Capitol Indemnity Corporation v. United States of America, Defendant-Third Party v. Mt. Vernon Township High School District 201, Third Party

41 F.3d 320
CourtCourt of Appeals for the Third Circuit
DecidedJanuary 23, 1995
Docket93-3633
StatusPublished
Cited by5 cases

This text of 41 F.3d 320 (Capitol Indemnity Corporation v. United States of America, Defendant-Third Party v. Mt. Vernon Township High School District 201, Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capitol Indemnity Corporation v. United States of America, Defendant-Third Party v. Mt. Vernon Township High School District 201, Third Party, 41 F.3d 320 (3d Cir. 1995).

Opinion

CUMMINGS, Circuit Judge.

This appeal involves competing rights in a “progress payment” earned during the course of an ill-fated construction contract. The payment was designated for the general contractor, levied on by the Internal Revenue Service, and claimed by the completing surety for itself and a host of subcontractors. On cross-motions for summary judgment, the district court found that the funds belonged in part to the subcontractors and in part to the surety. The government has appealed this determination and we reverse.

FACTS

In May 1991, Mt. Vernon Township High School District No. 201 (the “District”) contracted (in the “Contract”) with B & H Construction Company (“B & H”) for asbestos removal and other work. B & H was to complete the project by August 9, 1991, in time for the new school year. The District agreed to a contract price of $248,340, due in monthly progress payments upon certification by the project architect that B & H had completed its work satisfactorily and paid its subcontractors and suppliers. The monthly payments would represent the work performed to date, less 10% “retainage” to be withheld until completion of the project and extinction of all liabilities to subcontractors, suppliers or other creditors. B & H agreed to obtain performance bonds and payment bonds for the protection of the subcontractors. The Contract further provided that “[njeither the Owner nor the Architect shall have any obligation to pay or to see to the payment of any moneys to any Subcontrae-tors except as may otherwise be required by law.” Contract article 9, section 0.

B & H procured the necessary payment and performance bonds on May 31, 1991, from the surety, Capitol Indemnity Corporation (“CIC”), with whom it had a general indemnity agreement dating back to May 1989 (the “Agreement”). In the Agreement, B & H assigned all of its rights under future contracts to CIC; this assignment was subject to defeat if B & H did not default on its obligations. 1 Section 11 of the Agreement also purported to create a trust in the contract funds, “for the benefit of and for payment of all obligations for labor and material furnished in connection with such contract * * * for which the Surety would be liable under said bond or bonds” (Gov.Br.App. 39).

Work on the project commenced on June 4, 1991, followed almost immediately by problems: B & H fell behind schedule, and subcontractors began complaining about delayed or inadequate payments. The subcontractors did not then or at any other time file notices of liens pursuant to § 23 of Illinois’ Mechanics Lien Act, 770 ILCS 60/0.01 et seq., which governs liens against public funds. The District modified the contract in an effort to ensure completion before school started but B & H was unable to make up lost time, and the August 9 deadline came and went with no end to the work in sight.

By early September, B & H had completed $143,993 of the work and had submitted its application for the second progress payment. Hovering over that sum (which, minus previously paid sums and agreed-upon retainage, totaled $102,341), however, was the long shadow of the Internal Revenue Service (“IRS”). In late July 1991, the IRS informed B & H of a federal tax obligation (unrelated to the District work) in the amount of $124,-448.51. B & H failed to pay this sum and on September 12, 1991, the IRS served a notice of levy on the District for all property owned *323 by B & H and in the District’s possession. IRS officials instructed the District not to pay B & H any money owed it, but instead to send funds to the IRS.

The District’s architect had forwarded B & H’s application for the contested progress payment to his home office on September 9, 1991, with a recommendation that it be paid. After healing about the IRS lien, however, District officials decided not to issue the funds to B & H. Although the District’s architect formally certified the pay application on September 17, neither B & H nor the IRS was ever paid. On October 7 the District declared B & H in default, and on October 9 formally demanded that CIC perform on its bonds and complete the project. 2 CIC finished the job, paid the subcontractors, and received the withheld payment of $102,341 from the District in May 1992, along with the remainder of the Contract funds.

CIC subsequently filed suit against the government, challenging the levy as unlawful and claiming that B & H had no property interest in the $102,341 progress payment. CIC sought a declaration that its rights were superior to those of the United States, and an injunction against the United States from enforcing the levy. The government responded by counterclaiming that the progress payment was impressed with the lien, and also by filing a third-party counterclaim against the District for its failure to honor the levy.

The district court granted summary judgment against the government on both claims. The court held that the Illinois Mechanics Lien Act entitled the subcontractors to the portion of the progress payment that represented their work. Therefore, the court found that $85,921.70 was due the subcontractors and properly paid over to CIC on their behalf. As to the remaining $16,420, the district court held that the Agreement between CIC and B & H had transferred any remaining property right in the progress payment to the surety on the date that CIC issued the payment and performance bonds. The court concluded that B & H had no property right in the progress payment, and that the government thus had nothing to levy against.

DISCUSSION

If B & H possessed the sole property interest in the progress payment at the time of the tax lien, the IRS was empowered to levy on those funds and would prevail in the absence of a prior lien. See Avco Delta Corp. Canada Ltd. v. United States, 484 F.2d 692 (7th Cir.1973), certiorari denied, 415 U.S. 931, 94 S.Ct. 1444, 39 L.Ed.2d 490 (1974); 26 U.S.C. § 6321. State law governs the initial inquiry of whether the progress payment constituted property of B & H; federal law determines whether the state-created property right is one which a tax lien can reach. Aquilino v. United States, 363 U.S. 509, 512-514, 80 S.Ct. 1277, 1279-81, 4 L.Ed.2d 1365 (1960). If the progress payment was B & H’s property to which a tax lien could attach, the focus shifts to examining lien priorities, which requires the application of federal law. Id. at 514, 80 S.Ct. at 1280-81.

I. Property Rights

It is to these questions that we now turn, with the first step an examination of whether B & H or some other entity — namely the subcontractors, the District, or the surety— possessed a property interest in the progress payment at the time of the IRS lien.

A The subcontractors

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
41 F.3d 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capitol-indemnity-corporation-v-united-states-of-america-defendant-third-ca3-1995.