Shepherd Construction Co. v. State Highway Department

226 S.E.2d 79, 138 Ga. App. 252, 1976 Ga. App. LEXIS 2126
CourtCourt of Appeals of Georgia
DecidedMarch 1, 1976
Docket51472
StatusPublished
Cited by2 cases

This text of 226 S.E.2d 79 (Shepherd Construction Co. v. State Highway Department) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shepherd Construction Co. v. State Highway Department, 226 S.E.2d 79, 138 Ga. App. 252, 1976 Ga. App. LEXIS 2126 (Ga. Ct. App. 1976).

Opinions

Stolz, Judge.

Appellants (contractors) sued the appellee (Highway Department) to recover claims for (1) retainage of $5,981.66 plus interest, (2) payment of $204,869.37 for "removal of muck and sanitary landfill” to extra depths, plus interest, and (3) payment of $1,000,064.50 for "overhaul on excavation” plus interest, arising out of a highway construction contract. The highway department admitted that the $5,981.66 retainage was owed, and paid the sum into the registry of the court. The contractors moved for summary judgment, the highway department for judgment on the pleadings. The superior court judge awarded the contractors the retainage ($5,981.66) with interest from date of judgment, denied all of the contractors’ remaining motions and sustained the highway department’s motion for judgment on the pleadings, which we treat as a motion for summary judgment. See Code Ann. §§ 81A-112 (c) and 81A-156. It is from this judgment that the contractors appeal.

1. The record shows that the highway department tendered the retainage ($5,981.66) on January 27, 1970. The contractors refused to accept it. Section 9.08 of the contract specifically provides that final payment is not due the contractors until one of the following occurs: (a) The treasurer receives the final release properly executed by the contractors; (b) The total amount due has been decided by agreement after review by the engineer of the contractors’ written exceptions; (c) The amount due has been resolved by arbitration; or (d) The total amount due has been fixed by a court of proper authority. None of the foregoing had occurred prior to the superior court’s judgment on July 14, 1975. Here, the contractors were notified that the work was accepted pursuant to the contract; the treasurer was notified of the contract’s completion as to the "entire amount of every class of work performed and as to the value thereof.” The treasurer then forwarded the final payment estimate to the contractors, enclosing a release to be executed by the contractors (item "a,” supra). The contractors disputed the final payment, [253]*253refused to execute the final release and provided their written exceptions. Clearly, the parties were never in agreement as to the total amount due, as required by their contract. The judge of superior court correctly denied interest on the retainage ($5,981.66) from January 27, 1970, and awarded same from date of judgment. See Firemen’s Ins. Co. v. Oliver, 182 Ga. 212 (184 SE 858); Colevins v. Nat. Union Fire Ins. Co., 110 Ga. App. 533 (1) (139 SE2d 145).

2. The contractors’ claim for $204,869.37 for the removal of muck and sanitary landfill, is based on Section 104.19 (b) of the 1956 Standard Specifications, Vol. 1, p. 123, which is a part of the contract. This provision of the contract,relates to "Unclassified Excavation,” and provides for payment for removal based on the unit price bid per cubic yard to the depth shown within the neat cross sections on the plans, and to a depth of 2 feet below those cross sections. Beyond the 2-foot depth, the unit price bid plus an increasing scale was applied as the depth increased in stated measurements. The highway department contends that muck and sanitary landfill removal are covered by special provisions of the contract. We note that in the Itemized Proposal (Exhibit 2 of contractors’ complaint) a unit price of 40 cents per cubic yard is assigned to "unclassified excavation,” while removal of both muck and sanitary landfill are compensated at $1.25 per cubic yard. The "Special Provisions” of the contract entitled "Excavation, Borrow, Waste, Muck and Sanitary Landfill” provide: "9. Muck Excavation. A. This item consists of removal and disposal of Class IV materials within the construction limits. B. Class IV material within the limits of construction will be removed for the full depth of such material in accordance with the detail shown on sheet No. six (6) of the plans. The engineer may direct that all or any portion of the material removed under this item be stockpiled for use in topping slopes or other areas which are to be grassed (See Par. 7 & 8 above). Any material removed under this item and not stockpiled for reuse shall be disposed of in accordance with Article 104.07 of the Standard Specifications. C. Material to be removed under this item will be measured as follows: ... (2) The volume (in cubic yards) contained between the [254]*254original ground and the neat lines shown as the limits of muck removal on the detail of sheet No. six (6) in the plans will be computed by the average end area method. No payment will be made for material excavated before cross-sections are taken or for material removed outside the pay limits shown on sheet No. six (6) of the plans.”

We further note that paragraph 12 of the aforesaid prpvisions provides: "Payment will be made under: Item No. 104 Unclassified Excavation — Per cubic yard; Item No. 104 Removal of Muck — Per cubic yard; Item No. 104 Removal of Sanitary Landfill — See Special Provision for this item.” Examination of sheet No. 6 of the plans shows that the depth of material (muck and sanitary landfill) varies and that the basis of payment for the removal of both items is established "per cubic yard.” The special provision for sanitary landfill (old garbage dump) removal provided that the material shall be taken out to full depth and cross section and that the price bid per cubic yard "shall include the cost of excavation, loading, spraying, hauling,... tools, equipment, labor, etc., as may be required to -complete the work. . .”

We have previously noted that the contracts’ "Itemized Proposals” separated unclassified excavation, muck removal and sanitary landfill removal; the compensation was set at 40 cents per cubic yard for the first item and $1.25 per cubic yard for the latter two. If the "sliding scale” urged by the contractors (contract, Section 104.19 (b)) were applicable, it would be based on 40 cents per cubic yard (Unclassified Excavation), not $1.25 per cubic yard (Muck and Sanitary Landfill removal). Moreover, the payment schedule set out in Section 104.19 (b) only applies to the removal of unsuitable material not shown on the plans. The removal of muck and sanitary landfill is shown on sheet No. 6 of the plans.

3. In approaching the contractors’ claim of $1,000,064.50 for overhaul on borrow, it is helpful to understand some basic definitions. "Borrow” is dirt which is used for fill and is obtained from a pit located outside the right of way of the project. A "station yard” is the hauling of one cubic yard of borrow (dirt) the distance of one station. — 100 feet. The contractors claim they are entitled to be paid $.005 per station yard for 200,012,900.4 station [255]*255yards of overhaul on borrow. Special Provisions, Borrow Excavation is found in the Modification of Section 110 of the contract, which provides in part, "110.05. Payment: Borrow excavation will be paid for at the Contract unit price for Borrow Excavation when the Contract includes this Item, otherwise it will be included and counted for payment as Unclassified Excavation. Selected Borrow will be paid for at the Contract unit price established for this Item. In both cases the prices paid shall be full compensation for furnishing all labor, equipment, tools, superintendence and incidentals necessary to complete the work including overhaul unless overhaul for borrow excavation is set up in the contract as a separate pay item. If the Contractor is required to pay royalties for the material, the Pay Items will be listed with the words 'Including Material’ added. Payment will be made under: Item No. 110-A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Department of Transportation v. Dalton Paving & Construction, Inc.
489 S.E.2d 329 (Court of Appeals of Georgia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
226 S.E.2d 79, 138 Ga. App. 252, 1976 Ga. App. LEXIS 2126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shepherd-construction-co-v-state-highway-department-gactapp-1976.