McAtee v. United States Fidelity and Guaranty Co.

401 F. Supp. 11, 18 U.C.C. Rep. Serv. (West) 220, 1975 U.S. Dist. LEXIS 13052
CourtDistrict Court, N.D. Florida
DecidedApril 1, 1975
DocketPCA 74-112
StatusPublished
Cited by10 cases

This text of 401 F. Supp. 11 (McAtee v. United States Fidelity and Guaranty Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McAtee v. United States Fidelity and Guaranty Co., 401 F. Supp. 11, 18 U.C.C. Rep. Serv. (West) 220, 1975 U.S. Dist. LEXIS 13052 (N.D. Fla. 1975).

Opinion

DANIEL HOLCOMBE THOMAS, District Judge.

The above-styled cause, a Miller Act case, was heard by the Court, without a jury, on stipulated facts and arguments of counsel and taken under submission on March 5, 1975. Having considered the stipulated facts, exhibits and arguments of counsel, the Court makes the following findings of fact and conclusions of law:

FINDINGS OF FACT

1. This action was brought by the plaintiff, James R. McAtee, as Trustee in Bankruptcy for Chavis Construction, Inc. (Chavis) to recover in behalf of the bankrupt estate funds in the possession of the defendant, United States Fidelity and Guaranty Company (USF&G), said funds being payments made by the United States pursuant to two construction contracts with the bankrupt Chavis. The plaintiff also seeks to retain for the bankrupt estate an additional payment made by the United States and now in the plaintiff’s possession. The defendant denies that the plaintiff is entitled to any of the payments and, accordingly, seeks to recover the payment in the plaintiff’s possession. In addition, both parties seek a determination as to which of them would be entitled to a portion of the contract price due on one of the contracts but withheld by the United States as liquidated damages, if such were eventually paid.

2. USF&G is the surety on Performance Bonds and Labor and Material Payment Bonds issued in conjunction with two construction contracts entered into by Chavis with the United States.

3. By contract dated September 14, 1970, contract # 14-16-0004-272 in the amount of $522,165.66, Chavis contracted with the United States for the construction of a marine laboratory in Panama City, Florida. Back charges and change orders in the sum of $13,036.11 brought the total contract price to the sum of $535,201.77.

4. Chavis and USF&G, as principal and surety, respectively, executed and delivered to the United States, as obligee, their Performance Bond in the sum of $522,165.66 and their Labor and Material payment bond in the sum of $261,182.83, both dated September 17, 1970.

5. By contract dated April 24, 1970, contract # 62467-70-7040 Chavis contracted with the United States for repairs to building 672, Naval Air Station, Pensacola, Florida. Change orders in the sum of $165.10 increased the total contract price of $90,292.00 to the sum of $90,457.10.

6. Chavis and USF&G, as principal and surety, respectively, executed and delivered to the United States, as obligee, their performance bond in the sum of $90,292.00 and their labor and mate *13 rial payment bond in the sum of $45,146.00, both dated September 17, 1970.

7. By letters to USF&G and to the United States Department of Interior, dated April 4, 1972, Chavis advised that it would be unable to complete the construction of the marine laboratory and called upon USF&G to complete.

8. By correspondence dated April 11, 1972, from the United States Department of Interior to Chavis, the aforesaid contract was defaulted and USF&G was requested and permitted to complete the contract.

9. By correspondence dated April 4, 1972, to the officer in charge of construction, Pensacola Naval Air Station, Pensacola and USF&G, Chavis advised that it was unable to complete the contract and requested USF&G to complete the job.

10. Thereafter USF&G proceeded to complete the contract for the marine laboratory under its performance bond and to pay outstanding labor and material bills under its payment bond. The cost to USF&G of completion was $8,998.34, and the labor and materials paid for by USF&G were in the sum of $90,620.15. Such costs were paid by USF&G between April 21, 1972 and October 11, 1972.

11. Payments received by USF&G from the United States totalled $43,026.-17. In addition, one payment in the amount of $1,346.84 is being held by the plaintiff.

12. Receipts and payments on the contract for the marine laboratory as set forth above are summarized as follows:

Labor and Materials $90,620.15
Completion 8,998.34
TOTAL PAID $99,618.49
Receipts from U.S.A. $44,373.01
(Including $1,346.84 held by Plaintiff)
NET LOSS TO USF&G $55,245.48

13. In addition to the above, the United States has withheld payment of $21,300.00 as liquidated damages under the contract for 142 days delayed completion at the rate of $150.00 per day. USF&G and the Trustee have contested some part of the liquidated damages, but the United States has refused to pay any of such retained balance of the contract.

14. On the Naval Air Station job in Pensacola, USF&G was called upon to pay the sum of $1,675.00 for labor and materials under its labor and material payment bond and received from the United States the sum of $465.00 as final payment on the contract price. This resulted in a net loss to USF&G of the sum of $1,209.90 under its bond. These receipts and disbursements were made during November, 1972.

15. Chavis filed a voluntary petition in bankruptcy and was adjudicated a bankrupt on July 14, 1972.

16. James R. McAtee, plaintiff herein, was appointed Trustee in Bankruptcy for Chavis Construction Company, Inc., on August 14, 1972 and is presently serving in that capacity. It is in such capacity that plaintiff has filed this present suit seeking payment into the bankrupt estate the sums received by USF&G from the United States on the two contracts and to retain for the estate of the said bankrupt and the general creditors of the estate the payment from the United States now in his possession in the sum of $1,346.84.

17. USF&G did not file a financing statement or Uniform Commercial Code form with the Secretary of State nor with the Clerk of the Court of either Bay or Escambia Counties showing a security interest of USF&G in the above mentioned contracts.

18. Plaintiff filed this instant suit on or about September 4, 1974 in four counts. In Counts III and IV of his complaint plaintiff demanded an accounting of defendant. Defendant in answer to said counts acknowledged that plaintiff was entitled to an accounting and has furnished the same. Plaintiff is satisfied with said accounting and abandons those claims of Counts III and IV.

*14 19. Plaintiff claims his interest in the contract proceeds on behalf of the estate of the bankrupt based upon the failure of the defendant, USF&G to file a financing statement or Uniform Commercial Code form with the Secretary of State or the Clerks of the Court of Bay and Escambia Counties, the counties in which the respective contracts of Chavis with the United States were to be performed and that defendant failed to put plaintiff as Trustee on notice of its security interest in the contracts. Defendant, by its answer admits that it has not filed a financing statement with the Secretary of State or with the Clerks of the Court of Bay or Escambia Counties. Defendant further admits receipt of payments from the United States.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reynolds v. McLaren Group, LLC
S.D. California, 2024
In Re Eastern Marine, Inc.
104 B.R. 421 (N.D. Florida, 1989)
Transamerica Ins. Co. v. Barnett Bank of Marion County, NA
540 So. 2d 113 (Supreme Court of Florida, 1989)
Transamerica Ins. Co. v. Barnett Bank of Marion County, NA
524 So. 2d 439 (District Court of Appeal of Florida, 1988)
In Re Kuhn Const. Co., Inc.
11 B.R. 746 (S.D. West Virginia, 1981)
First Alabama Bank v. Hartford Accident & Indemnity Co.
430 F. Supp. 907 (N.D. Alabama, 1977)
Finance Co. of America v. United States Fidelity & Guaranty Co.
353 A.2d 249 (Court of Appeals of Maryland, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
401 F. Supp. 11, 18 U.C.C. Rep. Serv. (West) 220, 1975 U.S. Dist. LEXIS 13052, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcatee-v-united-states-fidelity-and-guaranty-co-flnd-1975.