First Alabama Bank v. Hartford Accident & Indemnity Co.

430 F. Supp. 907, 21 U.C.C. Rep. Serv. (West) 1451, 1977 U.S. Dist. LEXIS 16961
CourtDistrict Court, N.D. Alabama
DecidedMarch 10, 1977
DocketCiv. A. CA 75-G-2138-S
StatusPublished
Cited by16 cases

This text of 430 F. Supp. 907 (First Alabama Bank v. Hartford Accident & Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Alabama Bank v. Hartford Accident & Indemnity Co., 430 F. Supp. 907, 21 U.C.C. Rep. Serv. (West) 1451, 1977 U.S. Dist. LEXIS 16961 (N.D. Ala. 1977).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

GUIN, District Judge.

This case involves resolution of the competing claims of a construction contractor’s assignee bank and its surety to contract progress payments disbursed by the owner of the project to the surety which immediately disbursed equivalent funds, by means of its own checks, to unpaid subcontractors and suppliers designated by the contractor as due such funds.

Because of the several contentions of the assignee bank, herein after stated, a more lengthy than usual statement of pertinent facts is called for.

In December, 1971, Marsh and Daniel, Inc. (the “Contractor”) entered into a financing arrangement with Exchange Security Bank, predecessor of plaintiff herein (the “Bank”), and in connection therewith executed a general assignment of all contract proceeds, both present and future; this general assignment was recorded in accordance with the Alabama Uniform Commercial Code on December 8, 1971. Thereafter from time to time the Contractor borrowed from the Bank and from time to time repaid to the Bank, a portion of its debts. On February 21, 1975, the Contractor consolidated its then outstanding indebtedness to the Bank executing a single note for $91,739.23. Subsequently, the Contractor borrowed an additional $25,000 from the Bank on February 28, 1975, and an additional $16,000 on April 4, 1975.

On May 14, 1974, in order to induce the defendant (the “Surety”) to issue labor and material payment bonds and performance bonds on its behalf, the Contractor executed a general indemnity agreement, which assigned, transferred and conveyed to the Surety all rights of the Contractor in any construction contracts into which it might enter, or additions or alterations thereto, conditioned, inter alia, on the failure, refusal or inability of the Contractor to perform the terms and provisions of any such contract, or the failure, delay, refusal or inability of the Contractor to pay for work and labor performed on any such contracts.

The Surety did not then, nor has it ever, recorded its general indemnity agreement in accordance with the Alabama Uniform Commercial Code.

On October 8, 1974, the Contractor entered into a contract (the “Contract”) with the University of Montevallo Board of Trustees (the “Owner”) for the construction and erection, within 210 days, of an environmental safety building (the “Project”) in accordance with plans and specifications prepared by the Owner’s architect, Dampi *909 er-Harris & Associates (the “Architect”). One condition of the Contract was that the Contractor was required to post both a performance bond and a labor and material bond, each in the amount of $192,000, the bid price on the Project, in favor of the Owner; the labor and material payment bond was also required by Title 50, Section 16, Code of Alabama, since the Project constituted a public work within the meaning of that statute. A further condition of the Contract was that the Contractor would promptly pay all who supplied labor and materials for the Project.

The Contractor obtained from the Surety and posted the required labor and material payment bond and the performance bond, and was issued a notice to proceed on October 10, 1974, making May 6, 1975, the completion date on the Project.

The Contractor commenced performance immediately, and submitted several monthly pay requests which were paid by the Owner, but as early as December, 1974, the Architect began receiving complaints from some of the Contractor’s subcontractors and suppliers that they were not receiving payment from the Contractor for work performed and materials supplied to the Project. Because of these complaints, the Architect, acting pursuant to the terms and conditions of the contract which authorized withholding of funds upon notification that subcontractors and suppliers were not being paid, on January 29,1975, notified the Contractor that he would not authorize payment by the Owner on a future payment request of the Contractor without certification by the Contractor that subcontractors and suppliers had been paid by the Contractor for work performed and materials delivered in the previous month; i. e., that previous payments made pursuant to the Contractor’s payment requests had in fact been used to pay subcontractors and suppliers.

The Owner and the Architect continued to receive complaints from the Contractor’s subcontractors and suppliers that they had not been paid for work and materials supplied and billed for; e. g., on February 7, 1975, the Architect notified the Contractor that he had received notice from Hackney Steel company, the Contractor’s steel supplier for the Project, that its billing to the Contractor of October 28,1974, for $2,644.46 had not been paid. Because of these complaints, on February 27, 1975, the Architect again notified the Contractor that certification of payment must be submitted with future estimates before they would be honored, and on or about March 9, 1975, the Architect met with the Contractor to discuss the contractor’s unpaid bills and the complaints of its subcontractors and suppliers. Nevertheless, the Owner and the Architect continued to receive complaints of nonpayment from the Contractor’s subcontractors and suppliers and during the month of March, 1975, it came to their attention that payroll checks issued to some of the Contractor’s laborers on the Project had been returned marked “Insufficient Funds”.

Although the Contractor had received payment from the Owner on its estimate submitted for work performed and materials supplied during January, 1975, it had not paid all of its subcontractors and suppliers’ billings for work performed and materials supplied by them during that month. The Contractor’s estimates submitted for work done and materials supplied during February and March, 1975, had not been paid because the Contractor could not provide the certificates of payment for previous work required of it by the Architect, and this state of affairs had come to the attention of the Surety, which, in late March, 1975, sent a representative to Birmingham. The Contractor’s president indicated to the Surety’s representative that the Contractor lacked sufficient funds to continue the Project and requested that the Surety finance it. The Surety’s representative declined to do so but instead arranged to meet with the Architect in order to arrange for payments direct from the Owner to the Contractor’s subcontractors and suppliers. On March 31, 1975, at the Surety’s request, the Contractor notified the Owner that further payments on the Project should be made payable to the Contractor in care of the Surety and transmitted directly to the Surety.

*910 The Architect, the Contractor and the Surety met several times during the last week of March, 1975, and agreed that at a meeting to be held at the Owner’s offices the Owner’s check for work done and materials supplied by the Contractor during the months of February and March would be delivered to the Surety which would immediately deliver the Surety’s checks to the Contractor’s unpaid subcontractors and suppliers.

The contemplated meeting occurred on April 10, 1975, and was attended by the Owner, the Contractor, the Surety, the Architect and a number of the Contractor’s unpaid subcontractors and suppliers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American States Insurance v. United States
324 B.R. 600 (N.D. Texas, 2005)
Ohio Casualty Insurance v. Vermeer Manufacturing Co.
298 F. Supp. 2d 575 (W.D. Kentucky, 2004)
Interfirst Bank Dallas, N.A. v. United States Fidelity & Guaranty Co.
774 S.W.2d 391 (Court of Appeals of Texas, 1989)
Transamerica Ins. Co. v. Barnett Bank of Marion County, NA
540 So. 2d 113 (Supreme Court of Florida, 1989)
Balboa Insurance v. Bank of Boston Connecticut
702 F. Supp. 34 (D. Connecticut, 1988)
Transamerica Ins. Co. v. Barnett Bank of Marion County, NA
524 So. 2d 439 (District Court of Appeal of Florida, 1988)
In RE v. Pangori & Sons, Inc.
53 B.R. 711 (E.D. Michigan, 1985)
Fidelity & Cas. Co. of NY v. CENTRAL, ETC.
409 So. 2d 788 (Supreme Court of Alabama, 1982)
Alaska National Bank of the North v. Gwitchyaa Zhee Corp.
639 P.2d 984 (Alaska Supreme Court, 1981)
Lambert v. Maryland Cas. Co.
403 So. 2d 739 (Louisiana Court of Appeal, 1981)
In Re Kuhn Const. Co., Inc.
11 B.R. 746 (S.D. West Virginia, 1981)
Waterhouse v. McDevitt and Street Co.
387 So. 2d 470 (District Court of Appeal of Florida, 1980)
Earl Dubey & Sons, Inc. v. MacOmb Contracting Corp.
296 N.W.2d 582 (Michigan Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
430 F. Supp. 907, 21 U.C.C. Rep. Serv. (West) 1451, 1977 U.S. Dist. LEXIS 16961, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-alabama-bank-v-hartford-accident-indemnity-co-alnd-1977.