Jefferson Construction Company v. The United States

392 F.2d 1006, 183 Ct. Cl. 720, 1968 U.S. Ct. Cl. LEXIS 88
CourtUnited States Court of Claims
DecidedApril 19, 1968
Docket81-65
StatusPublished
Cited by23 cases

This text of 392 F.2d 1006 (Jefferson Construction Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jefferson Construction Company v. The United States, 392 F.2d 1006, 183 Ct. Cl. 720, 1968 U.S. Ct. Cl. LEXIS 88 (cc 1968).

Opinion

OPINION

LARAMORE, Judge. *

Plaintiff, Jefferson Construction Company, hereinafter referred to as Jefferson, was awarded a contract for $963,714 by the General Services Administration to construct two reinforced concrete buildings, a retaining wall and a pump-house at the Northeast Shellfish Sanitation Research Center at Narragansett, Rhode Island. Jefferson alleges that by supplying plans which it knew, or should have known, were defective, the government breached its implied contractual obligation to furnish plans, specifications and rock boring data which, if complied with, would result in satisfactory performance. Plaintiff’s expected performance time and completion schedule were delayed when additional concrete and steel work were required to complete the contract under unanticipated weather conditions. Jefferson claims delay damages for breach of contract in addition to the equitable adjustment received from the contracting officer.

Originally plaintiff alleged four causes of action. Counts two and three 1 of the original petition were waived before trial. Plaintiff did not file exceptions to the trial commissioner’s report on Count four and at oral argument waived that Count. We agree with the trial commissioner that the General Services Administration Board of Contract Appeals’ decision (on Count four) is supported by substantial evidence. We have incorporated that part of the report, as modified, and deny any recovery for Count four.

Count one, the only claim now before us, alleges that Jefferson was unreasonably delayed both by the government’s failure to furnish adequate plans and borings and by its failure to correct the plans within a reasonable time after the inadequacies became evident. We conclude that plaintiff has not proved that defendant breached the contract. It has received all of the administrative relief to which it is entitled, and we dismiss the petition.

I.

Prior to the issuance of a request for bids, government personnel took 15 core boring test samples of the subsoil at the excavation site in the area immediately adjacent to the locale of the foundation pads. Jefferson’s bid and estimated excavation costs were based on government-furnished plans which indicated that foundation pad excavation would terminate at a depth where the core boring drill had shown “refusal,” i. e., the drill would not penetrate the subsoil beyond the point of refusal. No representative of Jefferson ever examined *1009 the core boring samples which the government had made available.

Jefferson acknowledged its July 19, 1962 receipt of the government’s July 17 notice to proceed and began work on the project the next day, July 20. Work was to have been completed within 360 days from the date of the notice to proceed. Because of the various delays encountered, substantial compliance did not occur until February 6, 1964, and the contract was not completed until June 16, 1964. Plaintiff claims to be entitled to compensation for the overhead costs incurred during delay.

Problems began at the first of the 36 required foundation pad (footing) excavations. Jefferson excavated to the depth indicated on the plans as the “refusal” point but encountered clay rather than the rock ledge which it had concluded was the basis for the “refusal.” It had anticipated placing the foundation pads on that rock.

Jefferson notified the government resident engineer on the following day (August 14, 1962). After an on-site inspection the government structural engineer directed Jefferson to continue its excavation until an appropriate base for the footing was reached. 2 Excavation at 34 of the 36 footing sites terminated at a depth other than the refusal point noted on the plans. Thirty-two footings were at a greater depth, with an average overcut of 4.3 feet and a maximum of 10.6 feet.

The absence of a known excavation depth disrupted plaintiff’s planned progress schedule, required additional manpower, special equipment and material, and prevented construction of wood forms (into which the concrete is poured) until after excavation for each footing was completed. Originally plaintiff claimed $46,229 as compensation for a 90-day delay, but its claim is now limited to $38,362.74 as compensation for a 70-day delay. 3

Plaintiff presented to the contracting officer its claim for actual costs and indirect costs incurred as a result of the delay. In response, the contracting officer offered $17,000 as an equitable adjustment for the additional costs expended during performance. Plaintiff accepted that payment but expressly reserved its right to compensation for the delay damages. The final decision of the contracting officer awarded plaintiff the $17,000 and granted a 21-day extension of time (plaintiff had requested 90 days). Jefferson accepted the $17,000 but sought review of the “equitable adjustment” from the GSA Board of Contract Appeals.

On February 5, 1965, the GSABCA upheld the $17,000 award but dismissed that part of the claim which requested damages for the delay. It concluded that plaintiff’s unreasonable delay claim was not covered by the contract and, therefore, as a breach of contract claim it was not within its jurisdiction. By a *1010 pre-trial agreement the parties agreed to try Count one de novo in this court.

Both parties agree that plaintiff exhausted its available administrative remedies when the GSABCA refused to consider the claim for lack of jurisdiction. The Board recognized the distinction between claims which, by virtue of an agreement by the parties (as embodied in their contract), are determinable by an administrative agency, and those claims which, because they have not been made subject to resolution under the contract, remain “pure” breach of contract claims to be tried before the court. See: The Len Company v. United States, 385 F.2d 438, 442, 181 Ct.Cl. 29 (October, 1967) (slip op. 5); J. G. Watts Construction Co. v. United States, 355 F.2d 573, 174 Ct.Cl. 1 (1966); Cf., Ekco Products Co. v. United States, 312 F.2d 768, 160 Ct.Cl. 75 (1963); New York Shipbuilding Corp. v. United States, 385 F.2d 427, 180 Ct.Cl. 446 (1967). A true breach of contract claim which, by definition is outside the scope of the contract, is subject neither to equitable adjustment under the contract nor to administrative review or resolution. United States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966); United States v. Utah Construction & Mining Co., 384 U.S. 394, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966); and L. L. Hall Construction Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDevitt & Street Co. v. Marriott Corp.
713 F. Supp. 906 (E.D. Virginia, 1989)
District of Columbia v. Savoy Construction Co.
515 A.2d 698 (District of Columbia Court of Appeals, 1986)
Pinkerton and Laws Co., Inc. v. Roadway Exp., Inc.
650 F. Supp. 1138 (N.D. Georgia, 1986)
Max Jordan Bauunternehmung v. United States
33 Cont. Cas. Fed. 74,562 (Court of Claims, 1986)
Utility Contractors, Inc. v. United States
32 Cont. Cas. Fed. 73,446 (Court of Claims, 1985)
M.C. Anderson v. Golden
569 F. Supp. 122 (S.D. Georgia, 1982)
A. J. Baltes, Inc. v. Department of Highways
13 Ct. Cl. 1 (West Virginia Court of Claims, 1979)
General Dynamics Corp. v. United States
558 F.2d 985 (Court of Claims, 1977)
Koppers/Clough v. United States
201 Ct. Cl. 344 (Court of Claims, 1973)
Carl M. Halvorson, Inc. v. United States
461 F.2d 1337 (Court of Claims, 1972)
John McShain, Inc. v. United States
412 F.2d 1281 (Court of Claims, 1969)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Paul Hardeman, Inc. v. The United States
406 F.2d 1357 (Court of Claims, 1969)
Red Circle Corporation v. The United States
398 F.2d 836 (Court of Claims, 1968)
Morrison-Knudsen Company, Inc. v. The United States
397 F.2d 826 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
392 F.2d 1006, 183 Ct. Cl. 720, 1968 U.S. Ct. Cl. LEXIS 88, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jefferson-construction-company-v-the-united-states-cc-1968.