The National Shawmut Bank of Boston v. New Amsterdam Casualty Co., Inc.

411 F.2d 843
CourtCourt of Appeals for the First Circuit
DecidedJune 10, 1969
Docket7260_1
StatusPublished
Cited by95 cases

This text of 411 F.2d 843 (The National Shawmut Bank of Boston v. New Amsterdam Casualty Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The National Shawmut Bank of Boston v. New Amsterdam Casualty Co., Inc., 411 F.2d 843 (1st Cir. 1969).

Opinions

COFFIN, Circuit Judge.

In the summer of 1962, Anderson Bros., Inc., a general contractor, entered into three construction contracts with the United States Air Force for work at Otis Air Force Base in Massachusetts and Dow Air Force Base in Maine. As required by the Miller Act, 40 U.S.C. § 270a et seq., Anderson Bros., Inc. applied to the appellee (surety) for payment and performance bonds. Contained in the application for the bonds was an assignment to the surety “ * * * of earned monies that may be due or become due under said contract * * This assignment to the surety was not recorded under the Uniform Commercial Code.

Subsequent to the posting of payment and performance bonds on two contracts, Anderson Bros., Inc. obtained a line of credit from appellant National Shawmut Bank (the Bank).1 As collateral for the loans an assignment of “ * * * all monies due and which shall hereafter become due from the United States * was made to the Bank. A financing statement covering this assignment was filed in compliance with M.G.L.A. c. 106-9, and notice of the assignment was given to the United States as required by the Assignment of Claims Act, 31 U.S.C. § 203 (1964). However, no written notice was given to the surety even though such notice was required by this Act.

In the spring of 1963 the construction contracts were terminated by the United States because of Anderson’s default. The surety completed the work as it was obligated to do under the bonds. The cost of completion was approximately $97,000.

As of the date of termination of the contracts, earned progress payments to-staled $44,202.05. Both the surety and the Bank- seek to satisfy their respective claims from this fund, v/

In December of 1964 a complaint was filed by the Bank naming the surety as defendant in the District Court for the District of Massachusetts. The case was tried to the court without a jury and on September 27, 1968, the district court dismissed the complaint and ordered judgment for the defendant surety. The Bank brings this appeal.2

The critical question which this appeal raises is one which has been, and continues to be, the cause of some uncertainty in the wake of enactment of Article 9 of the Uniform Commercial Code (U.C.C.). It is: to what extent, if any, does the doctrine of subrogation survive the passage of Article 9 of the U.C.C.?

Our effort will be to see what subrogation means in the transaction before us, to see what extent Article 9 is devised to deal with such a transaction, and to apply relevant case law. Subrogation is an old term, rooted in equity, and semantically stemming from words meaning “ask under”. Today we use the parallel phrase, “stand in the shoes of”. The equitable principle is that when one, pursuant to ^obligation — not a volunteer, fulfills the duties of another, he is entitled to assert rights of that other against third "'persons.

1 In this case there is confusion because the tendency is to think of the surety on [845]*845Miller Act payment and performance bonds as standing in the shoes only of the entity it “insures” — the contractor. So long as this one-dimensional concept prevails, logic compels the surety to be assessed as merely one of the contractor’s creditors, and to be subject to the system of priorities rationalized by the Uniform Commercial Code. But the surety in cases like this undertakes., dutie_s,~which-entitle it to step intoCthree) sets of shoes.) When, on default ofTiHe contractor, it pays all the bills of the job to date and completes the job, it stands in the shoes of the contractor insofar as there are receivables due it; in the shoes laborers and material men who have been paid by the surety — who may have had liens; and, not least, in the shoes of government, for whom the job was completed.

This unique accumulation of subrogation rights serves to induce a function that is neither ordinary insurance nor ordinary financing. The business of a construction contract surety is not one of ordinary insurance, for the risk is not aetuarially linked to premiums, nor is there a pooling of risks. Pearlman v. Reliance Ins. Co., 371 U.S. 132, 140 n. 19, 83 S.Ct. 232, 9 L.Ed.2d 190 (1962). Neither is the business one of ordinary financing, for while the surety extends its credit to the owner (the government), as the ultimate guarantee that the job will be done, this is a credit that may either never have to be drawn upon or, if it is drawn upon at all, will in all likelihood be overdrawn. That is, if a contractor defaults, “payment” of the credit depends upon the surety’s competence in economically finishing what somebody else has started. In this hermaphroditic situation, the “security” for the surety is not the fee but a compound of its confidence in the contractor and the opportunity to prevent or minimize its ultimate loss by its right to salvage the debacle by its own performance. Assuming that its confidence is misplaced, the surety receives very little from the contractor but the right to complete the job. Unlike a bank, it does not face specific requests for funds which it is able to link to suitable collateral with subsequent requests determined by assessment of current management and rcurrently available additional security. In case of default, the bank takes its security; the surety must go ahead and perform.

All of this, we think, is relevant background to an interpretation of the Uniform Commercial Code as applied to the kind of security interest at issue. We commence by saying that appellant makes a respectable argument based on the Code. At best, however, we deem the Code not compelling and, on balance, notl focused or directed to the surety’s problem.3 To begin with, we have the exculpatory general principle that “Unless displaced by the particular provisions of this chapter, the principles of law and equity * * * shall supplement its provisions.” M.G.L.A. § 1-103. As we shall see, the Massachusetts Supreme Judicial Court gives impressive weight to this canon in French Lumber Co., Inc. v. Commercial Realty & Finance Co., Inc., 346 Mass. 716, 719, 195 N.E. 507 (1964).

Going on to specifics, we note the definition of “security interest” in M.G. L.A. § 1-201(37) as “an interest in personal property or fixtures which secures payment or performance of an obligation * * * [and which] includes any interest of a buyer of accounts * * * or contract rights * * Neither clause seems to fit the construction contract surety. What secures its payment is really the opportunity, on default, to finish the job and apply any available funds against its cost of completion. This kind of right does not readily set-[846]*846tie under the rubric of “personal property” or “fixtures”. Nor does the surety easily fit the description of a “buyer of * - * contract rights”. We make a similar comment about M.G.L.A. § 9-102(1) (a) which applies the Code “to any transaction * * * which is intended to create a security interest in personal property or fixtures including * * * contract rights; and * * * (b) to any sale of * * * contract rights”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prestige Capital Corp. v. United Surety & Indemnity Co.
245 F. Supp. 3d 349 (D. Puerto Rico, 2017)
Dwyer v. Insurance Co. (In re Pihl, Inc.)
529 B.R. 414 (D. Massachusetts, 2015)
XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
Braunstein v. McCabe (In Re McCabe Group)
424 B.R. 1 (D. Massachusetts, 2010)
Gencor Industries, Inc. v. FIREMAN'S FUND INS.
988 So. 2d 1206 (District Court of Appeal of Florida, 2008)
Cruickshank v. Clean Seas Co.
346 B.R. 571 (D. Massachusetts, 2006)
American States Insurance v. United States
324 B.R. 600 (N.D. Texas, 2005)
First Intl. Bank v. Continental Casualty Co.
17 Mass. L. Rptr. 575 (Massachusetts Superior Court, 2004)
National Fire Insurance v. Fortune Construction Co.
320 F.3d 1260 (Eleventh Circuit, 2003)
Employers Insurance of Wausau v. Town of Northbourough
11 Mass. L. Rptr. 280 (Massachusetts Superior Court, 2000)
Buck Run Baptist Church, Inc. v. Cumberland Surety Insurance Co.
983 S.W.2d 501 (Kentucky Supreme Court, 1998)
Reliance Insurance v. U.S. Bank of Washington, N.A.
143 F.3d 502 (Ninth Circuit, 1998)
State Bank & Trust Co. v. Insurance Co. of the West
132 F.3d 203 (Fifth Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
411 F.2d 843, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-national-shawmut-bank-of-boston-v-new-amsterdam-casualty-co-inc-ca1-1969.