Blake Construction Company, Inc. v. United States of America, United States of America v. Aetna Casualty and Surety Company

296 F.2d 393, 111 U.S. App. D.C. 271, 1961 U.S. App. LEXIS 3779
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 3, 1961
Docket15948, 16049
StatusPublished
Cited by13 cases

This text of 296 F.2d 393 (Blake Construction Company, Inc. v. United States of America, United States of America v. Aetna Casualty and Surety Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blake Construction Company, Inc. v. United States of America, United States of America v. Aetna Casualty and Surety Company, 296 F.2d 393, 111 U.S. App. D.C. 271, 1961 U.S. App. LEXIS 3779 (D.C. Cir. 1961).

Opinions

BURGER, Circuit Judge.

In 1950 the Public Buildings Service of General Services Administration entered into negotiations with Blake Construction Company, appellant in No. '15948, for the renovation of a portion of a government building. A letter of understanding from the GSA, dated December 28, 1950, stated that Blake was to perform the work in accordance with specifications to be drawn by GSA for a [395]*395lump-sum figure to be determined on the basis of 5% for profit, and that a contemplated formal contract “will include a clause providing for renegotiation at completion of the work.” A further letter of the same date stated the proposal and incorporated provisions of government standard forms that the contract would be subject to renegotiation and that “all disputes concerning questions of fact arising under this contract” would be subject to departmental administrative review. Blake accepted these terms. The formal contract was finally prepared and submitted five months later at a time when the work was substantially complete.. It stated a lump-sum price for the work, but did not include the government form containing the renegotiation provision. Upon completion of the work, the government proposed an audit of Blake’s accounts pursuant to renegotiation. Although Blake maintained that there was no contractual provision for renegotiation, Blake allowed the audit to proceed since the contract might be subject to the Renegotiation Act of 1951, 65 Stat. 7, as amended, 50 U.S.C.A.Appendix, §§ 1211-1224. The contracting officer subsequently ruled that Blake had been overpaid $57,281.10. Blake contested this determination before the GSA Board of Review on the ground that the contract was not subject to renegotiation. The Board of Review concluded that the renegotiation provision had been omitted from the formal contract document inadvertently, and that both parties assumed that the contract was subject to renegotiation. Alternatively, the Board expressed the view that if it be assumed that the renegotiation provision was intentionally omitted, the modification of the original contract in favor of Blake was not supported by consideration. The government sued Blake for the overpayment in the District Court and also sought judgment against Aetna Casualty and Surety Company, appellee in No. 16049, who was surety on the performance bond provided by Blake. On cross-motions for summary judgment, the District Court granted summary judgment for the government in its action against Blake, but granted judgment for Aetna in that part of the action.

No. 15948

The issues presented on this appeal are:

(1) Assuming that the renegotiation provision was intentionally omitted from the formal contract, did the government receive consideration for relinquishing its right to renegotiate?
(2) If there was consideration, is appellant nonetheless bound by the government’s lack of authority to enter into a cost-plus-percentage-of-eost contract which did not include a renegotiation provision ?
(3) If not so bound, was the determination by the Board of Review that the provision was intentionally omitted binding upon the District Court as a finding on a “question of fact arising under” the contract ?

The government contends that the District Court’s grant of summary judgment in its favor may be sustained on the basis of the provisions of the December 28 letter. Blake denies that a contract was formed at that point because the letter did not specify the contract price or describe the work to be performed. We need not reach the question whether the exchange of letters constituted a valid contract. If we assume that the letters were not sufficiently definite, then the formal contract is sufficiently definite and supported by consideration. On the other hand, if there was a valid letter contract, it was superseded by the formal contract.

Until the execution of the formal contract, no fixed price had been determined. After execution, Blake obtained the opportunity of increasing its profit margin by economies in its operation but this was not without the possibility of some risk, however unlikely that risk might be. The government on the other hand acquired the benefit of a fixed maximum on the amount of its cost for the project. Thus, on either assumption with respect to the legal effect of the [396]*396prior negotiations, the formal contract was valid and supported by consideration. The government’s argument on this point takes a strained view of the nature of consideration required to support contractual obligations. Among other things it is not unknown in construction contracts for profits to become dissipated or even turn into losses because of factors encountered at the very latest stages of performance. It is not the probability of such an occurrence but the mere possibility which is sufficient to constitute legal consideration.

Alternatively, the government argues that the formal contract cannot be given effect because it is merely a disguised attempt to create a cost-plus-a-percentage of cost type of contract, barred by section 304(b) of the Federal Property and Administrative Services Act of 1949, 63 Stat. 395, as amended, 41 U.S.C.A. § 254 (b).

In dealings with the government, unlike those with private parties, one is charged with knowledge of the extent of the actual authority of the government’s contracting agent since no agent of the government can hold out to have any authority not sanctioned by law. However difficult the process may be, his actual authority can be ascertained. National Electronic Labs., Inc., v. United States, Ct.Cl. 1960, 180 F.Supp. 337, 341-342. The size and complexity of government makes this rule necessary, and the public nature of the instruments such as statutes, executive orders and regulations granting and limiting authority makes it the only feasible rule.

In essence the government argues that the inclusion of the renegotiation provision in the letter contract saved it from the bar of section 304(b), but that its omission in the formal document renders the latter nugatory since it contends a contract without a renegotiation provision was not authorized. But this argument fails to recognize that the formal contract established a fixed contract price, thereafter subjecting the contractor to the risk that, rising costs would dilute his profit margin. Moreover, even if we accept the government’s argument that at the late stage when the formal contract was executed, with ninety per cent of the work complete, risks were so calculable that the price merely disguised a cost-plus-pei’centage-of-cost arrangement, the invalidity of the formal contract would not support the government’s position on the appeal. If in fact the contract was made without authority, then perhaps no contract exists, but the contractor is nonetheless entitled to the reasonable value of the benefits conferred. 38 Decs.Comp.Gen. 38 (1958). The record does not reveal that such a computation would result in the precise amount determined by the contracting officer pursuant to the renegotiation provision which he believed to be a part of the contract. Hence, the judgment cannot be affirmed on that ground.

The government concedes that the reformation of the contract to express correctly the intent of the parties is a function of the District Court rather than the GSA Board of Review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Sears, Roebuck and Co
778 F.2d 810 (D.C. Circuit, 1985)
Navajo Tribe v. Bank of New Mexico
556 F. Supp. 1 (D. New Mexico, 1980)
Martin Fein & Co. v. Sealomatic Electronics Corp.
57 Misc. 2d 187 (Civil Court of the City of New York, 1967)
Atlantic Tobacco Co. v. United States
249 F. Supp. 661 (D. South Carolina, 1966)
Wingate Construction Co. v. United States
164 Ct. Cl. 131 (Court of Claims, 1964)
Wpc Enterprises, Incorporated v. The United States
323 F.2d 874 (Court of Claims, 1964)
WPC Enterprises, Inc. v. United States
323 F.2d 874 (Court of Claims, 1963)
United States v. Carlo Bianchi & Co.
373 U.S. 709 (Supreme Court, 1963)
Allied Paint & Color Works, Inc. v. United States
309 F.2d 133 (Second Circuit, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
296 F.2d 393, 111 U.S. App. D.C. 271, 1961 U.S. App. LEXIS 3779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blake-construction-company-inc-v-united-states-of-america-united-states-cadc-1961.