Nature-Tech, LLC v. Hartford Fire Insurance Company

CourtDistrict Court, D. Maryland
DecidedMarch 28, 2022
Docket1:19-cv-02053
StatusUnknown

This text of Nature-Tech, LLC v. Hartford Fire Insurance Company (Nature-Tech, LLC v. Hartford Fire Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nature-Tech, LLC v. Hartford Fire Insurance Company, (D. Md. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

: NATURE-TECH, LLC :

v. : Civil Action No. DKC 19-2053

: HARTFORD FIRE INSURANCE COMPANY, et al. :

MEMORANDUM OPINION Presently pending and ready for resolution in this case stemming from a heavily litigated construction project is a motion for summary judgment filed by Plaintiff Nature-Tech, LLC (“Nature- Tech”). (ECF No. 27). The issues have been fully briefed, and the court now rules, no hearing being necessary. Local Rule 105.6. For the following reasons, the motion will be granted in part and denied in part.1 I. Factual Background This case revolves around construction of a hotel and transition space “adjacent to the existing Maryland Live! Casino in Hanover, Maryland[.]” (ECF No. 27-1, at 1; 29-1, at 3). The Casino owner, PPE Casino Resorts MD LLC (“the Owner”), hired Tutor

1 On March 19, 2022, eight months after its initial motion, Nature-Tech moved for leave to file a supplemental summary judgment memorandum. (ECF No. 31). The motion will be denied as untimely. The proposed memorandum raises even more questions about whether the record regarding withheld retainage payments is complete. Perini Building Corporation (“Tutor Perini”) to be the general contractor for the project. (ECF No. 27-1, at 2 ¶ 1; ECF No. 29- 1, at 4). Tutor Perini hired Defendant Mortensen Woodwork, also

known as Capitol Woodwork, LLC, (“Capitol”) to furnish and install millwork. (ECF No. 27-2, at 1). A payment bond executed by Capitol and Defendant Hartford Fire Insurance Company (“Hartford”) guaranteed Capitol’s labor and material payments. (ECF No. 27-3, at 4). Capitol hired Nature-Tech to fabricate millwork worth $1,430,297.80 for the project. (See ECF Nos. 27-4; 27-5; 27-6). At some point the project got behind schedule, (ECF No. 29- 4, at 7 (Pickarts, Pawlowski, and Sellars Depo.)), and Capitol requested additional money from Tutor Perini for acceleration costs, (ECF No. 27-16, at 4-5 (Sukalo Depo.)). This resulted in a dispute between Capitol and Tutor Perini that is being litigated separately in Maryland state court but is central to this case. See PPE Casino Resorts Maryland LLC v. Tutor Perini Building Corp.,

No. C-02-CV-19-002049 (Anne Arundel Cnty. Circuit Court 2019). Capitol contends that Tutor Perini breached their contract when it refused to approve additional payments. (ECF No. 29-7, at 6, 10- 11; see generally ECF No. 29-22). Tutor Perini, which is not party to the suit here, disputes this characterization and accuses Capitol of holding the project “hostage” to its payment demands by “refusing to go ahead and continue with work of any kind.” (ECF No. 27-16, at 4-5). Tutor Perini purportedly terminated Capitol because of the delays. (ECF Nos. 27-8; 27-9; 29-23, at 7-8). Capitol believes otherwise, asserting that Tutor Perini plotted with Nature-Tech to manufacture Capitol’s termination and

replacement by Nature-Tech. (ECF No. 29-1, at 5, 10). Nature-Tech’s alleged coordination with Tutor Perini gave rise to the dispute here. On that and other grounds, Capitol refused to pay Nature-Tech’s outstanding billings. Nature-Tech claims that Defendants’ denial of payment violated the terms of their payment bond. Capitol counterclaims that Nature-Tech breached their contract by soliciting Tutor Perini and, through the same conduct, tortiously interfered with Capitol’s contract with Tutor Perini. A. Nature-Tech and Tutor Perini’s Meeting in April or May 2018 Nature-Tech’s alleged solicitation and inducement begins with a series of meetings at Nature-Tech’s facilities. Tutor Perini and Capitol twice inspected the Nature-Tech facilities in early 2018. (ECF No. 29-4, at 6). Afterward, Capitol said Tutor Perini was “welcome to continue [its] visits to Nature Tech to survey materials in the manufacturing process as needed.” (ECF No. 30- 2, at 1). Nature-Tech and Tutor Perini were told, however, that “anything that related to scheduling and delivery . . . had to go through Capitol.” (ECF No. 29-3, at 8; see ECF Nos. 29-4, at 17-

18; 29-8, at 1; 30-2, at 1). Nevertheless, Tutor Perini began to reach out separately to Nature-Tech, and Nature-Tech did not bring Capitol into the conversations. (ECF No. 29-4, at 26). Critically, Tutor Perini executives arranged for a meeting at

Nature-Tech’s facilities in April or May 2018. Tutor Perini called Nature-Tech’s CEO on a Friday afternoon and asked to visit the next Monday. (ECF No. 29-4, at 8-9, 64). Although Tutor Perini initiated the contact, Nature-Tech requested that a specific Tutor Perini executive with decision-making authority attend, as it had been instructed to do by Capitol. (Id., at 63-64). Nature-Tech assumed Tutor Perini wanted to inspect the millwork again. (ECF No. 29-4, at 10). Having a decision-maker included was necessary because Nature-Tech was “scrambling to try and get things done [and] [t]here was a lot of mistrust back and forth.” (See id., at 8, 64). The meeting was not an inspection. Instead, Tutor Perini

executives “laid out their plans for terminating Capitol [by declaring default] and taking over their contract[.]” (ECF No. 29- 4, at 8). Tutor Perini told Nature-Tech that its contract with Capitol gave it the right to request information about Nature- Tech’s work. (Id.; see also id., at 13-14). It specifically asked to inspect Nature-Tech’s purchase orders with Capitol. (Id., at 13). It told Nature-Tech that, after Capitol was terminated, it would write Nature-Tech purchase orders to complete work that was not already under contract. (Id., at 14). Nature-Tech did not know of Tutor Perini’s plans before the meeting. (Id.). B. Nature-Tech and Tutor Perini’s Subsequent Communications in June After the meeting, Nature-Tech told Tutor Perini that it wasn’t “doing anything until there was a termination, and [it was] moving forward on [its] contract [with Capitol] as it was.” (ECF No. 29-4, at 16, 49). But Nature-Tech continued to respond to Tutor Perini’s requests to identify outstanding work, which Capitol may not have known about. (ECF Nos. 29-9 (June 12); 29- 13, at 2 (June 22); see ECF No. 29-4, at 27).2 It called a list

of outstanding work provided in a June 12 email “a starting point for us to talk about.” (ECF No. 29-9). At times, the distinction between possible future work and current work blurred. In the same June 12 exchange, Tutor Perini suggested it would be sending information to create shop drawings, seemingly for headboards that Nature-Tech incorrectly believed were outside the scope of its purchase orders with Capitol. (See ECF Nos. 29-10, at 2; 29-4, at 30, 34). Nature-Tech asked whether they were “in a holding pattern until [they] hear[d] back from [Tutor Perini] for an approval to do” the work. (Id.).

2 Nature-Tech’s assertion that Capitol was aware of certain discussions is one of many examples in which it disputes Capitol’s factual assertions by citing deposition materials not in the record. (See ECF No. 30, at 17 (citing page 98 which is not included in Defendants’ excerpt, (see ECF No. 29-4, at 27-28))). Tutor Perini responded that it expected Capitol would be terminated imminently. It had a meeting the next day with “the client” and hoped it would “be on-board with our direction” and

give Tutor Perini “the authority to issue a Letter of Intent and follow up with a PO in a couple of days.” (ECF No. 29-10, at 2; see also ECF No. 29-4, at 15, 32). Tutor Perini then asked Nature- Tech if it was “stopping everything [it] had in line that was for [Capitol] [] to make a clean break?” (ECF No. 29-10, at 2). Nature-Tech replied, “We are continuing with only the items we have a P.O. for with Capitol and all other items we would like to continue to finish the job with you.” (Id., at 1; see also ECF No. 29-4, at 33).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Kunda v. C.R. Bard, Inc.
671 F.3d 464 (Fourth Circuit, 2011)
Coyle v. Englander's
488 A.2d 1083 (New Jersey Superior Court App Division, 1985)
Cruz v. Silva
984 A.2d 295 (Court of Special Appeals of Maryland, 2009)
Sharrow v. State Farm Mutual Automobile Insurance
511 A.2d 492 (Court of Appeals of Maryland, 1986)
Aon Risk Services, Inc. v. Liebenstein
2006 WI App 4 (Court of Appeals of Wisconsin, 2005)
Brew City Redevelopment Group, LLC v. Ferchill Group
2006 WI 128 (Wisconsin Supreme Court, 2006)
Burbank Grease Services, LLC v. Sokolowski
2006 WI 103 (Wisconsin Supreme Court, 2006)
Fowler v. Printers II, Inc.
598 A.2d 794 (Court of Special Appeals of Maryland, 1991)
General Builders Supply Co. v. MacArthur
179 A.2d 868 (Court of Appeals of Maryland, 1962)
Atlantic Contracting & Material Co. v. Ulico Casualty Co.
844 A.2d 460 (Court of Appeals of Maryland, 2004)
Kutzin v. Pirnie
591 A.2d 932 (Supreme Court of New Jersey, 1991)
Cochran v. Norkunas
919 A.2d 700 (Court of Appeals of Maryland, 2007)
MacKlin v. Robert Logan Associates
639 A.2d 112 (Court of Appeals of Maryland, 1994)
Laboratory Corp. of America v. Hood
911 A.2d 841 (Court of Appeals of Maryland, 2006)
Kronovet v. Lipchin
415 A.2d 1096 (Court of Appeals of Maryland, 1980)
Chung Shin v. Shalala
166 F. Supp. 2d 373 (D. Maryland, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Nature-Tech, LLC v. Hartford Fire Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nature-tech-llc-v-hartford-fire-insurance-company-mdd-2022.