In Re Jones Construction & Renovation, Inc.

337 B.R. 579, 2006 Bankr. LEXIS 852, 2006 WL 335886
CourtUnited States Bankruptcy Court, E.D. Virginia
DecidedJanuary 4, 2006
Docket05-31107
StatusPublished
Cited by7 cases

This text of 337 B.R. 579 (In Re Jones Construction & Renovation, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Jones Construction & Renovation, Inc., 337 B.R. 579, 2006 Bankr. LEXIS 852, 2006 WL 335886 (Va. 2006).

Opinion

MEMORANDUM OPINION

DOUGLAS O. TICE, JR., Chief Judge.

Hearing was held October 12, 2005, on the motion of Western Surety Company to approve payment to it of contract funds arising under two pre-petition construction contracts of the debtor, Jones Construction & Renovation, Inc. Western Surety also asserts its right to debtor’s claim against the owners of one of the projects, Christopher Newport University. The trustee opposes the motion. Following argument at hearing, the court reserved ruling and requested the parties to submit proposed findings of fact and conclusions of law, which have now been received.

For reasons stated in this opinion, the court adopts the position asserted by Western Surety and will grant its motion.

Facts.

Pre-petition, debtor Jones Construction & Renovations, Inc., engaged in a general contracting business. The issues in this case arise from two public construction projects that Jones Construction contracted to perform and for which the company contracted with Western Surety to underwrite the requisite payment and performance bonds.

Payment and performance bonds on the two projects were issued by Western Surety, as surety, naming Jones Construction as its principal and co-obligor and the property owners as obligees. Each of the performance bonds was issued to secure Jones Construction’s performance of its obligations to the owner under the general contract for which it was issued, and each of the payment bonds was issued for the protection of all persons who might qualify as claimants for labor or materials furnished directly to Jones Construction or one of its subcontractors.

The construction contracts at issue here are (1) the Christopher Newport University (CNU) Football Stadium Project, awarded to Jones Construction on January 28, 2003, for which Western Surety issued Bond No. 58607433 dated January 31, 2003, in the amount of $1,439,500.00; and (2) the Henrico Area Mental Health Project for Henrico County, Virginia, awarded to Jones Construction on February 4, 2003, for which Western Surety issued Bond No. 58607439 dated February 4, 2003, in the amount of $638,599.00. In each instance, the bonds were requested by Jones Construction, issued by Western Surety, and furnished by Jones Construction to the respective obligees in accordance with the terms and conditions of the general contracts for which they were issued and the provisions of Virginia’s Little Miller Act, Virginia Code §§ 2.2-4336 to 2.2-4342, a part of the Virginia Public Procurement Act, Virginia Code §§ 2.2-4300 et seq.

Western Surety’s bonds on these projects were issued in accordance with a general agreement of indemnity with Jones Construction dated November 13, 2002. Under this agreement, Jones Con *582 struction bound itself to indemnify Western Surety and to hold it harmless from and against all demands of whatever nature as a result of Western Surety’s issuance of bonds. Jones Construction secured its performance under the surety agreement, pursuant to paragraph 19 of the agreement, by executing a security agreement and financing statement. Under this security agreement, the agreement of indemnity was recorded as an original financing statement on February 17, 2004, under the provisions of the UCC, Virginia Code §§ 8.9-101 et seq. 1

In addition, pursuant to paragraph 9 of the indemnity agreement, Jones Construction assigned to Western Surety its rights under any underwritten construction contract. This assignment clause provided for the transfer to Western Surety, upon Jones Construction’s default, of all sums due under the contracts, including any remaining contract funds held by the obli-gors under the contracts.

After executing the construction contracts, Jones Construction encountered financial problems, which would later cause it to file bankruptcy. On November 17, 2003, Western Surety received a claim from United Rentals, Inc., against the contract payment bond for the CNU Football Stadium Project in the amount of $23,030.62. 2 Western Surety later received several other claims due to the inability of Jones Construction to satisfy many of its payment obligations under the CNU project to subcontractors, laborers and materialmen. By February 8, 2005, Western Surety had paid claims in connection with the CNU project in at least the amount of $334,879.00 and had $120,216.72 in claims pending. Although no claims have been paid on the Henrico project, Western Surety has been presented with four claims from that project totaling $44,348.03.

On February 8, 2005, Jones Construction filed this voluntary chapter 7 case, and Harry Shaia, Jr., was appointed trustee. The creditor schedules of the petition list Western Security as an unsecured creditor with a claim in an unknown value. The personal property schedules list approximately $1,450,000.00 of accounts receivables arising from the CNU and Henrico projects; this figure consists of a balance of $50,000.00 due from Henrico County and a balance of $1,400,000.00 owed by CNU. The Henrico receivable is for remaining contract funds held by the county in the actual amount of $49,669.02. The CNU receivable includes funds held by CNU in the undisputed principal amount of $152,054.93 for approved change orders, and the balance is a pre-petition claim by Jones Construction for additional compensation, including extra work and unapproved change orders. This claim, in the amount of $1,210,608.50, has not been approved for payment by CNU. Western Surety’s right to the CNU claim is the second contested issue in this case.

*583 Conclusions of Law.

Western Surety asserts that neither the remaining contract funds nor the pre-petition claim Jones Construction filed against CNU constitute property of the estate in which the trustee holds an interest by virtue of the assignment provisions in the indemnity agreement and the doctrine of equitable subrogation. 3

The trustee does not dispute that, under the doctrine of equitable subrogation, Western Surety is entitled to the $152,054.93 in remaining contract funds held by CNU. He does dispute that under the doctrine of equitable subrogation, Western Surety is entitled to the $49,669.02 held by Henrico County because, although Western Surety has received claims on that project, it has yet to sustain a loss. The trustee also disputes Western Surety’s rights by assignment to the $49,669.02 held by Henrico County and the debtor’s pre-petition claim against CNU. He asserts the assignments contained in paragraph 9 of the indemnity agreement are nothing more than a mere security interest in an assignment of'collateral.

The court agrees with the legal analysis presented by Western Surety in its proposed conclusions of law concerning Western Surety’s rights under the doctrine of equitable subrogation and by assignment under the indemnity agreement.

WESTERN SURETY’S RIGHT TO EQUITABLE SUBROGATION

The doctrine of equitable subrogation “arises when a contractor defaults on its obligations and a surety completes the work called for by the contract [or] pays all of the related bills.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
337 B.R. 579, 2006 Bankr. LEXIS 852, 2006 WL 335886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-jones-construction-renovation-inc-vaeb-2006.