Seaboard Surety Co. v. Richard F. Kline, Inc.

603 A.2d 1357, 91 Md. App. 236, 1992 Md. App. LEXIS 71
CourtCourt of Special Appeals of Maryland
DecidedApril 8, 1992
Docket873, September Term, 1991
StatusPublished
Cited by88 cases

This text of 603 A.2d 1357 (Seaboard Surety Co. v. Richard F. Kline, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaboard Surety Co. v. Richard F. Kline, Inc., 603 A.2d 1357, 91 Md. App. 236, 1992 Md. App. LEXIS 71 (Md. Ct. App. 1992).

Opinion

MOTZ, Judge.

The case presents the question of whether a subcontractor who contracts with a joint venturer has a “direct contract” with the joint venture itself so that the subcontractor is a “claimant” under a surety bond obtained by the joint venture. Because it is undisputed that when contracting with the subcontractor the joint venturer was acting on behalf and with the authorization of the joint venture, we hold that the subcontractor had a “direct contract” with the joint venture and so was a “claimant” under the surety bond. Accordingly, we affirm the order of the Circuit Court for Frederick County (Dwyer J.) granting the subcontractor summary judgment.

(i)

On December 18, 1985, Carrollton Associates Limited Partnership (“the Owner”) entered into a construction contract (“the Prime Contract”) with American International Construction Corp. and Elion Concrete Inc. Joint Venture (“the Joint Venture”) pursuant to which the Joint Venture would act as prime contractor and build a United States Department of Housing and Urban Development (“HUD”) subsidized garden apartment project in Frederick, Maryland. The members of the Joint Venture were two corporations: American International Construction Corp. (“AIC”) and Elion Concrete, Inc. (“Elion”).

The prime contract, as is mandated in HUD-financed projects, required the Joint Venture to assure completion of the work in the form of performance and payment bonds. The joint venture agreement between AIC and Elion provided that AIC “would construct the Project for the Joint Venture, entering into contracts in fAIC’s own name and paying all expenses of construction” and Elion would be responsible for obtaining surety bonds for the project and supplying additional capital that might be needed. Appellant, Seaboard Surety Company (“Seaboard”) refused to *239 issue the bonds unless Elion pledged its credit. Elion pledged its credit, and on December 18, 1985, Seaboard issued the surety bonds to the Joint Venture. The price of the bonds was a reimbursable expense, i.e., a cost which, under the Prime Contract, would be reimbursed by the Owner. AIC actually paid for those bonds but was reimbursed for that cost by the Owner.

The payment bond provides in pertinent part:

Know All Men By These Presents, THAT WE American International Construction Corp./Elion Concrete, Inc., Joint Venture of Baltimore Maryland os Principal, (hereinafter called the Principal) and Seaboard Surety Company, a New York Corporation as Surety, (hereinafter called the Surety) are held and firmly bound unto Carrollton Associates Limited Partnership, DBA Carroll-ton X Associates Limited Partnership as Obligee, (hereinafter called the “Owner”), for the use and benefit of claimants as hereinafter defined, in the sum of Eight Million One Hundred Sixteen Thousand Seven Hundred Twenty and 00/100 Dollars ($8,116,720.00), lawful money of the United States of America, for the payment of which Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
******
NOW, THEREFORE, THE CONDITIONS OF THIS OBLIGATION is such that, if Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions:
1. A claimant is defined as one having a direct contract with the Principal or with a subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone *240 service, or rental of equipment directly applicable to the Contract.
2. The above named Principal and Surety hereby jointly and severally agree with the Owner that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant's work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon____
3. No suit or action shall be commenced hereunder by any claimant:
(a) Unless claimant, other than one having direct contract with the Principal, shall have given written notice to any two of the following: The Principal, the Owner, or the Surety above named, within ninety (90) days after such ... performed the last of the work ... stating with substantial accuracy the amount claimed and the name of the party to whom materials were furnished, or for whom the work or labor was done or performed. Such notice shall be served by mailing the same by registered mail or certified mail, postage prepaid ... or served in any manner in which legal process may be served in the state in which the aforesaid project is located____

(emphasis added.)

On March 18, 1986, AIC (not the Joint Venture) entered into a subcontract with appellee, Richard F. Kline, Inc. (“Kline”), pursuant to which Kline would furnish and install all bituminous paving on the project. In that subcontract, AIC identified itself as the Contractor; the cover of the specifications book identified the contractor as being “American Int’l Const., Inc./Elion Concrete Incorporated.” The subcontract contains no signature line for Elion or the Joint Venture. Nothing in the text of the subcontract purports to bind the Joint Venture. The subcontract does *241 refer to the Prime Contract and arguably incorporates it by reference into the subcontract.

Kline performed paving work under the subcontract. Following a dispute over payment, Kline commenced an arbitration proceeding against AIC which resulted in an award for Kline against AIC in the amount of $140,000. On May 21, 1990, that award was confirmed by the Circuit Court for Baltimore City and judgment was entered for Kline against AIC. Kline was unsuccessful in collecting from AIC on this judgment.

Ultimately, Kline attempted to collect from Seaboard on the payment bond. Seaboard refused to pay. On September 13,1990, Kline then filed this action against Seaboard in the Circuit Court for Frederick County where the project is located. On May 13, 1991, the Circuit Court issued a short order granting summary judgment for Kline.

On appeal, Seaboard raises three questions:

1. Whether one who contracts with a single member of a joint venture, rather than the joint venture itself, can qualify as a “claimant” on a payment bond that names the joint venture as principal and then defines “claimant” as one having a direct contract with the named principal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shapiro v. Hyperheal Hyperbarics
Court of Special Appeals of Maryland, 2024
Haw v. NCAA
Court of Special Appeals of Maryland, 2024
Asmussen v. CSX Transportation
237 A.3d 908 (Court of Special Appeals of Maryland, 2020)
Baker v. Baker
109 A.3d 167 (Court of Special Appeals of Maryland, 2015)
May v. Air & Liquid Systems Corp.
100 A.3d 1284 (Court of Special Appeals of Maryland, 2014)
Hamilton v. Dackman
75 A.3d 327 (Court of Special Appeals of Maryland, 2013)
Catler v. Arent Fox, LLP
71 A.3d 155 (Court of Special Appeals of Maryland, 2013)
Tig Insurance v. Monongahela Power Co.
58 A.3d 497 (Court of Special Appeals of Maryland, 2012)
Reiter v. ACandS, Inc.
947 A.2d 570 (Court of Special Appeals of Maryland, 2008)
Clark v. O'MALLEY
901 A.2d 279 (Court of Special Appeals of Maryland, 2006)
Wilger Enterprises, Inc. v. Broadway Vista Partners
2005 NMCA 088 (New Mexico Court of Appeals, 2005)
Honeycutt v. Honeycutt
822 A.2d 551 (Court of Special Appeals of Maryland, 2003)
Martello v. Blue Cross
795 A.2d 185 (Court of Special Appeals of Maryland, 2002)
CERBERUS INTERN. LTD. v. Apollo Mgmt. LP
794 A.2d 1141 (Supreme Court of Delaware, 2002)
Cerberus International, Ltd. v. Apollo Management L.P.
794 A.2d 1141 (Supreme Court of Delaware, 2002)
Shipley v. Perlberg
780 A.2d 396 (Court of Special Appeals of Maryland, 2001)
Halliday v. Sturm, Ruger & Co.
770 A.2d 1072 (Court of Special Appeals of Maryland, 2001)
McCoy v. Hatmaker
763 A.2d 1233 (Court of Special Appeals of Maryland, 2000)
Homes Oil Co. v. Maryland Department of Environment
762 A.2d 1012 (Court of Special Appeals of Maryland, 2000)
Wood v. Toyota Motor Corp.
760 A.2d 315 (Court of Special Appeals of Maryland, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
603 A.2d 1357, 91 Md. App. 236, 1992 Md. App. LEXIS 71, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaboard-surety-co-v-richard-f-kline-inc-mdctspecapp-1992.