Tri-City Service District v. Pacific Marine Dredging & Construction (In Re Pacific Marine Dredging & Construction)

79 B.R. 924, 5 U.C.C. Rep. Serv. 2d (West) 1110, 1987 Bankr. LEXIS 1776, 16 Bankr. Ct. Dec. (CRR) 915
CourtUnited States Bankruptcy Court, D. Oregon
DecidedOctober 9, 1987
Docket99-32660
StatusPublished
Cited by15 cases

This text of 79 B.R. 924 (Tri-City Service District v. Pacific Marine Dredging & Construction (In Re Pacific Marine Dredging & Construction)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-City Service District v. Pacific Marine Dredging & Construction (In Re Pacific Marine Dredging & Construction), 79 B.R. 924, 5 U.C.C. Rep. Serv. 2d (West) 1110, 1987 Bankr. LEXIS 1776, 16 Bankr. Ct. Dec. (CRR) 915 (Or. 1987).

Opinion

MEMORANDUM OPINION

ALBERT E. RADCLIFFE, Bankruptcy Consultant.

This matter comes before the court on cross motions for summary judgment filed by three of the defendants; Pacific Marine Dredging and Construction (debtor), International Fidelity Insurance Company (International), and Key Bank of Oregon (Key Bank).

The parties have consented to a determination of this proceeding by the bankruptcy consultant. Accordingly, this opinion is entered pursuant to Miscellaneous Order No. 87-21 of the United States District Court for the District of Oregon Matter of Radcliffe, 72 B.R. 20 (1987). The parties have stipulated and this court finds that this adversary proceeding is a core proceeding as defined in 28 U.S.C. § 157.

FACTS

The parties have stipulated to the following facts.

The debtor is a marine contracting company.

In early 1984, Key Bank, provided debtor with a $500,000 line of credit for operating purposes. Key Bank took a security interest in all of debtor’s accounts and general intangibles, then existing or thereafter acquired, to secure this line of credit. Key Bank perfected its security interest in February, 1984 by filing UCC Financing Statements in both Oregon and Washington. Debtor currently owes Key Bank $319,-204.66 on this secured line of credit, plus accrued interest. In addition, Key Bank has incurred costs and attorney fees of not less than $25,898.05.

On September 27, 1984, debtor entered into a contract with plaintiff, (the contract) under which debtor was to provide certain services on a construction project (construction of the Willamette Interceptor 1A Outfall Oregon City Interceptor and River Crossing). The total consideration to be paid to debtor under the contract was $884,693.

The contract required that debtor execute and deliver to plaintiff two bonds, each in an amount equal to the contract price. One, for the faithful performance of the contract (performance bond) and the *926 other for the payment of all laborers, mate-rialmen and other sub-contractors (payment bond).

The contract also required that debtor promptly pay its sub-contractors for the work which they provided under the contract. It further provided that plaintiff would make periodic progress payments to debtor based upon percentages of work completed and that plaintiff would retain 5% of each of these progress payments until final completion and acceptance of the work covered by the contract.

Concerning the final payment owed under the contract, the contract, in section 7.01C states that:

Before the owner pays the contractor his final payment for the work, the contractor shall sign and deliver to the owner a release of liens and claims sworn to under oath and duly notarized. The release shall state that the contractor satisfied all claims and indebtedness of every nature in any way connected with the work, including ... amounts due to sub-contractors, accounts for labor performed and materials furnished ...

Prior to the execution of the contract, Debtor obtained its payment and performance bonds from International, each in the amount of $884,693. Both bonds were issued on September 12, 1984 and properly executed on that date.

Debtor commenced work on the construction project on October 14, 1984. Much of the work called for under the contract was performed by sub-contractors of debtor.

Pursuant to the contract, debtor billed plaintiff for progress payments. From February 22, 1985 to August 23, 1985 four progress payments were paid, by plaintiff to debtor, in the total amount of $747,-909.72.

The fifth progress billing is dated November 1, 1985. It states that 98.79% of the work to be done under the contract had been completed. That billing requests an earned amount of $82,368.80. Plaintiff withheld payment of this sum upon notice of debtor's bankruptcy filing and upon notice that various sub-contractors had claims for unpaid goods and services.

On November 8, 1985 debtor filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code.

The contract was not terminated by plaintiff or debtor. Debtor substantially completed the contract. Certain minor punch list items were required to be performed prior to final completion of the contract. Plaintiff requested, post-petition, that debtor complete the minor work. Notice was given to International and debtor that if the work was not performed, plaintiff would issue a unilateral change order deleting the work from the contract and would deduct the estimated value thereof from the contract price. Plaintiff would then accept the job. Plaintiff received no response from either debtor or International. The unilateral change order was entered and approved by plaintiffs county commissioners.

Debtor did not make payments due to all sub-contractors for their services on the contract. From November 7, 1985 to March 3, 1986, 11 sub-contractors made claims against the payment bond for unpaid amounts due. International has paid the sub-contractors an aggregate total of $372,794.17. All of these payments were made after debtor filed its Chapter 11 petition (post-petition).

On November 5, 1986, plaintiff commenced this adversary proceeding in the nature of interpleader. Plaintiff deposited $117,393.20 into court. This amount represents the remaining contract balance (after deductions by plaintiff resulting from the unilateral change order), including the 5% retainage from progress payments, plus accrued interest thereon.

The following additional facts are established by the record in this proceeding.

The debtor has answered plaintiffs complaint contending that the amount interpled into court is insufficient. By an order entered herein on December 31, 1986, that issue has been severed and is not part of the matters dealt with by the cross motions for summary judgment.

*927 Two of the defendants, Bill Bernert Tugboat Service, Inc. and Columbia Fence Company have been dismissed by an order entered, herein, on May 29, 1987 on the basis that these defendants have been paid by International and make no further claim to the funds which have been interpled (the fund).

Finally, there are competing claims by the parties requesting that they be awarded attorneys’ fees resulting from this adversary proceeding. The issue of attorneys’ fees is not, however, before this court for the purpose of resolving the cross motions for summary judgment.

STATUTORY BACKGROUND

A brief overview of Oregon’s statutory payment scheme for public contracts is in order. Oregon law defines a public contract as any purchase, lease or sale by a public agency (owner), of personal property, public improvements or services other than agreements which are for personal services. O.R.S. 279.011(4).

O.R.S. 279.312 in part provides:

Every public contract shall contain a condition that the contractor shall:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
79 B.R. 924, 5 U.C.C. Rep. Serv. 2d (West) 1110, 1987 Bankr. LEXIS 1776, 16 Bankr. Ct. Dec. (CRR) 915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-city-service-district-v-pacific-marine-dredging-construction-in-re-orb-1987.