General Builders Supply Co. v. MacArthur

179 A.2d 868, 228 Md. 320, 1962 Md. LEXIS 451
CourtCourt of Appeals of Maryland
DecidedApril 16, 1962
Docket[No. 223, September Term, 1961.]
StatusPublished
Cited by19 cases

This text of 179 A.2d 868 (General Builders Supply Co. v. MacArthur) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Builders Supply Co. v. MacArthur, 179 A.2d 868, 228 Md. 320, 1962 Md. LEXIS 451 (Md. 1962).

Opinion

Horney, J.,

delivered the opinion of the Court.

In an action brought by an owner against the builder as principal and the surety on a performance bond for the construction of a dwelling, the Circuit Court for Montgomery County entered a judgment against the surety as well as the builder (though in varying amounts) and the surety appealed.

In October of 1959 Bruce M. MacArthur (the owner) entered into a memorandum agreement with the Construction and Development Corporation of Maryland (the builder or principal) under which the builder proposed to construct a dwelling for $29,431, and the owner made a deposit on account of $1,000. Subsequently, before the construction contract was executed, the builder suggested that a “precut house” be purchased from the Hog Island Lumber Company (Hilco) at a cost of $10,000. The owner adopted the suggestion and paid the builder another $2,500 on account for the precut lumber.

The construction contract, to which the plans and specifications were attached, was executed in February of 1960. Between October and February the owner had paid to the builder an additional sum of $931, or a total of $4,431, on account of the contract price. And, when the construction contract had *323 been signed, the owner went beyond the requirements of the contract and sent a check direct to Hilco for $7,500, at the request of the builder, for the balance due on the lumber. But almost immediately thereafter the owner, having become concerned about the ability of the builder to meet its obligations for labor and materials, stopped payment on the check and demanded a performance bond to assure compliance with the construction contract.

In the area in which the dwelling was under construction, the General Builders Supply Company, Inc., had an agency agreement with Hilco whereby it received a commission on the prefabricated houses sold in its territory. On other occasions the agent had become surety on other performance bonds. And, when Hilco was informed of the stop order and demand for bond, it promptly communicated with its agent (sometimes referred to as surety) and arranged for it to become surety on the bond demanded by the owner. The agent, because it. was reluctant to be bound for so large a sum, hesitated at first to sign the bond, but when Hilco insisted and intimated that, the agent might lose its franchise if it did not go on the bond,, the agent as surety executed the bond with the builder as principal and delivered it to the owner. The obligation of the bond! was to the effect that if the principal did not perform its contract with the owner, then the surety would “remedy the default” or “complete the contract in accordance with its terms and conditions.” Promptly thereafter the owner paid Hilco the balance due of $7,500.

After the signing of the construction contract, sums slightly in excess of the balance of the contract price were deposited from time to time in a joint bank account and all withdrawals therefrom were signed by or on behalf of the owner and builder. But by May of 1960 it became evident that there would not be sufficient funds to complete the house. As of that time the financial status of the builder was such that it could not meet current obligations. And, although $29,598.69 had been expended, there were unpaid bills totaling $7,904.31. At this point the owner refused to make further advances and as a result no further work was done by the builder. The surety was notified of the builder’s default, but it denied lia *324 bility, and refused to complete the house. And when the surety also defaulted, the owner proceeded to complete the construction of the house. The total cost, including extras costing $2,901, was $46,433.24. And, since the contract price was $29,431, the difference between that price and the actual cost of $43,532.24 was $14,101.24. Judgment was entered against the builder for the difference, but because $4,431 had been paid the builder before the performance bond was executed, a judgment for $9,670.24 was entered against the surety.

Relying primarily on Maryland Rule 828 b, the appellee moved to dismiss the appeal because the record was so inadequate that it would not permit a determination of the questions presented. The appellant’s record extract is indeed skimpy, but we think there is enough in the record extract and the appellee’s appendix to decide most, if not all, of the questions raised. We therefore deny the motion to dismiss and will dispose of the appeal on its merits insofar as it is possible.

On appeal the surety contends (i) that the performance bond was unenforceable for want of assent; (ii) that the bond was unenforceable for want of consideration; (iii) that it was relieved of liability because the owner breached the contract; and-(iv) that the owner failed to prove his claim in accordance with the established rules of evidence.

(i)

The claim here is that the owner cannot enforce the performance bond against the surety because its signature was •obtained under such circumstances of business necessity or "Compulsion as to render the signing involuntary and excuse -the -surety from liability. The claim is without merit. Even if -.it is assumed, without deciding, that the execution of the bond ■was obtained by the exertion of “economic compulsion,” the :record .discloses that such coercion as was used was the act of the agent’s own principal and not that of the owner, for the only evidence of coercion on the part of the owner is that he stopped payment of the check for lumber and demanded the execution of a performance bond. There is nothing in the record to show that the owner did anything more than insist *325 that someone act as surety for the builder: it was Hilco that insisted that its agent become the surety on the bond. And, since there is no claim that the owner was bound to advance the balance due on the lumber or make other advances not required by the terms of the construction contract, it appears that the owner was within his rights when he demanded that he be furnished with a bond assuring performance of the contract by the builder. See Montauk Corp. v. Seeds, 215 Md. 491, 501, 138 A. 2d 907 (1958), for a statement of the doctrine of business or economic compulsion.

(ü)

The next contention is that there was a lack of legal consideration flowing from the owner to the surety for the surety-ship agreement which renders the performance bond unenforceable as to the surety. This contention is likewise with-cut merit.

The record shows that the surety undertook the surety-ship at the request or insistence of Hilco and that the consideration for the undertaking was a matter between the principal (Hilco) and the agent (General Builders). That the surety was the agent of Hilco is not disputed. And the record shows that the agent, who had acted as surety in previous transactions, undertook to act as surety in this instance in order to forestall the possibility of losing a valuable franchise right. This we think was sufficient consideration to support the suretyship agreement. It was not necessary for the surety to also receive consideration from the owner in order to make the performance bond enforceable as to it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wildewood Operations v. WRV Holdings
Court of Special Appeals of Maryland, 2023
Middlebrook Tech, LLC v. Moore
849 A.2d 63 (Court of Special Appeals of Maryland, 2004)
Atlantic Contracting & Material Co. v. Ulico Casualty Co.
844 A.2d 460 (Court of Appeals of Maryland, 2004)
Mercantile Club, Inc. v. Scherr
651 A.2d 456 (Court of Special Appeals of Maryland, 1995)
Republic Insurance v. Prince George's County
608 A.2d 1301 (Court of Special Appeals of Maryland, 1992)
Seaboard Surety Co. v. Richard F. Kline, Inc.
603 A.2d 1357 (Court of Special Appeals of Maryland, 1992)
General Motors Acceptance Corp. v. Daniels
492 A.2d 1306 (Court of Appeals of Maryland, 1985)
Sergeant Co. v. Clifton Building Corp.
423 A.2d 257 (Court of Special Appeals of Maryland, 1980)
State Highway Administration v. Transamerica Insurance
367 A.2d 509 (Court of Appeals of Maryland, 1976)
Conner v. State
366 A.2d 385 (Court of Special Appeals of Maryland, 1976)
Lamot v. State
234 A.2d 615 (Court of Special Appeals of Maryland, 1967)
Travelers Indemnity Company v. Nationwide Construction Corporation
224 A.2d 285 (Court of Appeals of Maryland, 1966)
Peisner v. State
202 A.2d 585 (Court of Appeals of Maryland, 1964)
Queen City Enterprises, Inc. v. Independent Theatres, Inc.
187 A.2d 459 (Court of Appeals of Maryland, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
179 A.2d 868, 228 Md. 320, 1962 Md. LEXIS 451, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-builders-supply-co-v-macarthur-md-1962.