Travelers Indemnity Co. v. West Georgia National Bank

387 F. Supp. 1090, 1974 U.S. Dist. LEXIS 6740
CourtDistrict Court, N.D. Georgia
DecidedSeptember 16, 1974
DocketCiv. A. 991
StatusPublished
Cited by7 cases

This text of 387 F. Supp. 1090 (Travelers Indemnity Co. v. West Georgia National Bank) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Travelers Indemnity Co. v. West Georgia National Bank, 387 F. Supp. 1090, 1974 U.S. Dist. LEXIS 6740 (N.D. Ga. 1974).

Opinion

*1092 ORDER

ALBERT J. HENDERSON, Jr., District Judge.

This is a diversity action for a declaratory judgment to determine the respective rights of the parties to certain monies and property. The plaintiff, Travelers Indemnity Company (hereinafter referred to as “Travelers”), as surety of General Constructors, Inc. (hereinafter referred to as “General”) brought this suit against the West Georgia National Bank (hereinafter referred to as the “bank”) which managed General’s accounts on a construction project for the Housing Authority of the City of Carrollton, Carroll County, Georgia (hereinafter referred to as “Authority”), also a defendant. The bank answered and filed a counterclaim against Travelers, as General’s surety, to recover $8,964.02 plus cost which allegedly represents a portion of an unpaid loan to General for labor and materials.

The case came on for trial before the court without a jury and at the conclusion thereof, the parties were directed to submit written arguments and briefs. They have complied with that direction and the case is ready for decision.

General contracted with the Authority on January 23, 1970, for construction of a low rental housing project. In connection with that contract, Travelers, which in 1962 entered into an agreement of indemnity with General, issued a performance and payment bond on this project in the amount of $973,826.00. Thereafter, General opened an account with the bank and made arrangements for the extension of unsecured loans, the last being for $30,000.00 in March of 1971. During April of 1970, in accordance with its loan agreement with the bank, General authorized the Authority to deposit all progress payments from the project directly into its account at the bank.

On April 23, 1971, the bank received a check for $21,197.86 dated April 22, 1971, and credited General’s account with that sum. At the same time, however, construction on the Authority’s project halted because of General’s financial inability to complete the job. By this time, all the parties were aware of General’s lack of funds and the resulting work stoppage. A formal notice of default was sent to the Authority on April 22, 1971 and shortly thereafter Travelers financed the completion of the construction.

In order to recover part of its outstanding loan of $30,000.00 the bank, on April 23, 1971, “set off” the deposit against General’s past due note. This set off left a deficiency remaining on the note and the bank attached certain items of equipment found at the job site. A judgment against General was obtained by the bank in the State Court of Carroll County for the unpaid balance of $8,904.02 and a fi fa issued. Thereafter, three pieces of equipment were sold for $11,000.00 and that sum placed in the registry of the court on May 29, 1973.

The issues pending for determination are :

(1) (a) Is the surety, Travelers, entitled to recover from the defendant bank the sum of $21,197.86, representing the amount of the progress payment it received on April 23, 1971, after General’s formal notice of default to the Authority ?
(b) If not, can the surety recover this amount from the Authority ?
(2) (a) Is the plaintiff entitled to recover from the Authority the remaining portion of the contract price less the amount withheld for uncompleted and unsatisfactory work?
(b) To what extent, if any, are liquidated damages to be deducted from the balance due on the contract in favor of the Authority ?
(3) (a) Can the bank recover from the surety the full amount of its March, 1971 loan to General ?
(b) Is the bank entitled to recover from the surety the sum of $8,964.02 plus costs representing the remaining *1093 balance due on the monies advanced to General in March, 1971 ?
(4) Which party, the plaintiff or the defendant bank, is entitled to the proceeds of the sale of the attached equipment presently in the registry of the court?

The leading case in this circuit on the right of recovery of progress payments as between the defaulting contractor’s surety and an assignee bank is Fidelity & Deposit Co. of Maryland v. Scott Brothers Construction Co., 461 F.2d 640 (5th Cir. 1972) which follows the reasoning of American Fire & Casualty Co. v. First Nat’l Bank of New York, 411 F.2d 755 (1st Cir. 1969) and National Shawmut Bank of Boston v. New Amsterdam Casualty Co., 411 F.2d 843 (1st Cir. 1969). In Scott Brothers, 461 F.2d at 642, the court expounded the following rule:

The District Court, in resolving the issue, correctly perceived and followed the distinction between, on the one hand, retainages and earned but unpaid progress payments and, on the other hand, progress payments that already have been paid before the contractor defaults. As to the former category of contract funds a surety enjoys a claim superior to that of an assignee bank, whereas the bank’s rights take priority of the surety’s as to contract payments made before default. See National Shawmut Bank of Boston v. New Amsterdam Cas. Co., 411 F.2d 843, 848 (1st Cir. 1969); Trinity Universal Ins. Co. v. United States, 382 F.2d 317, 320 (5th Cir. 1967). . . .
The distinction reflects the theory that a surety “is not only a subrogee of the contractor, . . . but also a subrogee of the [owner] and entitled to any rights the [owner] has to the retained funds.” Trinity Universal, supra, 382 F.2d at 320. “But for the surety’s completion of the work, the obligee on the bond, be he owner or prime contractor, would have been entitled to apply the funds against the cost of completion. It is the surety’s performance which frees the funds, and, . . . the surety is entitled to them.” American Fire & Cas. Co. v. First National City Bank of N. Y., 411 F.2d 755, 758 (1st Cir. 1969). . Any payments made by the owner prior to default, however, are attributable to the contractor’s performance, not the surety’s, and the owner, to whom the surety becomes subrogated, may not rightfully withhold such payments so long as the contractor is in material compliance with its obligations under the contract. American Cas. Co. of Reading, Pa. v. Line Materials Indus., 332 F.2d 393, 395 (10th Cir. 1964).

This principle of recovery was emphasized in National Shawmut Bank of Boston, supra, 411 F.2d at 848:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fidelity & Cas. Co. of NY v. CENTRAL, ETC.
409 So. 2d 788 (Supreme Court of Alabama, 1982)
Lambert v. Maryland Cas. Co.
403 So. 2d 739 (Louisiana Court of Appeal, 1981)
Earl Dubey & Sons, Inc. v. MacOmb Contracting Corp.
296 N.W.2d 582 (Michigan Court of Appeals, 1980)
United States Fidelity & Guaranty Co. v. Leach
438 F. Supp. 295 (M.D. Georgia, 1977)
In Re Merts Equipment Co.
438 F. Supp. 295 (M.D. Georgia, 1977)
First Alabama Bank v. Hartford Accident & Indemnity Co.
430 F. Supp. 907 (N.D. Alabama, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
387 F. Supp. 1090, 1974 U.S. Dist. LEXIS 6740, Counsel Stack Legal Research, https://law.counselstack.com/opinion/travelers-indemnity-co-v-west-georgia-national-bank-gand-1974.