Associated Mechanical Corp. v. Martin K. Eby Construction Co.

67 F. Supp. 2d 1375, 1999 U.S. Dist. LEXIS 15094, 1999 WL 787245
CourtDistrict Court, M.D. Georgia
DecidedSeptember 29, 1999
Docket5:95-cv-00094
StatusPublished
Cited by2 cases

This text of 67 F. Supp. 2d 1375 (Associated Mechanical Corp. v. Martin K. Eby Construction Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Mechanical Corp. v. Martin K. Eby Construction Co., 67 F. Supp. 2d 1375, 1999 U.S. Dist. LEXIS 15094, 1999 WL 787245 (M.D. Ga. 1999).

Opinion

ORDER

OWENS, District Judge.

Defendant Martin K. Eby Construction Company, Inc. (“Eby”) has filed a motion for summary judgment on plaintiff Associated Mechanical Contractors, Inc.’s (“AMC”) claims for final contract payment and pre-judgment interest on such payment. While Eby argued in its briefs that it was not obligated to pay AMC the final amount (“retainage”) because of unsatisfied conditions precedent, Eby has now paid a portion of the amount making this issue moot. However, the issues of whether the remaining portion of the principal is' due and whether pre-judgment interest on the entire final payment is due remain. Having carefully considered the motion, the related caselaw and statutes, and the file as a whole, the Court enters the following order.

I. Background

This action arises from the construction of the Dooley Correctional Institution (“Project”) for the Georgia Building Authority (“Owner”). Eby was the prime contractor on the Project, and entered into a subcontract (“Subcontract”) with AMC. AMC was to perform certain mechanical and related work for the Project under the Subcontract. AMC began its work shortly after January 29, 1990, and had completed its work by the end of 1992.

This Court has previously denied all of AMC’s claims by partial summary judgment, except AMC’s claim for' final payment and interest.

At the time of filing this motion Eby had paid AMC the full Subcontract amount, except for AMC’s final payment, known as retainage. Eby claimed that the retainage payment was not yet due under the Subcontract, because the Owner was still withholding it from Eby. Eby claimed that AMC’s interest claim is the only matter remaining in dispute before the Court.

Section 14 of the Subcontract provides for final payment:

The retained percentage and/or final progress payment shall be paid to [AMC] after (1) the work performed by the Subcontractor is completed satisfactorily; (2) the Subcontractor has paid all of its creditors as to these obligations which arise from or related to Subcontractor’s performance of this subcontract; (3) the Contractor has been paid by the Owner for the Work set forth in this Subcontract; (4) Subcontractor completes, executes, and files with the Contractor a release on the forms supplied by the Contractor; and (5) all disputes, claims, liens, causes of actions and/or lawsuits which are related in any way to this Subcontract or the Subcon *1377 tractor’s performance of the Work are resolved.

Subcontract § 14.

Eby argued that three of these conditions had not been met when it filed its motion for summary judgment.

Eby argued that AMC’s final payment was also subject to the provisions of Eby’s contract with the Owner (“Prime Contract”). The Prime Contract provisions require Eby to provide an affidavit stating that there are no claims of any kind “which might constitute a lien upon the property of the Owner.” Prime Contract, Articles E-28, E-32. They also permit the Owner to withhold payment if any claims are filed. Id., Article E-26. AMC agreed to be bound by these provisions, and “to assume towards [Eby] all of the obligations and responsibilities which [Eby], by the Prime Contract, assumes towards the Owner.... ” Subcontract, § 1.

AMC filed its original complaint in this civil action on March 4, 1995. It sought only additional compensation by way of a claim for an equitable adjustment due to delays and disruptions experienced by AMC. A First Amended Complaint was filed by AMC on March 22, 1995, stating substantially the same claims for relief as the original complaint. Eby filed three separate motions for summary judgment, and this Court granted the “Third Motion for Summary Judgment,” by Order entered on November 19, 1997, which effectively disposed of the AMC claim for equitable adjustment.

In July, 1999, after Eby filed this motion, AMC received $231,820.09 as payment for the unpaid balance. AMC claims that an unpaid balance of $23,943.28 still remains unpaid. AMC claims interest is due on the both amounts. AMC seeks interest on the $231,820.09 that accrued between the filing of its Second Amended Complaint on or about May 20, 1997, and the date of receipt of the $231,820.09 amount on or about July 9, 1997. AMC also seeks interest accruing on the remaining $23,943.28 yet unpaid.

II. Discussion

A. Issues Now Moot

The Court notes that at least partial payment on the Subcontract retainage has been paid to AMC. In July, 1999, $231,-820.09 was paid to AMC by Eby. Therefore, the Court finds that AMC’s claim for payment of retainage principal is moot to the extent already paid by Eby.

B. Summary Judgment Standard

Federal Rule of Civil Procedure 56(c) provides that summary judgment may be entered in favor of the movant where “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is (1) no genuine issue as to any material fact and that (2) the moving party is entitled to judgment as a matter of law.” Federal Rules of Civil Procedure 56(c). See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Irby v. Bittick, 44 F.3d 949, 953 (11th Cir.1995).

The evidence and all reasonable factual inferences arising from it must be viewed in the light most favorable to AMC, the non-moving party. See Welch v. Celotex Corp., 951 F.2d 1235, 1237 (11th Cir.1992). The movant’s entitlement to judgment as a matter of law is satisfied where “the non-moving party has failed to make a sufficient showing on an essential element of her case with respect to which she has the burden of proof.” Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). Once a party has moved for summary judgment and properly supported its motion, the burden shifts to the nonmovant to create, through the evidentiary forms listed in Federal Rules of Civil Procedure 56(c), genuine issues of material fact necessitating a trial. Id. at 324, 106 S.Ct. 2548.

C. Conditions Precedent

Eby’s motion for summary judgment focuses on the language of the Subcontract. *1378

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Powell Company v. McGarey Group, LLC
508 F. Supp. 2d 1202 (N.D. Georgia, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
67 F. Supp. 2d 1375, 1999 U.S. Dist. LEXIS 15094, 1999 WL 787245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-mechanical-corp-v-martin-k-eby-construction-co-gamd-1999.