MEMORANDUM OPINION On July 12, 2019, Plaintiff Nature-Tech, LLC (“Nature-Tech”) commenced this action, which stems from a heavily litigated construction project, asserting a single breach of payment bond claim against Defendants Capitol Woodwork, LLC (“Capitol”) and Hartford Fire Insurance Company (“Hartford”). A bench trial was held on September 28 and September 29, 2022. After carefully considering the parties’ exhibits, the testimony of the witnesses, the pretrial submissions and post-trial briefs, and the oral arguments of counsel, this court now issues findings of fact and conclusions of law pursuant to Fed.R.Civ.P. 52(a). For the reasons articulated below, judgment will be entered in favor of Defendants Capitol and Hartford. I. Background This case involves work done as part of the construction of a hotel and transition space at the Maryland Live! Casino in Hanover, Maryland (“the Project”).1 The casino owner, PPE Casino Resorts Maryland LLC (“the Owner”), hired Tutor Perini Building Corporation (“Tutor Perini”) as the general contractor for the

Project—neither the Owner nor Tutor Perini is party to this lawsuit. (PTX 1 at 1; ECF No. 1).2 Tutor Perini hired Capitol, also known as Mortensen Woodwork, to furnish and install millwork for the Project. (PTX 1). Capitol and Hartford executed a payment bond to guarantee payment for Capitol’s labor and materials. (PTX 2). The payment bond states that Capitol and Hartford jointly and severally, bind themselves . . . to the Contractor [Tutor Perini] . . . to pay for labor, materials[,] and equipment used or reasonably required and furnished for use in the performance of the Subcontract [between Tutor Perini and Capitol], which is incorporated in this bond by reference and pursuant to which this bond is issued.

Capitol hired Nature-Tech to fabricate millwork for the Project, and the two companies entered into a Master Subcontract Agreement (“the Agreement”). (PTX 3). Article 12.5 of the Agreement provides that Nature-Tech, as the Subcontractor, would submit applications for payment to Capitol, the Contractor, and the “Contractor shall pay ninety (90%) percent of the amount of

1 A detailed factual background is also set out in a prior opinion. (ECF No. 33); Nature-Tech, LLC v. Hartford Fire Ins. Co., No. 19-cv-2053-DKC, 2022 WL 899417, at *1-4 (D.Md. Mar. 28, 2022).

2 “PTX” refers to exhibits offered by Nature-Tech at trial, and “DTX” refers to exhibits offered by Capitol and Hartford. the Application, withholding ten (10%) percent retainage (the ‘Retainage’) from each Application.” (PTX 3 at ¶ 12.5). Article 12.8, titled “Conditions Precedent,” provides:

Retainage and/or the Final Application payment shall be paid to Subcontractor only after; (a) the Work (including any punch-list work) is completed satisfactorily and accepted by Owner and Contractor; . . . and (e) all disputes, claims, liens, causes of action, and/or lawsuits which are related in any way to this Agreement or to Subcontractor’s performance of the Work are resolved.

(PTX 3 at ¶ 12.8).

While construction on the Project was underway, a dispute arose between Capitol and Tutor Perini related to delays in the construction schedule. This dispute, among other issues, is being litigated as part of a lawsuit that is presently pending in Maryland state court. See PPE Casino Resorts Maryland LLC v. Tutor Perini Building Corp., No. C-02-CV-19-002049 (Anne Arundel Cnty. Circuit Court 2019). Capitol, Hartford, Tutor Perini, and the Owner are among the parties involved in that litigation, but Nature-Tech is not. On July 31, 2018, Capitol advised Nature-Tech that it was “demobilizing the installation team” at the construction site while it tried to work out its dispute with Tutor Perini and that “[n]o deliveries [were] to be scheduled to the jobsite” unless specifically requested by Capitol. (PTX 47). Nature-Tech continued to fabricate millwork but did not ship it, per Capitol’s request. (PTX 50). On August 23, 2018, Tutor Perini issued to Capitol a 48-hour “Notice to Cure,” and on August 30, 2018, Tutor Perini declared Capitol in default and terminated it for failure

to cure. (PTX 8, 51). At the time of Capitol’s termination, Nature-Tech had not yet completed all outstanding purchase orders with Capitol. Tutor Perini notified Nature-Tech of its intent for Nature-Tech to complete that work through new contracts with Tutor Perini. (PTX 53). It later issued Nature-Tech purchase orders for shipments and millwork. (DTX 49-52). However, Tutor Perini advised Nature- Tech to seek payment from Hartford for certain items that were included in purchase orders from Capitol prior to the termination. (DTX 22). Nature-Tech requested payment from Capitol for millwork completed and shipped, millwork in progress, and outstanding

retainage, and Capitol refused. Nature-Tech submitted a claim against the payment bond for $473,961.70 in unpaid billings. (DTX 23). Hartford reviewed Nature-Tech’s claim and analyzed thirty- two items that Tutor Perini and Nature-Tech had identified as outstanding as of August 30, 2018, the termination date of Capitol’s contract. Hartford determined that Capitol was not responsible for twelve of the items, so it deducted $140,629.13 from the claim amount. It also determined that Capitol was entitled to keep $135,603.18 as retainage. The remaining amount that Hartford determined was due to Nature-Tech was $197,729.39. $157,280.56 had already been paid, and Hartford released the remaining $40,448.83 to Nature-Tech. (DTX 24).

Nature-Tech has conceded that Capitol was not responsible for some of the twelve items, but it has maintained that it is entitled to payment from the payment bond for five items, worth $66,827.25, as well as $127,855.46 of the retainage.3 The five items are: 1) “Foot rail for main bar,” shipped 2/5/19: $7,350.00 2) “Series #104 Prefunction entrance door surrounds,” shipped 1/16/19: $25,364.00

3) “Series #9 Coat Check and surrounding wood veneer wall panels,” shipped 2/5/19: $18,936.00

4) “Taller Base molding for in Ballroom,” shipped 9/1/18: $6,342.25

5) “Ballroom Doors 180 A, B, C, D, E, G, & H,” shipped 9/24/18: $8,835.004

(DTX 46). In a May 9, 2019, email to a Vice President of Tutor Perini, a Nature-Tech Senior Project Manager listed those items and described them as “items that were shipped to the job site AFTER Capitol was terminated from the project,” adding that they were “all items that were ordered by Capitol, but we were told to

3 At trial, Nature-Tech provided a revised retainage amount, which excluded retainage that had been drawn from items for which Nature-Tech had billed but not completed.

4 Hartford’s report lists the amount it withheld for the Ballroom Doors as $8,335.00. (DTX 23 at 9, 11). It is unclear whether the difference in digits is a typographical error or reflective of a disagreement in calculations. ship by Tutor Perini so that the project could continue to move towards completion.”5 The Nature-Tech employee went on to state that “these items need to be added to you[r] claim against Capitol

and the[n] we would receive compensation from Tutor Perini.” The Vice President of Tutor Perini responded that he understood that Hartford refused to pay for those items and said, “We are including [them] in our claim.” (DTX 46). Nature-Tech filed the instant lawsuit to recover the portion of its claim against the payment bond for which it argues Hartford improperly denied payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Nature-Tech, LLC v. Hartford Fire Insurance Company, (D. Md. 2022).

Nature-Tech, LLC v. Hartford Fire Insurance Company (Nature-Tech, LLC v. Hartford Fire Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Gonzales
520 U.S. 1 (Supreme Court, 1997)
General Builders Supply Co. v. MacArthur
179 A.2d 868 (Court of Appeals of Maryland, 1962)
Atlantic Contracting & Material Co. v. Ulico Casualty Co.
844 A.2d 460 (Court of Appeals of Maryland, 2004)
Duff v. Trenton Beverage Co.
73 A.2d 578 (Supreme Court of New Jersey, 1950)
Lange v. Board of Education
37 A.2d 317 (Court of Appeals of Maryland, 1944)
East Coast Repair v. United States
16 F.4th 87 (Fourth Circuit, 2021)
Thomas Orr Trucking & Forwarding Co. v. Metropolitan Surety Co.
73 A. 541 (Supreme Court of New Jersey, 1909)