Wingate Construction Co. v. United States

164 Ct. Cl. 131, 1964 U.S. Ct. Cl. LEXIS 38, 1964 WL 8537
CourtUnited States Court of Claims
DecidedJanuary 24, 1964
DocketNo. 934-60
StatusPublished
Cited by14 cases

This text of 164 Ct. Cl. 131 (Wingate Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wingate Construction Co. v. United States, 164 Ct. Cl. 131, 1964 U.S. Ct. Cl. LEXIS 38, 1964 WL 8537 (cc 1964).

Opinion

Durfee, Judge,

delivered the opinion of the court:

This suit involves a claim for additional compensation that plaintiff corporation alleges it has earned through construction of sidewalks that were not included in the original construction contract. Defendant contends that the sidewalk construction at issue was included in the contract.

On June 20, 1958, an invitation was issued for bids on “Construction of Off-Site Utilities for Title VIII Housing” at McGuire Air Force Base, New Jersej. Included with the invitation to bid sent to prospective contractors were the technical specifications of the proposed work. These specifications did describe concrete sidewalks, some of which were included under Section G which pertained to road paving, and some of which were included as an additive alternate. (See finding 3(a) for the pertinent contract provisions). The term “additive alternate” is used to designate an item which is desirable but not essential. Both parties were aware of the term’s meaning. In the specifications distributed with the invitations to bid, the section dealing with additive alternates, including sidewalks, had been deleted. Accordingly, plaintiff did not include an estimate for the construction of concrete sidewalks in its bid.

On July 30, 1958 Contract No. AF 11 (626)-64 was awarded to plaintiff. The technical specifications which had accompanied the invitation to bid were incorporated into the contract.

In addition, the contract contained the following provisions:

GeNeral Provisions

*****
2. Specifications and drawings
The Contractor shall keep on the work a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown in the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or [134]*134mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. * * *
Special Provisions
H: $ * $ $
SP 1-02 Scope op work
All work which is manifestly necessary to carry out the intent of the drawings and specifications or which is customarily performed for such work shall be performed by the contractor. Any requirement shown on the drawings, but omitted from the specifications, or any requirement shown in the specifications but omitted from the drawings shall be considered as being required mider the contract as if set forth in both. Any change in drawings or specifications directed by the Contracting Officer shall be made in accordance with the clause hereof entitled “Changes.”

The sidewalk construction in dispute is a T-shaped area. The top of the “T” connects sidewalks leading from the on-site dwelling units at the project boundary line. Plain- ■ tiff’s interpretation of the specifications was that the deletion of the additive alternate providing for the concrete sidewalks completely eliminated any requirement on plaintiff's part to build concrete sidewalks.

Defendant contends that the deletion of the additive alternate providing for sidewalks only eliminated the requirement that plaintiff build those sidewalks which were additive .alternates and the off-site drawings contained a requirement for sidewalks which were not additive alternates.

The contract drawings which plaintiff had received are a series of 16 sheets. Sidewalks appear on sheets 5, 6, 7, 8, 9, 10, 11, 13, and 14. The areas designated as sidewalks are shown either by parallel solid lines or a series of parallel broken lines. On sheet 5, the area designated as a sidewalk is shown as parallel solid lines, and is referred to variously as a “new 5'0" cone, sidewalk” and a “new 5'0" cone, sidewalk (additive alternate).” Sheets 6, 7, 10, 11, 13, and 14 show part of the sidewalk area as parallel broken lines and part as parallel solid lines. Sheet 8 shows a portion of the sidewalk designated “additive alternate,” as both a series of [135]*135parallel broken lines and as of a sidewalk designated, as “concrete sidewalk, additive alternate,” as both a series of parallel broken lines and as parallel solid lines. Sheet 9 also shows a concrete sidewalk as parallel solid lines.

On November 18, 1958, plaintiff wrote, to defendant asking, among other things, “how to proceed with additive sidewalk item.” In the reply letter of December 2, 1958, defendant pointed out that a discussion of the matter had been forwarded to the Military Air Transport Service Headquarters and that no decision had as yet been received.

Plaintiff never received a site plan which provided for sidewalks. Further, plaintiff never received a copy of the Specifications for On-Site Work which did mention sidewalks. All that plaintiff did receive was the set of drawings discussed above. These drawings were not the same as a site plan.

On April 3, 1959 plaintiff informed defendant by letter that under its reading, the contract did not contain any requirement for the construction of sidewalks. The contracting officer, in a July 31 reply, directed that the sidewalks be constructed. Plaintiff protested the directive in its letter of August 6, 1959, but nevertheless proceeded with the installation of the sidewalks.

Upon completion of the sidewalks plaintiff submitted a claim for additional compensation in the sum of $4,684.21, and on December 21, 1959 plaintiff appealed the contracting officer’s interpretation of the contract to the Armed-Services Board of Contract Appeals.

On August 19, 1960 the Board rendered its decision denying plaintiff’s claim for extra compensation on the ground that the sidewalks in the off-site area were required by the contract. Plaintiff then initiated suit here.

Defendant first argues that the contract was clear and unambiguous; that the obligations and duties of both parties were clearly set forth in the instrument and the attendant documents and circumstances. Under defendant’s reading, the sidewalks were clearly required. Plaintiff on the other hand read the deletion of the additive alternate section as completely eliminating sidewalk construction from the con[136]*136tract. Plaintiff acted on this interpretation. It made no provision for sidewalk construction in its bid. Though the specifications provided that “Sidewalks shall be of size and location as per site plan” (see contract clause G-06 set out in finding 3(a)), plaintiff never received a site plan. The same clause provided for “b. Build in sockets” which defendant never required plaintiff to install.

The interpretation plaintiff adopted is reasonable. As we said in WPG Enterprises, Incorporated v. United States, 163 Ct. Cl. 1, 6, 323 F. 2d 874, 876-77 (1963) :

* * * As with so many other agreements, there is something for each party and no ready answer can be drawn from the texts alone. Both plaintiff’s and defendant’s interpretations lie within the zone of reasonableness; neither appears to rest on an obvious error in drafting, a gross discrepancy, or an inadvertent but glaring gap; the arguments, rather, are quite closely in balance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B. D. Click Co. v. United States
614 F.2d 748 (Court of Claims, 1980)
Monroe M. Tapper & Associates v. United States
602 F.2d 311 (Court of Claims, 1979)
Timber Access Industries Co. v. United States
553 F.2d 1250 (Court of Claims, 1977)
Maxwell Dynamometer Company v. United States
386 F.2d 855 (Court of Claims, 1967)
K E C O Industries, Inc. v. The United States
364 F.2d 838 (Court of Claims, 1966)
C. J. Montag & Sons, Inc. v. United States
348 F.2d 954 (Court of Claims, 1965)
Hunt & Willett, Inc. v. United States
351 F.2d 980 (Court of Claims, 1964)
H & H Manufacturing Co. v. United States
168 Ct. Cl. 873 (Court of Claims, 1964)
Commerce International Co. v. United States
167 Ct. Cl. 529 (Court of Claims, 1964)
Potter v. United States
167 Ct. Cl. 28 (Court of Claims, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
164 Ct. Cl. 131, 1964 U.S. Ct. Cl. LEXIS 38, 1964 WL 8537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wingate-construction-co-v-united-states-cc-1964.