Consolidated Engineering Co. ex rel. Fulton National Bank of Atlanta v. United States

98 Ct. Cl. 256, 1943 U.S. Ct. Cl. LEXIS 108, 1943 WL 4308
CourtUnited States Court of Claims
DecidedFebruary 1, 1943
DocketNo. 43159
StatusPublished
Cited by18 cases

This text of 98 Ct. Cl. 256 (Consolidated Engineering Co. ex rel. Fulton National Bank of Atlanta v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Engineering Co. ex rel. Fulton National Bank of Atlanta v. United States, 98 Ct. Cl. 256, 1943 U.S. Ct. Cl. LEXIS 108, 1943 WL 4308 (cc 1943).

Opinion

Madden, Judge,

delivered the opinion of the court:

Plaintiff is a Maryland corporation which is a successor to a Delaware corporation, the succession having taken place May 8,1933, after the predecessor corporation had completed the construction of the Department of Commerce building under a contract with the United States. The predecessor corporation subcontracted the plumbing, heating, and ventilating work on the building to W. S. Loftis, who did business as the Loftis Heating and Plumbing Company. He assigned to the Fulton National Bank, of Atlanta, Georgia, any amount due him under his subcontract, as security for advances made by the bank to him. Loftis and the bank are the real parties in interest on plaintiff’s side of this case. The term “plaintiff” is used to describe either the Delaware or the Maryland corporation.

Plaintiff’s contract with the Government was dated April 2, 1929, and the price was $13,567,000. Plaintiff’s subcontract with Loftis was dated April 19,1929, and the price was $1,200,000. The building was completed within the contract time. Loftis was paid $1,239,400.03 by plaintiff, which sum included certain extras beyond the work originally subcontracted to him. He and the bank nevertheless claim, through plaintiff, considerable sums for work and materials which they claim were required of Loftis beyond what he in his subcontract and plaintiff in its contract agreed to do, and for which the defendant has refused to pay.

Such of these claims as plaintiff has seriously urged here will be taken up seriatim.

[280]*280Painting

There was an ambiguity in the words of the writing making up plaintiff’s contract with the defendant with regard to the painting of the mechanical equipment which fell within Loftis’ subcontract. Paragraph 4 of the specifications called for the doing of all work necessary to completion of the building “except elevator and a dumb-waiter system and exclusive of those items of work which are specified as not included, as indicated on drawings and specified herein”. Paragraph 5, in pertinent part, was as follows:

The following items of work will not be included in this contract: Models, Decorating and all Painting except all shop coats for all trades and field painting of structural steel.

On the other hand, many pertinent paragraphs of the specifications provided in detail for the exact manner in which a complete painting job was to be done upon the pipes and equipment whose painting is here in question. The provisions of the specifications relevant to this question are quoted in finding 5. The inconsistency of Paragraph 5 of the specifications with these other provisions was so patent that it might well have evoked an inquiry from prospective bidders, including plaintiff, as to what the specifications really meant. Plaintiff, however, though fully aware of the ambiguity, instead of asking for a clarification, protected itself by discussing the question with Loftis when the subcontract was under negotiation, and insisting upon the following statement in the subcontract:

It is also understood and agreed that all painting referred to in these particular paragraphs and these Addenda specified to be done by the Heating or Plumbing contractor, is to be done by this subcontractor.

We think that plaintiff, aware of an ambiguity, perhaps inadvertent, in the defendant’s invitation to a contract, could not accept the contract and then claim that the ambiguity should be resolved favorably to itself. In these circumstances plaintiff in legal effect agreed with the defendant, and required Loftis to agree with it, to do whatever painting the defendant intended by the specifications, if the language [281]*281of the specifications might reasonably be interpreted to express such an intent. The defendant intended that the painting should be done as provided in detail in the specifications. That is what plaintiff bound itself to do, and Loftis’ obligation was the same as that of plaintiff. Besides, it was provided in Paragraph 15Á of the specifications that the decision of the architects as to the proper interpretation of the specifications should be final. Neither plaintiff nor Loftis has any just ground of complaint 'as to the painting.

Installation of Additional Air Compressors

The contract provided for two separate air compressor rooms, one in the north section and one in the south. The purpose of the compressors was to eject sewage from receptacles which were below the level of the city sewers. The specifications did not state the number of compressors to be installed, but Paragraph 804, describing the control panel in each room, specified for each room two of each of the accessories to the compressors, such as automatic starters, pressure gauges, etc. The contract drawings described in finding 6, each purporting to show one of the two air compressor rooms, make it plain that there were to be two compressors in each room. Defendant’s Exhibit 8 shows two compressors in one room, with an arrow pointing to each, and the plural “compressors” as the legend. Exhibit 9 shows two compressors, though the legend, “Air Compressor”, is in the singular. Exhibit 10 shows the two compressors as 9 does, and each compressor bears the separate legend “Air Compressor”. Exhibit 11 shows two compressors, with no accompanying legend. Of the several references in the drawings and contract writings, all of which were to be taken into account in ascertaining the meaning of the contract, only the use of the singular word “Compressor” on the drawing which is the defendant’s Exhibit 9 would have any tendency toward the construction of the contract for which plaintiff contends. Even on that drawing, the singular word in the legend was written across a figure of two compressors. We think the meaning of the contract was plain from the writings and drawings, and the in[282]*282stallation of,two compressors in each of the two compressor rooms was no more than plaintiff was legally bound to do. It may not, therefore, recover extra compensation for doing so.

Sewing on of Canvas Covering on Pipes

The contract required that certain pipes be covered with canvas. Employees of Loftis mistakenly covered additional pipes, and his superintendent did not notice that they were doing so. Loftis had the work stopped as soon as he learned of it. He claimed $10,450.17 for the extra work, and plaintiff asked that the claim be considered. The architects advised plaintiff that their estimate of the cost was only $1,734.56, and that they would recommend the allowance of a claim for that amount plus overhead and profit. This was done, but the Treasury Department rejected the claim because no change order had been given as required by the contract.

Loftis, by mistake, conferred upon the defendant an unrequested benefit by covering pipes which were not included in the contract. No legal duty to pay for this unrequested work arises out of these facts. The defendant was within its rights in refusing to pay for it.

Radiator Valves

The contract provisions relating to radiator valves are' quoted in finding 8. Loftis had received, on March 22, 1929, a quotation of $41,000 from the manufacturers of the “Sterlco” valve, for the valves needed on this contract, and he submitted a valve of that make for test by the Bureau of Standards, as the contract required.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Briscoe Co., Inc. v. County of Clark
772 F. Supp. 513 (D. Nevada, 1991)
James A. Mann, Inc. v. United States
535 F.2d 51 (Court of Claims, 1976)
Chris Berg, Inc. v. United States
455 F.2d 1037 (Court of Claims, 1972)
J. W. Bateson Co. v. United States
450 F.2d 896 (Court of Claims, 1971)
Morrison-Knudsen Company, Inc. v. The United States
397 F.2d 826 (Court of Claims, 1968)
L. Rosenman Corporation v. The United States
390 F.2d 711 (Court of Claims, 1968)
Tulelake Irrigation District v. The United States
342 F.2d 447 (Court of Claims, 1965)
Wingate Construction Co. v. United States
164 Ct. Cl. 131 (Court of Claims, 1964)
Wpc Enterprises, Incorporated v. The United States
323 F.2d 874 (Court of Claims, 1964)
WPC Enterprises, Inc. v. United States
323 F.2d 874 (Court of Claims, 1963)
MacDougald Construction Co. v. United States
122 Ct. Cl. 210 (Court of Claims, 1952)
Severin v. United States
99 Ct. Cl. 435 (Court of Claims, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
98 Ct. Cl. 256, 1943 U.S. Ct. Cl. LEXIS 108, 1943 WL 4308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-engineering-co-ex-rel-fulton-national-bank-of-atlanta-v-cc-1943.