Carroll Seating Company v. Verdico J.J.L. Inc.

CourtAppellate Court of Illinois
DecidedDecember 21, 2006
Docket1-04-3026 & 1-04-3457 Rel
StatusPublished

This text of Carroll Seating Company v. Verdico J.J.L. Inc. (Carroll Seating Company v. Verdico J.J.L. Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carroll Seating Company v. Verdico J.J.L. Inc., (Ill. Ct. App. 2006).

Opinion

FOURTH DIVISION December 21, 2006

1-04-3026 & 1-04-3457 (Cons.)

CARROLL SEATING COMPANY J.J.L. ) Appeal from the Inc., d/b/a/ American Roofing ) Circuit Court of and Repair Company, LOMBARDI ELECTRIC, ) Cook County. INC., and TEAM MECHANICAL, INC., ) ) Plaintiffs-Appellees, ) ) v. ) ) PETER B. VERDICO and JULIE VERDICO, ) ) Defendants and Intervenors-Appellants ) ) ) (P.B. Verdico, Inc., an Illinois ) Corporation; Travelers Casualty and ) Surety Company of America, a Foreign ) Corporation, and Berkeley School ) District No. 87, a body politic, ) The Honorable ) Clifford L. Meacham, Defendants). ) Judge Presiding.

MODIFIED UPON REHEARING

PRESIDING JUSTICE QUINN delivered the opinion of the court:

Defendant-intervenors are the owners of a construction

company, P.B. Verdico, Inc. (Verdico), that was hired by School

District 87 in Berkeley, Illinois, to renovate and build additions

to several school buildings. Plaintiffs Carroll Seating Company1,

J.J.L., Inc., d/b/a American Roofing and Repair Co., Lombardi

1 Carroll Seating did not file a brief in this matter. 1-04-3026 & 1-04-3457 (Cons.) Electric, Inc., and Team Mechanical, Inc., were subcontractors

hired by Verdico for the project.

As required by section 1 of the Public Construction Bond Act

(Bond Act) (30 ILCS 550/1 (West 2002)), Verdico posted a payment

bond for the project, with Travelers Casualty and Surety Company of

America (Travelers) acting as the surety for the bond. When

Verdico failed to pay plaintiffs the entire amount owed to them

under their respective subcontracts, they sued Verdico, Travelers,

and the school district to recover on the bond.

After the circuit court had granted summary judgment to

Carroll Seating, Verdico's owners intervened, claiming that they

had a stake in the case because they had agreed to indemnify

Travelers for any payments made under the bond. Seeking to have

the circuit court reconsider and vacate its grant of summary

judgment to Carroll Seating, intervenors argued that plaintiffs'

claims on the bond were untimely because the six-month time limit

contained in section 2 of the Bond Act (30 ILCS 550/2 (West 2002)),

and not the one-year time limit contained in the bond supplied by

Verdico, was applicable. The circuit court denied intervenors'

motion for reconsideration. This appeal followed.

ANALYSIS

On appeal, plaintiffs first argue that intervenors lacked

standing to intervene in the underlying lawsuit. In their

petition to intervene, intervenors alleged that they had an

2 1-04-3026 & 1-04-3457 (Cons.) interest in the proceedings because they had "personally

guaranteed to Travelers payment of any losses suffered by

Travelers regarding the subject payment bond." Plaintiffs argue

that intervenors provided no evidence of that guarantee in the

record before this court.

As intervenors point out, however, plaintiffs did not

contest their standing to intervene in the circuit court below.

Thus, we find that plaintiffs' lack-of-standing argument is

waived and express no opinion as to whether intervenors had

standing to intervene. See Greer v. Illinois Housing Development

Authority, 122 Ill. 2d 462, 508 (1988) (stating that "lack of

standing in a civil case is an affirmative defense, which will be

waived if not raised in a timely fashion in the trial court").

The next question on appeal is which claim-filing

limitations period is applicable, the six-month time limit found

in the Bond Act, or the one-year time frame contained in the bond

supplied by Verdico. Prior to the passage of the Bond Act,

materialmen and laborers had no right to impose a mechanic's lien

on a public work. See Fodge v. Board of Education of the Village

of Oak Park, District 97, 309 Ill. App. 109, 122, 32 N.E.2d 650,

656 (1941), citing Gunther v. O'Brien Bros. Construction Co., 369

Ill. 362, 370 (1938). Additionally, in interpreting public works

contracts between the state and its contractors, Illinois courts

had found that those contracts did not confer upon subcontractors

the status of third-party beneficiaries to those contracts or

3 1-04-3026 & 1-04-3457 (Cons.) create a "common-law right of action against a surety," even

where, in some cases, those contracts contained a provision

stating that "the principal contractor agree[d] 'to pay the

subcontractor.'" Fodge, 309 Ill. App. At 122, 32 N.E.2d at 656.

Without the ability to place a lien on public property and with

no imputed rights under the bond contract between the state and

general contractor, many subcontractors were left with no legal

recourse when a general contractor failed to fulfill his

contractual obligation.

In 1931 the Bond Act was passed, requiring that state

officials obtain a payment bond2 from contractors who agree to

2 The practical benefits of requiring a "payment bond" have

been stated as follows:

"By guaranteeing payment for labor and materials

furnished the contractor under the contract, the

payment bond assures the contractor's credit, and thus

expedites the subcontractor's performance. It reduces

to a minimum the filing of mechanic's liens and the

loss of time and money necessary for enforcing them by

litigation. As mechanic's liens or other liens cannot

be filed against property of the United States and of

most states, the payment bonds have a singular value

with respect to public works contracts as they assure

payment to those who might otherwise have to depend

solely on the personal responsibility of the

4 1-04-3026 & 1-04-3457 (Cons.) perform "public work of any kind costing over $5,000." 30 ILCS

550/1 (West 2002). The aim of the Bond Act was twofold: it

protected "those who furnish[ed] labor or materials on public

works" and guarded "the tax money allotted for public works."

Housing Authority v. Holtzman, 120 Ill. App. 2d 226, 241 (1970);

see also Aluma Systems, Inc. v. Frederick Quinn Corp., 206 Ill.

App. 3d 828, 853-54 (1990) ("The purpose of sections 1 and 2

[citation] of the Bond for Public Works Act is to protect payment to contractors and materialmen for whom no right of mechanics'

liens exists against a public body, and to regulate claims

against public monies").

These dual aims were codified into the claim-filing

procedures contained in section 2 of the Bond Act, which allows

subcontractors, materialmen, or laborers employed on a public

works project to sue on the payment bond, but requires any such

suit to be filed within six months of the state's acceptance of

the project:

"Every person furnishing material or performing

labor, either as an individual or as a sub-contractor

for any contractor, with the State, or a political

contractor. Hence, the bond requirement tends to lower

bids because it eliminates the tendency to add to the

bid a figure to cover the credit hazard." T. Hass,

The Corporate Surety and Public Construction Bonds, 25

Geo. Wash. L. Rev. 206, 210 (1956-57).

5 1-04-3026 & 1-04-3457 (Cons.) subdivision *** in this Act, shall have the right to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
Greer v. Illinois Housing Development Authority
524 N.E.2d 561 (Illinois Supreme Court, 1988)
Housing Authority v. Holtzman
256 N.E.2d 873 (Appellate Court of Illinois, 1970)
MQ Construction Co. v. Intercargo Insurance
742 N.E.2d 820 (Appellate Court of Illinois, 2000)
Gunther v. O'Brien Bros. Construction Co.
16 N.E.2d 890 (Illinois Supreme Court, 1938)
William J. Templeman Co. v. United States Fidelity & Guaranty Co.
317 Ill. App. 3d 764 (Appellate Court of Illinois, 2000)
Fodge v. Board of Education
32 N.E.2d 650 (Appellate Court of Illinois, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
Carroll Seating Company v. Verdico J.J.L. Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/carroll-seating-company-v-verdico-jjl-inc-illappct-2006.