Stribling Investments, LLC v. Mike Rozier Construction Company, Inc.

189 So. 3d 1216, 2016 Miss. LEXIS 19, 2016 WL 159370
CourtMississippi Supreme Court
DecidedJanuary 14, 2016
Docket2013-CA-02145-SCT
StatusPublished
Cited by10 cases

This text of 189 So. 3d 1216 (Stribling Investments, LLC v. Mike Rozier Construction Company, Inc.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stribling Investments, LLC v. Mike Rozier Construction Company, Inc., 189 So. 3d 1216, 2016 Miss. LEXIS 19, 2016 WL 159370 (Mich. 2016).

Opinions

COLEMAN, Justice,

for the Court:

¶ 1. Stribling Investments, LLC,' sued Mike Rozier Construction Company, Inc;, alleging negligence and negligent construction. The trial court granted Mike Rozier Construction’s Motion for Summary Judgment and dismissed Stribling Investments’ Complaint on the ground that Mike Rozier Construction did not owe a duty to Stri-bling Investments. Stribling Investments appeals. , Holding that the trial court should consider whether the builder-vendor rule applies to Mike Rozier Construction Company, we reverse.

FACTS AND PROCEDURAL HISTORY

¶ 2. In December 2005, D.G. Gluckstadt, LLC' (a nonparty to the suit), bought property on Yándell Road in Gluckstadt, Mississippi, and entered into a lease with Dollar General. Mike Rozier and his son formed D.G. Gluckstadt solely to buy property in Gluckstadt, build a Dollar General Store, and, then sell the property and assign the Dollar General lease to a subsequent buyer.

¶ 3. The lease between D.G. Gluckstadt, as Lessor, and Dollar General, as Lessee, provided D.G. Gluckstadt with Dollar General’s standard plans to build a store and parking lot. ■ Specifically, the lease required D.G. Gluckstadt to

[c]onstruct a building per the attached Lessee approved site plan (showing building ingress and egress) using the Lessee’s Prototype Design Package (both documents attached hereto and made a part of the Lease). Demised Premises to be complete, in compliance with all governing code authorities and ready for Lessee’s immediate occupancy. Dimensions of Demised Premises to be as listed.

The Dollar General prototype plans included grading and paving options for the heavy-duty section of the'parking lot, but provided an exception in the event that a [1218]*1218certified geotechnical report specified an alternate .method of construction. ■

¶ 4. D.G. Gluckstadt then sent a project budget to Dollar General :to help determine the ’ lease amount, calculating a $30,000 cost of' building the parking lot. The project budget also stated that an additional $80,000 would be ' used for “earthwork,” including grading, excavating, filling, and degrassing the site. D.G. Gluckstadt claims that it then hired Mike Rozier Construction Company, Inc. (“Rozier Construction”), to construct the building and the parking lot. Mike Rozier also owns Rozier Construction. No formal written agreement existed between Rozier Construction and D.G. Gluckstadt. According to Mike Rozier, “I do not write contracts to myself.”

¶ 5. Before construction, Ladner Testing Laboratories was hired to test the soil and recommend the' best way to build the parking lot. Rozier Construction did nbt follow the construction recommendations from Ladner Laboratories, nor did it excavate the ground according to the project budget. Rozier Construction degrassed the area for the parking lot, .installed between three and eight feet of fill, and laid a slab. Rozier Construction did not check the moisture level of the soil. It also did not utilize any steel rebarb or geotechnical fabric to stabilize the parking lot. Rozier Construction claims that it informed D.G. Gluckstadt of all of the above, and that D.G. Gluckstadt waived the duty of workmanlike construction. Rozier Construction states that D.G. Gluckstadt “made an informed economic decision” to construct a less-expensive parking lot than that recommended by Ladner Laboratories and Dollar General’s prototype plan, all considered with “full knowledge and appreciation of the costs and benefits of the construction design and methods.”

¶6. Other than Mike Rozier’s depositions, the record does not contain any evidence that Rozier Construction communicated the means of construction to D.G. Gluckstadt, let alone that D.G. Gluckstadt approved those means. In fact, during his deposition, Rozier stated that he was not sure whether he had ever seen the 2005 Ladner Report. Further, as Rozier owned both companies, for Rozier Construction to present facts and options to D.G. Gluck-stadt would mean that Mike Rozier presented them to himself (and, perhaps, his son.)

¶ 7. In 2006, at the end of construction, D.G. Gluckstadt sold the building and land to Stribling Investments, LLC, and assigned to it the Dollar General lease. Prior to purchase, Stribling procured an inspection performed by a licensed contractor that did not reveal any visual cracks or other issues in the parking lot. The contract between D.G. Gluckstadt and Stribling did not disclose the subsoil conditions. The land sale contract between D.G. Gluckstadt arid Stribling contained an “as-is clause” that stated:

It is understood and agreed that the property is being sold “as is”; that Buyer has, or will have prior to the Closing Date, Inspected the Property; and that neither Seller nor Agent makes any representation or warranty as to the physical condition or value of the Property or its suitability for Buyer’s intended use.

After the, lot began showing signs of deficiencies and deterioration and an April 2012 analysis and report from Ladner Testing Laboratories indicated poor construction, Stribling contacted Rozier Construction and made a demand for repairs. When Rozier Construction did not respond, Stribling filed suit against Rozier Construction in the Circuit Court of Madison County, alleging negligent design and negligent construction of the. parking lot.

[1219]*1219¶8. The trial judge granted summary judgment in favor of Rozier Construction. The trial judge found that “[t]he plaintiff has not shown any ‘summary judgment’ proof that the Defendant failed to construct the parking, lot in question according to the specifications required according to its verbal contract with D.G.” The instant appeal followed.

ISSUE

¶ 9. We address the, issue of whether genuine issues of material fact exist and preclude summary judgment in favor of Rozier Construction. Resolving this question requires us to address the following:

I. Whether D.G. Gluckstadt indeed-waived the duty owed by Rozier Construction such that Stribling - cannot invoke it.
II. Whether the sale contract’s “as-is” clause bars Stribling’s suit against Rozier Construction.

STANDARD OF REVIEW

¶ 10. The grant or denial of a summary judgment- motion is reviewed de novo. Town Creek Master Water Mgmt. Dist. of Lee, Pontotoc, Prentiss, Union Ctys. v. Webb, 93 So.3d 20, 24 (¶ 9) (Miss.2012). “[The] Court, as well as the . trial court, considers all evidentiary matters before it-admissions in pleadings, answers to interrogatories, depositions, affidavits, etc.” Rein v. Benchmark Constr. Co., 865 So.2d 1134, 1142 (¶ 24) (Miss.2004). The, Court views the evidence in a light most favorable to the nonmoving party. “The moving party has the burden to show no genuine issue of material fact exists.” Cade v. Beard, 130 So.3d 77, 81 (¶ 11) (Miss.2014). The opposing party must then set forth specific facts to show a genuine issue for trial. Id. Summary judgment is proper if “there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law.” Rein, 865 So.2d at 1142 (¶ 25).

ANALYSIS

¶ 11. We reverse the grant of summary judgment because whether Rozier Construction and D.G. Gluckstadt had a builder-vendor relationship serves as an issue of material fact. If so, D.G.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
189 So. 3d 1216, 2016 Miss. LEXIS 19, 2016 WL 159370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stribling-investments-llc-v-mike-rozier-construction-company-inc-miss-2016.