Allied Paint & Color Works, Inc. v. United States

309 F.2d 133, 1962 U.S. App. LEXIS 4221
CourtCourt of Appeals for the Second Circuit
DecidedAugust 29, 1962
Docket27236_1
StatusPublished
Cited by9 cases

This text of 309 F.2d 133 (Allied Paint & Color Works, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Paint & Color Works, Inc. v. United States, 309 F.2d 133, 1962 U.S. App. LEXIS 4221 (2d Cir. 1962).

Opinion

WATERMAN, Circuit Judge.

Appellant, a paint contractor, brought the present action against the United States in the U. S. District Court for the Southern District of New York for breach of contract, alleging that the Government failed to deliver a certain quantity of phosphorescent paint which it was the Government’s duty to furnish under the contract. This is an appeal from the order of the district court dismissing appellant’s complaint. We affirm the court below.

*134 On June 20, 1952, following an invitation to bid, appellant and the Government entered into contract No. N383s-77428 (hereinafter referred to as contract No. 1), under which appellant agreed to furnish the Government 7,644 paint kits to be delivered to various government depots within 90 days after the date of the contract. Each kit was to contain a quart can of phosphorescent paint which was called component “A,” a quart can of white primer, a quart can of thinner, and a quart can of varnish. The contract expressly provided that the 7,644 quarts of phosphorescent paint, to-talling 1,911 gallons, were to be Government-furnished, and the Government was to deliver them in one gallon cans to appellant’s plant within 30 days from the contract date.

Contract No. 1 then provided that upon request by appellant the dates for appellant’s performance would be extended if the Government delayed in supplying the Government-furnished property, and though the Government would not be liable for delays in the delivery of the phosphorescent paint or for failure to deliver, an equitable adjustment in the performance date or the price would be made upon the written request of the contractor. The contract also provided that the Government could increase or decrease the amount of property it was to furnish, and in such event, there was provision for price or date adjustments. Although title to the phosphorescent paint remained in the Government, appellant agreed to assume the risk of loss after the property was delivered by the Government. The contract stated that:

“[T]he Contractor, upon delivery to it of any Government-furnished property, assumes the risk of, and shall be responsible for, any loss thereof or damage thereto except for reasonable wear and tear * * * ”

The contract also contained a “Disputes” clause, whereby the parties agreed that disputes arising under the contract should be settled by the Contracting Officer, with the right of appeal to the Secretary of Defense or his representative, i. e., the Armed Services Board of Contract Appeals.

Under contract No. 1 the Government was able to deliver to appellant only 3,-956 quarts (989 one gallon cans) of phosphorescent paint. All but 240 quarts of the paint were put up by appellant in the specified quart cans, and were combined with the other required products to complete 3,716 kits, which were delivered to, and paid for by, the Government. After delivery of these kits appellant still had the remaining 240 quarts of Government-furnished phosphorescent paint on hand.

Negotiations between appellant and the Government during 1953 led to the execution of a second contract, No. 383s-97516, on January 7, 1954 (hereinafter referred to as contract No. 2). In this contract, appellant agreed to furnish the Government 3,688 quarts of phosphorescent paint in one quart cans at a price of f 6.17 per quart. This was the exact amount of paint needed to complete contract No. 1 and was paint of the same type of phosphorescent paint called for by contract No. 1.

Contract No. 2, unlike the earlier contract, contained no express words in the schedule, specifications, or elsewhere, stating that “The Government shall furnish to the Contractor for use in connection with this contract, the material set forth below,” followed by a description of any “material.” Contract No. 2 did provide, however, as follows:

“Government Furnished Material

“The Phosphorescent Paint to be furnished under this contract shall be packaged and marked by the contractor so it may be used, without repacking or remarking, as Component ‘A’ of the Phosphorescent Paint Kits to be furnished by the same contractor under Contract N383S-77428 [No. 1].
“Contract N383s-77428 [No. 1] provides that Component ‘A’ (Phosphorescent Paint) shall be supplied by the Army as Government Furnished Material in the amount of 1,911 gallons, which amount is suffi *135 cient to produce 7,644 Phosphorescent Paint Kits covered by that contract; however, a quantity of 989 gallons only were available from Army stocks as Government Furnished Material. Procurement of 3,688 quarts (922 gals.) under Contract N383s-97516 [No. 2] was, therefore, necessary to effect completion of Contract N383s-77428 [No. 1].”

Notwithstanding the nature of contract No. 2, the standard “Government-Furnished Property” clause, which allocated the risk of loss for such property, was also inserted. Since contract No. 2 was a negotiated contract instead of an advertised one, the risk of loss by fire of the “Government-Furnished Property” was placed upon the Government, see 32 C.F. R. 13.502, but the insertion of this standard clause created the ambiguity which caused the present controversy.

Contract No. 2 also contained a “Disputes” clause, identical to the one in contract No. 1.

Appellant manufactured 1,118 quarts of phosphorescent paint pursuant to contract No. 2, and these 1,118 quarts, subsequently destroyed by fire, became the subject matter out of which the action before us arose. Of the 1,118 quarts, 318 were inspected and accepted by the Government at appellant’s plant on April 6, 1954, and 800 were inspected and accepted by the Government at the plant on May 5, 1954. On each occasion, the Government inspector executed a “Material Inspection and Receiving Report,” which recited among other things:

“Government-furnished property.
“Material to be used for Contract N383s-77428 [No. 1] by same Contractor for Component ‘A.’ ”

Copies of these reports were given to appellant. Subsequently, the Government paid appellant the purchase price for these 1,118 quarts.

After the Government had accepted the 1,118 quarts, they were kept in appellant’s plant. This paint was not mingled with the 240 quarts which appellant had previously received as Government-furnished property under contract No. 1. Appellant did not increase the dollar limit on its inventory insurance to reflect the value of the 1,118 quarts manufactured under contract No. 2.

On May 31, 1954, appellant’s plant was destroyed by fire. Included within the property lost were the 240 quarts of paint which were admittedly Government-furnished under contract No. 1 and for which appellant acknowledged liability, and the 1,118 quarts which had been manufactured by the appellant under contract No. 2 and had been accepted by the Government. The appellant, by letter dated June 8,1954, informed the Government of the loss of the two lots of paint. In the letter, the appellant stated: “The first 60 gal. was material which we had left from Government Furnished Material. The Balance was made for Aviation Supply Office under Contract N383s-77428 [No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jefferson Construction Company v. The United States
392 F.2d 1006 (Court of Claims, 1968)
United States v. Utah Construction & Mining Co.
384 U.S. 394 (Supreme Court, 1966)
Compudyne Corp. v. Maxon Construction Co.
248 F. Supp. 83 (E.D. Pennsylvania, 1965)
Gottlieb Contracting, Inc. v. United States
247 F. Supp. 988 (E.D. New York, 1965)
Crowder v. United States
255 F. Supp. 873 (N.D. California, 1964)
Construction Management Corp. v. Brown & Root, Inc.
41 Misc. 2d 864 (New York Supreme Court, 1964)
Silverman Brothers, Inc. v. United States
324 F.2d 287 (First Circuit, 1963)
United States v. Carlo Bianchi & Co.
373 U.S. 709 (Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
309 F.2d 133, 1962 U.S. App. LEXIS 4221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-paint-color-works-inc-v-united-states-ca2-1962.