American States Insurance v. United States

324 B.R. 600, 53 Collier Bankr. Cas. 2d 967, 2005 U.S. Dist. LEXIS 1758, 44 Bankr. Ct. Dec. (CRR) 72
CourtUnited States Bankruptcy Court, N.D. Texas
DecidedFebruary 7, 2005
Docket19-30755
StatusPublished
Cited by3 cases

This text of 324 B.R. 600 (American States Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American States Insurance v. United States, 324 B.R. 600, 53 Collier Bankr. Cas. 2d 967, 2005 U.S. Dist. LEXIS 1758, 44 Bankr. Ct. Dec. (CRR) 72 (Tex. 2005).

Opinion

MEMORANDUM OPINION AND ORDER

GODBEY, District Judge.

Before the Court is Appellant American States Insurance Co.’s (“ASIC”) appeal from the Bankruptcy Court’s Orders of January 13, 2004 and March 8, 2004. Because the Court determines that the Bankruptcy Court failed to give full effect to Pearlman v. Reliance and unduly limited a surety’s equitable subrogation right under Texas common law, the Court vacates those orders and finds for ASIC.

I. BACKGROUND

On August 28, 2000, Debtor SSEM Corp. (“SSEM”) entered into a subcontract with Manhattan Construction Co. (“Manhattan”) as general contractor in connection with the City of Dallas Convention Center Expansion and Renovation (the “Project”). ASIC, as surety, issued both performance and payment bonds for .the Project on behalf of SSEM and for the benefit of Manhattan. SSEM performed some work on the subcontract and then defaulted.

Pursuant to the subcontract, SSEM was to submit payment applications monthly for work done. The subcontract further provided that Manhattan was not required to pay SSEM in the event of default, and could retain 5% of the amounts earned by SSEM. Apparently pursuant to those two provisions, Manhattan withheld approximately $88,631.73 (the “Withheld Balances”). Following SSEM’s default, ASIC as surety paid $430,806.66 to complete SSEM’s work on the Project.

On April 11, 2003, SSEM filed a voluntary petition for relief under Chapter 11 of *602 the Bankruptcy Code, which was converted to a Chapter 7 case. One of SSEM’s significant creditors was the Internal Revenue Service (“IRS”), which had filed a pre-petition lien against SSEM for unpaid payroll taxes exceeding $500,000. On August 7, 2003, the United States, on behalf of the IRS, filed a motion for relief from automatic stay, claiming that the Withheld Balances were property of the SSEM estate, and that the IRS had a priority claim on the Withheld Balances due to its pre-petition liens. ASIC disagreed with the IRS’s motion and filed its own motion for relief from automatic stay on August 12, 2003, arguing that it was entitled to the Withheld Balances under its equitable sub-rogation rights and that the Withheld Balances were never earned by SSEM and thus never became part of the estate. The Trustee opposed the IRS’s motion on the basis that the IRS tax lien may be subordinated to other claims under Section 724 of the Bankruptcy Code.

On January 13, 2004, the Bankruptcy Court entered its thoughtful and scholarly order (the “Order”) denying both motions for relief from automatic stay, and ordering that the Withheld Balances be turned over to the Trustee. ASIC timely moved for reconsideration. On March 8, 2004, the Bankruptcy Court issued an order denying the motion for reconsideration, except that it vacated that part of the Order requiring payment of the Withheld Balances to the Trustee. ASIC timely appealed from both of those orders.

This Court has jurisdiction to “hear appeals from final judgments, orders, and decrees from a bankruptcy court.” 28 U.S.C. § 158(a)(1). On appeal, this Court applies the same standard of review as a court of appeals would use reviewing a district court ruling. Id. § 158(c). “[Conclusions of law are reviewed de novo, findings of fact are reviewed for clear error, and mixed questions of fact and law are reviewed de novo.” In re Nat’l Gypsum Co., 208 F.3d 498, 504 (5th Cir.2000) (citation omitted).

II. THE NATURE OF SSEM’S INTEREST

Before considering ASIC’s interests in the Withheld Balances, the Court must briefly consider what basis SSEM had to claim an interest in those balances. ASIC before this Court consistently refers to the balances as unearned, but also indicates the funds were withheld by Manhattan under two contractual provisions. See ASIC Brief at 4, 6. Counsel for the Trustee at oral argument below indicated that the Withheld Balances were entirely re-tainage, and that the debtor had additional claims for earned but unpaid balances not at issue in this appeal. R. 4:322. The Bankruptcy Court’s Order stated: “The funds in question were funds retained under the contract between the Debtor and Manhattan Construction Company, the general contractor for the Project.” Order at 2 (R. 3:241). The nature of SSEM’s interest in the Withheld Balances may have been apparent to all parties and the Bankruptcy Court below, and that may be why the Order does not address that subject in greater detail. See R. 4:318 (“THE COURT. The facts are undisputed ....”) (also reflecting counsel indicating no facts in dispute). Alas, the facts are not so evident to this Court sitting on appeal given the limited appellate record, so the Court must undertake some analysis of the subcontract.

The subcontract was for a face amount of $1,290,000. R. 3:199. SSEM was to make applications for payment monthly for work performed during the month. R. 3:219 (Art. 5.2.1). Subject to a variety of conditions, id. (Art. 5.2.2.-7), SSEM would eventually receive payment for each application. Payment for each approved *603 application, however, was subject to five percent (5%) retainage. 1 R. 3:199. Finally, the subcontract provides: “Notwithstanding any provision of the Subcontract to the contrary, Manhattan is not obligated to make any payment to [SSEM] under the Subcontract if any one or more of the following conditions exists: (a) Subcontractor ... otherwise is in default under the Subcontract or the Contract Documents.” R. 3:219 (Art. 5.3.1(a)).

These two contractual provisions for withholding payment are the only provisions cited to the Court by the parties permitting Manhattan to withhold payment from SSEM. The parties do not point the Court to any factual basis in the record on appeal for SSEM’s claim to the Withheld Balances, such as evidence that SSEM performed work, submitted payment applications that met the requirements of Article 5.2, and was due payment. The Court will, therefore, assume that the Withheld Balances comprise retainage and earned balances that were unpaid due to SSEM’s default, pursuant to Article 5.3.1(a). Because the Court’s analysis is the same for both of those categories, the Court will not dwell further on the distinctions between the two. 2

Both retainage and earned but unpaid balances involve balances for work actually done by SSEM but for which payment had not become due under the subcontract at the time of SSEM’s filing for protection. By having actually performed the work, SSEM appears to have at least an equitable claim to the balances. Moreover, under certain circumstances SSEM could have a valid contractual claim to those balances. For example, if ASIC could have stepped in and completed the subcontract for no more than the unearned balance on the contract, and if SSEM had diligently paid its downstream subcontractors and suppliers, it would have a valid contract claim for the retainage and earned but unpaid balances. Property of the estate includes “all legal or equitable interests of the debtor in property as of the commencement of the case.” 11 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
324 B.R. 600, 53 Collier Bankr. Cas. 2d 967, 2005 U.S. Dist. LEXIS 1758, 44 Bankr. Ct. Dec. (CRR) 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-states-insurance-v-united-states-txnb-2005.