Wildewood Operations v. WRV Holdings

CourtCourt of Special Appeals of Maryland
DecidedOctober 30, 2023
Docket0388/22
StatusPublished

This text of Wildewood Operations v. WRV Holdings (Wildewood Operations v. WRV Holdings) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wildewood Operations v. WRV Holdings, (Md. Ct. App. 2023).

Opinion

Wildewood Operating Company, LLC, v. WRV Holdings, LLC, et al., No. 388, September Term 2022. Opinion by Tang, J.

PRINCIPAL AND SURETY – REMEDIES OF CREDITORS – CONDITIONS PRECEDENT TO ACTION AGAINST SURETY – NOTICE AND DEMAND

Although performance bond language lacked explicit timely notice requirement, language is read as requiring obligee owner to timely notify surety of default and termination of construction contract before third party took over remedial work. To read otherwise would render meaningless surety’s rights to exercise mitigation options under bond.

PRINCIPAL AND SURETY – NATURE AND EXTENT OF LIABILITY OF SURETY – PERFORMANCE OF CONTRACT OR CONDITIONS BY CREDITOR

PRINCIPAL AND SURETY – DISCHARGE OF SURETY – NEGLECT TO GIVE NOTICE TO SURETY OF DEFAULT – EFFECT OF OMISSION OR DELAY

Obligee owner’s failure to provide timely notice to surety of obligor contractor’s default and termination of construction contract before third party took over remedial work deprived surety of its right to participate in curing contractor’s default under performance bond, discharging surety of liability under bond.

PRINCIPAL AND SURETY – REMEDIES OF CREDITORS – CONDITIONS PRECEDENT TO ACTION AGAINST SURETY – NOTICE AND DEMAND

Requirement in provision of performance bond to demonstrate actual prejudice when obligee owner fails to comply with notice requirement governing intent to declare contractor’s default did not apply to separate notice requirement governing declaration of contractor’s default and termination of construction contract.

PRINCIPAL AND SURETY – RIGHTS AND REMEDIES OF SURETY – AS TO CREDITOR

Surety suffered prejudice as a matter of law when it was deprived of its contractually agreed- upon rights to exercise mitigation options under performance bond. Circuit Court for St. Mary’s County Case No. C-18-CV-17-000118

REPORTED

IN THE APPELLATE COURT

OF MARYLAND

No. 388

September Term, 2022

WILDEWOOD OPERATING COMPANY, LLC

v.

WRV HOLDINGS, LLC, et al.

Beachley, Tang, Kehoe, Christopher B.*

JJ.

Opinion by Tang, J. Pursuant to the Maryland Uniform Electronic Legal Materials Act (§§ 10-1601 et seq. of the State Government Article) this document is authentic.

2023-10-30 14:59-04:00 Filed: October 30, 2023

Gregory Hilton, Clerk

* Kehoe, Christopher B., now retired, participated in the hearing of this case while an active member of this Court; after being recalled pursuant to the Constitution, Article IV, Section 3A, he also participated in the decision and the preparation of this opinion. This appeal concerns a surety’s obligations under a construction performance bond.

Wildewood Operating Company, LLC (“Wildewood Operating”), appellant, filed a

complaint against First Indemnity of America Insurance Company (“First Indemnity”),

appellee, for breach of a performance bond, in which it sought from First Indemnity

indemnification for an amount incurred to complete construction after the contractor

defaulted. 1 First Indemnity moved for summary judgment, arguing that it was discharged

of liability under the bond. The Circuit Court for St. Mary’s County granted the motion,

and Wildewood Operating appealed. For the reasons set forth below, we affirm the

judgment of the circuit court.

FACTUAL BACKGROUND

In January 2013, Wildewood Operating purchased from WRV Holdings, LLC

(“WRV”) a parcel of land located in St. Mary’s County, with the intention of constructing

an assisted living facility (the “Facility”). Pursuant to the sales contract, WRV allowed

Wildewood Operating to perform site work on WRV’s adjacent parcel necessary for the

construction of the Facility. The work included, inter alia, the construction of a submerged

gravel wetland (“SGW”) to manage stormwater.

In conjunction with the sale, Wildewood Operating entered into a contract with

Clark Turner Construction, LLC (“Clark Turner”) for the construction of the Facility,

including SGW and other bioretention facilities. The construction contract required Clark

1 Wildewood Operating also sued WRV Holdings, LLC for unjust enrichment, but the claim was disposed of by summary judgment and is not the subject of this appeal. Turner to substantially complete the work no later than one year from the date of

commencement.

First Indemnity issued a performance bond set forth in a standard, American

Institute of Architects (“AIA”) form A312 (2010) (the “Bond”). 2 The Bond refers to Clark

Turner as “Contractor,” Wildewood Operating as “Owner,” and First Indemnity as

“Surety.” The Bond incorporates by reference the construction contract and outlines

Wildewood Operating’s obligation to notify First Indemnity in the event of Clark Turner’s

default. The notice requirements provide:

§ 3 If there is no Owner Default under the Construction Contract, the Surety’s obligation under this Bond shall arise after

.1 the Owner first provides notice to the Contractor and the Surety that the Owner is considering declaring a Contractor Default. Such notice shall indicate whether the Owner is requesting a conference among the Owner, Contractor and Surety to discuss the Contractor’s performance. If the Owner does not request a conference, the Surety may, within five (5) business days after receipt of the Owner’s notice, request such a conference. If the Surety timely requests a conference, the Owner shall attend. Unless the Owner agrees otherwise, any conference requested under this Section 3.1 shall be held within ten (10) business days of the Surety’s receipt of the Owner’s notice. If the Owner, the Contractor and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an agreement shall not waive the Owner’s right, if any, subsequently to declare a Contractor Default;

.2 the Owner declares a Contractor Default, terminates the Construction Contract and notifies the Surety; and

2 The AIA is an organization that, among other things, “[s]ets the industry standard in contract documents with more than 100 forms and contracts used in the design and construction industry.” Schneider Elec. Bldgs. Critical Sys., Inc. v. W. Sur. Co., 231 Md. App. 27, 34 n.3 (2016) (citation omitted).

2 .3 the Owner has agreed to pay the Balance of the Contract Price in accordance with the terms of the Construction Contract to the Surety or to a contractor selected to perform the Construction Contract.

§ 4 Failure on the part of the Owner to comply with the notice requirement in Section 3.1 shall not constitute a failure to comply with a condition precedent to the Surety’s obligations, or release the Surety from its obligations, except to the extent the Surety demonstrates actual prejudice.

Section 5 of the Bond describes the election of remedies available to First Indemnity

upon satisfaction by Wildewood Operating of the notice requirements:

§5 When the Owner has satisfied the conditions of Section 3, the Surety shall promptly and at the Surety’s expense take one of the following actions:

§ 5.1 Arrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract;

§ 5.2 Undertake to perform and complete the Construction Contract itself, through its agents or independent contractors;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

St. Paul Fire & Marine Insurance v. VDE Corp.
603 F.3d 119 (First Circuit, 2010)
Chirichella v. Erwin
310 A.2d 555 (Court of Appeals of Maryland, 1973)
Myers v. Kayhoe
892 A.2d 520 (Court of Appeals of Maryland, 2006)
Mayor of Baltimore v. Fidelity & Deposit Co.
386 A.2d 749 (Court of Appeals of Maryland, 1978)
General Builders Supply Co. v. MacArthur
179 A.2d 868 (Court of Appeals of Maryland, 1962)
Atlantic Contracting & Material Co. v. Ulico Casualty Co.
844 A.2d 460 (Court of Appeals of Maryland, 2004)
Cochran v. Norkunas
919 A.2d 700 (Court of Appeals of Maryland, 2007)
Uninsured Employers' Fund v. Danner
882 A.2d 271 (Court of Appeals of Maryland, 2005)
Laurel Race Course, Inc. v. Regal Construction Co.
333 A.2d 319 (Court of Appeals of Maryland, 1975)
Stonington Water Street Assoc., LLC v. Hodess Building Co.
792 F. Supp. 2d 253 (D. Connecticut, 2011)
Chesapeake Bank v. Monro Muffler/Brake, Inc.
891 A.2d 384 (Court of Special Appeals of Maryland, 2006)
Hartford Fire Insurance v. Himelfarb
736 A.2d 295 (Court of Appeals of Maryland, 1999)
National Union Fire Insurance v. David A. Bramble, Inc.
879 A.2d 101 (Court of Appeals of Maryland, 2005)
Town of Plainfield v. Paden Engineering Co.
943 N.E.2d 904 (Indiana Court of Appeals, 2011)
John McShain, Inc. v. Eagle Indemnity Co.
23 A.2d 669 (Court of Appeals of Maryland, 1942)
Lange v. Board of Education
37 A.2d 317 (Court of Appeals of Maryland, 1944)
Schneider Electric Buildings Critical Systems, Inc. v. Western Surety Co.
149 A.3d 778 (Court of Special Appeals of Maryland, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Wildewood Operations v. WRV Holdings, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wildewood-operations-v-wrv-holdings-mdctspecapp-2023.