Kappa Development & General Contracting, Inc. v. Hanover Insurance Company

CourtUnited States Bankruptcy Court, S.D. Mississippi
DecidedJuly 2, 2019
Docket17-06046
StatusUnknown

This text of Kappa Development & General Contracting, Inc. v. Hanover Insurance Company (Kappa Development & General Contracting, Inc. v. Hanover Insurance Company) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kappa Development & General Contracting, Inc. v. Hanover Insurance Company, (Miss. 2019).

Opinion

fess Res SO ORDERED, SY, SE 3X .

eal, fir Judge Katharine M. S. CN III □□ udge Katharine M. Samson United States Bankruptcy Judge □□□ OO Date Signed: July 2, 2019 The Order of the Court is set forth below. The docket reflects the date entered.

IN THE UNITED STATES BANKRUPTCY COURT FOR THE SOUTHERN DISTRICT OF MISSISSIPPI IN RE: KAPPA DEVELOPMENT AND CASE NO. 17-51155-KMS GENERAL CONTRACTING INC. DEBTOR CHAPTER 11 KAPPA DEVELOPMENT AND PLAINTIFF GENERAL CONTRACTING INC. V. ADV. NO. 17-06046-KMS HANOVER INSURANCE COMPANY DEFENDANT HANOVER INSURANCE COMPANY COUNTER-CLAIMANT V. KAPPA DEVELOPMENT AND COUNTER-DEFENDANT GENERAL CONTRACTING INC. HANOVER INSURANCE COMPANY THIRD-PARTY PLAINTIFF V. THE FIRST, A NATIONAL BANKING THIRD-PARTY DEFENDANT ASSOCIATION THE FIRST, A NATIONAL BANKING CROSS-CLAIMANT ASSOCIATION V. KAPPA DEVELOPMENT AND CROSS-DEFENDANT GENERAL CONTRACTING INC.

OPINION AND ORDER GRANTING MOTION FOR SUMMARY JUDGMENT BY HANOVER AND DENYING MOTION FOR SUMMARY JUDGMENT BY THE FIRST

This matter is before the Court on cross-motions for summary judgment by Third-Party Plaintiff Hanover Insurance Company (“Hanover”), ECF No. 34, and Third-Party Defendant The First, a national banking association (“The First”), ECF No. 42.1 Each party asserts entitlement to funds (“Disputed Funds”) currently held in part by Plaintiff Kappa Development and General Contracting Inc. (“Kappa”) as Debtor in possession and in part in the registry of the Court. Kappa takes no affirmative position because, whatever the outcome, Kappa expects not to receive any of the Disputed Funds. Answer, ECF No. 29. This proceeding is core under 28 U.S.C. § 157(b)(2)(K) (“determinations of the validity, extent, or priority of liens”). The Disputed Funds were disbursed by the project owners under construction contracts for two unrelated government projects. Kappa, the contractor for both projects, failed to pay all its subcontractors and material suppliers and also failed to pay a workers’ compensation premium. Hanover, Kappa’s surety under both projects’ payment and performance bonds, paid the subcontractors and suppliers and the workers’ compensation premium that Kappa did not pay. Hanover asserts that it is therefore entitled to the Disputed Funds—$130,107.60 for one project and $58,019.77 for the other—under the principle of equitable subrogation, which gives a surety the right to the retainage withheld on public works contracts to ensure project completion and payment of materialmen and laborers. The First asserts that it is entitled to the Disputed Funds because its security interest in Kappa’s accounts receivable, general intangibles, and account

1 “ECF No. ___” indicates a citation to the docket in this adversary proceeding. “Case ECF No. ___” indicates a citation to the docket in the underlying chapter 11 case. proceeds was perfected before the payment and performance bonds were executed and is therefore superior to Hanover’s rights. The right of a surety to retainage is superior to a creditor’s security interest in accounts receivable, general intangibles, and account proceeds regardless of when the creditor’s security

interest was perfected. Accordingly, summary judgment is granted to Hanover and denied to The First. Hanover is entitled to the Disputed Funds in the amounts Hanover was required to pay under each project’s payment and performance bonds. Hanover is also entitled to attorney’s fees and expenses in an amount yet to be determined. The First is entitled to any remaining balance. UNDISPUTED FACTS I. The First’s Perfected Security Interest.

1. On September 3, 2010, Kappa executed a Promissory Note for Loan No. XXX0631 in favor of The First in the principal amount of $850,000.00, as modified by Promissory Note dated December 10, 2011; Promissory Note dated April 9, 2013; Promissory Note dated July 10, 2014; Promissory Note dated October 1, 2015; and Loan Modification Agreement dated March 14, 2017 (together, “2010 Note”). The First MSJ Ex. A, Cl. No. 2, ECF No. 42-1 at 4-14. 2. Also on September 3, 2010, and in connection with the 2010 Note, Kappa executed a Commercial Security Agreement, as modified by Commercial Security Agreement dated December 10, 2011; Commercial Security Agreement dated April 9, 2013; Commercial Security Agreement dated July 10, 2014; and Commercial Security Agreement dated October 1, 2015 (together, “2010 Security Agreement). Id. at 15-39. 3. On September 13, 2010, and in connection with the 2010 Note and the 2010 Security Agreement, The First filed UCC Financing Statement Number 20100194368A, which covered the following collateral: All inventory, accounts receivable and equipment, whether any of the foregoing it owned now or acquired later; all accessions, additions, replacements, and substitutions relating to any of the foregoing, all records of any kind relating to the foregoing, all proceeds relating to any of the foregoing (including insurance, general tangibles and accounts proceeds).

Id. at 40.

4. Kappa is in default on the 2010 Note. The amount due and owing on Loan No. xxx0631 as of June 12, 2017, the date of the bankruptcy petition, was $859,137.50. The First MSJ, Fact No. 6, ECF No. 42 at 4; Hanover Resp., Fact No. 6, ECF No. 51 at 3. II. City of Waveland Project

5. On October 9, 2014, Kappa entered into a contract with the City of Waveland, Mississippi, designated as FEMA Hazard Mitigation Program (“City of Waveland Project”). The First MSJ, Fact No. 7, ECF No. 42 at 4; Hanover MSJ, Fact No. 3, ECF No. 34 at 2. 6. On October 9, 2014, Hanover executed and issued a Performance Bond and a Payment Bond as surety for Kappa with respect to its contract for the City of Waveland Project. Hanover MSJ Ex. 2, Moses Aff. Exs. C, D, ECF No. 34-2 at 11-16. 7. Hanover paid a total of $67,683.92 to the following subcontractors and suppliers that provided labor or materials on the City of Waveland Project and made claims on Hanover’s Payment Bond: Delta Industries - $12,656.34 Soil Tech Consultants- $30,027.58 Precision Pipe & Products Company - $25,000.00 Hanover MSJ Ex. 2, Moses Aff. ¶¶ 14-15, ECF No. 34-2 at 3. 8. Kappa failed to pay these subcontractors and suppliers. Id. ¶ 15. 9. Kappa’s payment defaults on the City of Waveland Project occurred pre-petition. Cl. No. 7 (Delta Industries); Sch. E/F: Creditors Who Have Unsecured Claims, Cl. No. 3.45, Case ECF No. 9 at 28 (Soil Tech Consultants); Sch E/F, Cl. No. 3.41, Case ECF No. 9 at 26 (Precision Pipe & Products Company).

10. The Payment Bond required Hanover to pay subcontractors and suppliers that Kappa failed to pay. Hanover MSJ Ex. 2, Moses Aff. Ex. D, Payment Bond para. beginning “NOW, THEREFORE,” ECF No. 34-2 at 14. 11. During the City of Waveland Project, disputes arose between Kappa, the City of Waveland, and The Pickering Firm, which was the engineering firm of record for the City of Waveland Project. These disputes were still unresolved when Kappa filed its bankruptcy case. The First MSJ, Fact No. 8, ECF No. 42 at 4; Hanover Resp. Fact No. 8, ECF No. 51 at 3. 12. On March 26, 2018, Kappa asked the Court to approve a settlement between Kappa, the City of Waveland, and The Pickering Firm. See The First MSJ Ex. B, Mot. to Approve

Settlement & Compromise, ECF No. 42-2. Under the proposed settlement agreement (“Settlement Agreement”), the City of Waveland would pay Kappa $421,731.76 in “final payment for closeout of the Project.” Id. at 8. Of that amount, $130,107.60 was identified as “Retainage.” Mot. to Approve Settlement & Compromise Ex. 2, Kappa-Waveland Global Settlement, id. at 73. 13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Liquid Air Corp.
37 F.3d 1069 (Fifth Circuit, 1994)
Pearlman v. Reliance Insurance
371 U.S. 132 (Supreme Court, 1962)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States v. TAC Const. Co., Inc.
760 F. Supp. 590 (S.D. Mississippi, 1991)
Reliance Insurance Co. v. First Mississippi Nat. Bank
263 So. 2d 555 (Mississippi Supreme Court, 1972)
Travelers Indemnity Co. v. Clark
254 So. 2d 741 (Mississippi Supreme Court, 1971)
American States Insurance v. United States
324 B.R. 600 (N.D. Texas, 2005)
In Re Jones Construction & Renovation, Inc.
337 B.R. 579 (E.D. Virginia, 2006)
Kimberly-Clark Corp. v. Alpha Building Co.
591 F. Supp. 198 (N.D. Mississippi, 1984)
Bradley Croft v. Jeanette Lowry
737 F.3d 372 (Fifth Circuit, 2013)
Stribling Investments, LLC v. Mike Rozier Construction Company, Inc.
189 So. 3d 1216 (Mississippi Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Kappa Development & General Contracting, Inc. v. Hanover Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kappa-development-general-contracting-inc-v-hanover-insurance-company-mssb-2019.