M.C. Anderson v. Golden

569 F. Supp. 122, 36 Fed. R. Serv. 2d 213, 1982 U.S. Dist. LEXIS 10282
CourtDistrict Court, S.D. Georgia
DecidedDecember 28, 1982
DocketCV481-237
StatusPublished
Cited by14 cases

This text of 569 F. Supp. 122 (M.C. Anderson v. Golden) is published on Counsel Stack Legal Research, covering District Court, S.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.C. Anderson v. Golden, 569 F. Supp. 122, 36 Fed. R. Serv. 2d 213, 1982 U.S. Dist. LEXIS 10282 (S.D. Ga. 1982).

Opinion

ORDER

EDENFIELD, District Judge.

The above-captioned case came on for bench trial before this Court on August 24, 1982. After hearing three days of testimony and reviewing numerous exhibits and depositions, the Court now makes the following Findings of Fact and Conclusions of Law.

Introduction

This suit involves a classic confrontation between the developer of a project, McAlpin Square Shopping Center, and his contractor, in this case, the rough-grading and storm drainage system contractor. The conflict which arose during the course of the work was exacerbated by the weather and other adverse conditions at the site of the development. Each party accused the other of various breaches of the contract. The contractor, M.C. Anderson, doing business as M.C. Anderson Construction Company, filed a materialmen’s lien against the McAlpin Square property. He subsequently brought this action, which was removed to this Court on the basis of diversity jurisdiction, against Donald Golden, the developer of McAlpin Square. He seeks monies allegedly due under the contract, remuneration in quantum meruit, reimbursement of certain funds expended during the course of the job, and attorney’s fees. Golden, in turn, asserted a counterclaim for delay damages, for the cost of correcting or completing work under Anderson’s contract, for expenses incurred, and for slander of title.

FINDINGS OF FACT

I. The Parties and the Contract

1. Plaintiff, an earthwork contractor, entered a lump sum contract to perform site work at the proposed McAlpin Square Shopping Center, with Donald Golden, a real estate developer with a leasehold in the property. The site is located in Chatham County, Georgia, northwest of the intersection of Victory Drive and Wallin Street.

2. Anderson received an invitation to bid on the development in late May, 1979. In order to prepare bids on the site grading and storm sewer construction work, prospective bidders were provided with a package of information prepared by Golden’s architect, John Carey. The package included a bound book entitled “Specifications for Site Grading and Storm Sewer Work for the McAlpin Square Shopping Center” which contained detailed bidding and soil *127 boring information and a site grading plan dated May 23, 1979. The scope of the site work initially included clearing the site, raising it to the required elevation, rough-grading, and general preparation of building pad and parking area sites. Bidders were instructed to carefully examine the site, the drawings, and other bid documents and to verify conditions and locations in the field.

3. Anderson, the only earthwork contractor to bid the job, submitted a bid of $575,695.00 on June 12, 1979. In order to achieve a reduction in this price, John Carey engaged in discussions with Steve Chavis, Anderson’s employee in charge of the McAlpin Square bid. After the elimination of a soil stabilization mat and the addition of a provision requiring the excavation of fill from retention areas adjacent to the site, Anderson submitted a revised bid of $425,-000.00 on June 21, 1979. After further discussions and negotiation, Anderson submitted a final proposal on August 15, 1979, for $425,000.00, which was substantially similar to the June 21, 1979 bid. Golden accepted this bid and after adding $4,250.00 for the bond premium, the contract price was $429,500.00.

4. Prior to the execution of the contract, Carey issued a revised grading plan dated August 23,1979, which superceded the May 23rd plan. In addition to other minor configuration changes, the dimensions of easements in the retention pond area, which had been inadvertently omitted on the May 23rd drawings, were shown.

5. Anderson and Golden executed the standard AIA contract on September 12, 1979. The contract documents included the Owner-Contractor Agreement, the August 23rd drawings, the Specifications, the Instructions to Bidders, the Uniform Proposals, Addendum No. 1 (Post-Bid), and the General and Supplemental General Conditions. The contract contained a merger clause. Pertinent portions or paraphrases of portions of the contract documents are set out below.

a) The Agreement

Art. 2. The Contractor shall furnish all supervision, labor, materials, equipment, transportation and supplies necessary to perform the site grading work and storm sewer work for the Project.

Notwithstanding anything set forth in the contract documents to the contrary, Contractor acknowledges and agrees that Contractor has investigated soil and subsoil conditions of the site to its full and complete satisfaction.

Art. 3. Work to be commenced as soon as possible and substantial completion to be achieved according to terms of Schedule A.

Art. 6. Final payment when work completed, contract performed and final Certification for Payment issued by architect.

b) Schedule A

(1) Building pads for Units A & C to be completed by November 1, 1979. The remainder of the building pad areas by December 1, 1979. All remaining work by February 1, 1980.

Time is of the essence of this Agreement.

Without limiting the provisions of the preceding sentence, Contractor also agrees to complete the work as rapidly as field conditions permit ... so as to enable the Contractor to complete the work within the time limits specified above.

c) General Conditions

Art. 1.2.2. By executing the Contract, the Contractor represents that he has visited the site, familiarized himself with the local conditions under which the work is to be performed, and correlated his observations with the requirements of the Contract documents.

1.2.3. The Contract documents are complementary, and what is required by anyone shall be as binding as if required by all.

2.2.2. Architect shall have no authority to execute Change Orders.

2.2.3. The architect will visit the site at intervals appropriate to the stage of construction to familiarize himself generally *128 with the progress and quality of the work....

2.2.17. If the owner and architect agree, the architect will provide one or more Project Representatives.

4.2.1. The Contractor shall carefully study and compare the Contract Documents and shall at once report in writing to the architect any error, inconsistency or omission he may discover.

4.3.1. Contractor ... shall be solely responsible for all construction means, methods, techniques, sequences and procedures and for coordinating all portions of the work under the Contract. If Contractor shall have knowledge of same, he shall notify owner and architect of any actual impending or probable shortages of labor or material or of other factors which may affect adherence to the progress schedule.

6.1.3. The owner will provide for the coordination of the work of his own force and of each contractor with the work of the Contractor, who shall cooperate therewith as provided in Paragraph 6.2.

8.1.3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
569 F. Supp. 122, 36 Fed. R. Serv. 2d 213, 1982 U.S. Dist. LEXIS 10282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mc-anderson-v-golden-gasd-1982.