, with Travelers Casualty and Surety Company of America (Travelers) acting as the surety for the bond. When Verdico failed to pay plaintiffs the entire amount owed to them under their respective subcontracts, they sued Verdico, Travelers, and the school district to recover on the bond.

After the circuit court had granted summary judgment to Carroll Seating, Verdico’s owners intervened, claiming that they had a stake in the case because they had agreed to indemnify Travelers for any payments made under the bond. Seeking to have the circuit court reconsider and vacate its grant of summary judgment to Carroll Seating, intervenors argued that plaintiffs’ claims on the bond were untimely because the six-month time limit contained in section 2 of the Bond Act (30 ILCS 550/2 (West 2002)), and not the one-year time limit contained in the bond supplied by Verdico, was applicable. The circuit court denied intervenors’ motion for reconsideration. This appeal followed.

ANALYSIS

On appeal, plaintiffs first argue that intervenors lacked standing to intervene in the underlying lawsuit. In their petition to intervene, intervenors alleged that they had an interest in the proceedings because they had “personally guaranteed to Travelers payment of any losses suffered by Travelers regarding the subject payment bond.” Plaintiffs argue that intervenors provided no evidence of that guarantee in the record before this court.

As intervenors point out, however, plaintiffs did not contest their standing to intervene in the circuit court below. Thus, we find that plaintiffs’ lack-of-standing argument is waived and express no opinion as to whether intervenors had standing to intervene. See Greer v. Illinois Housing Development Authority, 122 iLL. 2d 462, 508 (1988) (stating that “lack of standing in a civil case is an affirmative defense, which will be waived if not raised in a timely fashion in the trial court”).

The next question on appeal is which claim-filing limitations period is applicable, the six-month time limit found in the Bond Act, or the one-year time frame contained in the bond supplied by Verdico. Prior to the passage of the Bond Act, materialmen and laborers had no right to impose a mechanic’s lien on a public work. See Fodge v. Board of Education of the Village of Oak Park, District 97, 309 iLL. App. 109, 122, 32 N.E.2d 650, 656 (1941), citing Gunther v. O’Brien Bros. Construction Co., 369 iLL. 362, 370 (1938). Additionally, in interpreting public works contracts between the state and its contractors, Illinois courts had found that those contracts did not confer upon subcontractors the status of third-party beneficiaries to those contracts or create a “common-law right of action against a surety,” even where, in some cases, those contracts contained a provision stating that “the principal contractor agree[d] ‘to pay the subcontractor.’ ” Fodge, 309 iLL. App. at 122, 32 N.E.2d at 656. Without the ability to place a lien on public property and with no imputed rights under the bond contract between the state and general contractor, many subcontractors were left with no legal recourse when a general contractor failed to fulfill his contractual obligation.

In 1931 the Bond Act was passed, requiring that state officials obtain a payment bond 2 from contractors who agree to perform “public work of any kind costing over $5,000.” 30 ILCS 550/1 (West 2002). The aim of the Bond Act was twofold: it protected “those who furnish[ed] labor or materials on public works” and guarded “the tax money allotted for public works.” Housing Authority v. Holtzman, 120 Ill. App. 2d 226, 241 (1970); see also Aluma Systems, Inc. v. Frederick Quinn Corp., 206 Ill. App. 3d 828, 853-54 (1990) (“The purpose of sections 1 and 2 [citation] of the Bond for Public Works Act is to protect payment to contractors and materialmen for whom no right of mechanics’ liens exists against a public body, and to regulate claims against public monies”).

These dual aims were codified into the claim-filing procedures contained in section 2 of the Bond Act, which allows subcontractors, materialmen, or laborers employed on a public works project to sue on the payment bond, but requires any such suit to be filed within six months of the state’s acceptance of the project:

“Every person furnishing material or performing labor, either as an individual or as a sub-contractor for any contractor, with the State, or a political subdivision *** in this Act, shall have the right to sue on such bond or letter of credit in the name of the State, or the political subdivision thereof entering into such contract, as the case may be, for his use and benefit, *** provided, however, that this Act shall not be taken to in any way make the State, or the political subdivision thereof entering into such contract, as the case may be, liable to such sub-contractor, materialman or laborer to any greater extent than it was liable under the law as it stood before the adoption of this Act. ***
?¡t 5¡: j{í
Provided, further, that no action shall be brought until the expiration of 120 days after the date of the last item of work or the furnishing of the last item of materials *** nor shall any action of any kind be brought later than 6 months after the acceptance by the State or political subdivision thereof of the building project or work. Such action shall be brought only in the circuit court of this State in the judicial circuit in which the contract is to be performed.” 30 ILCS 550/2 (West 2002).

Intervenors argue that the Bond Act’s claim-filing provisions (i.e., the six-month limitations period which begins to run after the project is accepted) are applicable to the bond provided by Verdico because (1) the plain language of the bond itself evidences an intent to incorporate the Bond Act’s claim-filing provisions, and (2) even if the bond cannot be so read, the Bond Act’s provisions preempt or “override[ ]” the bond’s one-year filing period. We disagree.

Paragraph 11 of the bond provided by Verdico states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake County Grading Co. v. Village of Antioch
2014 IL 115805 (Illinois Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
861 N.E.2d 1045, 308 Ill. Dec. 480, 369 Ill. App. 3d 724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carroll-seating-co-jjl-inc-v-verdico-illappct-2006.