Gus Kraus, Doing Business as Condor MacHine Works v. The United States

366 F.2d 975, 177 Ct. Cl. 108, 1966 U.S. Ct. Cl. LEXIS 88
CourtUnited States Court of Claims
DecidedOctober 14, 1966
Docket29-61
StatusPublished
Cited by13 cases

This text of 366 F.2d 975 (Gus Kraus, Doing Business as Condor MacHine Works v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gus Kraus, Doing Business as Condor MacHine Works v. The United States, 366 F.2d 975, 177 Ct. Cl. 108, 1966 U.S. Ct. Cl. LEXIS 88 (cc 1966).

Opinions

OPINION

COWEN, Chief Judge.1

This is a suit on a bid contract between the parties, dated June 30, 1958, designated N 228(217) 24792, pursuant to which plaintiff, conducting a tool and die business at San Francisco, California, manufactured and delivered to defendant’s San Francisco Naval Shipyard 2,300 quick-coupling securing straps made in three different overall lengths itemized as CRES Assemblies Nos. 1 through 3. The total contract price was $11,425, averaging about $5 per unit. The contract documents were drawn by the defendant.

After all deliveries had been made, defendant determined that the coupling straps were too short, and demanded that plaintiff rework them to provide overall lengths in conformity with defendant’s interpretation of contract requirements. Plaintiff complied, but reserved its right to claim additional costs as an equitable adjustment for a change in the contract specification ordered by defendant’s contracting officer.

After delivery of the reworked straps, defendant completed payment of the original contract price, as modified in respects not now relevant. The parties are agreed that if plaintiff is entitled to recover, judgment may be entered for plaintiff in the sum of $9,500 for his additional costs incurred for reworking the straps.

Pursuant to the standard Disputes article of the contract, hereinafter quoted in the findings of fact, the dispute concerning interpretation of the contract was decided adversely to plaintiff by defend[977]*977ant’s contracting officer, and, on plaintiff’s appeal, by the Armed Services Board of Contract Appeals (ASBCA No. 5535). In the trial of this case, the parties, pursuant to formal stipulation, agreed that the record of proceedings before the Board—

* * * may be received in evidence in this action before the Court of Claims, and that the same may be considered by the said Court for the purpose of determining whether the decision of the Armed Services Board of Contract Appeals, rendered September 9, 1960, is final and conclusive upon the respective parties or so arbitrary, capricious, unsupported by substantial evidence, or otherwise erroneous in law as to be deprived of such finality or conclusiveness. It is further stipulated by the respective parties that, aside from the foregoing record, which is jointly offered in evidence, no further proof will be offered or presented by or on behalf of either party hereto, each party agreeing and stipulating to the closing of its own proof upon the receipt of the foregoing record in evidence herein.

Following this language was the above-mentioned conditional agreement concerning amount of recovery, after which the parties agreed:

The foregoing stipulations have been entered into and subscribed by the respective parties upon their mutual agreement for the submission of the case without the necessity for proof de novo before the Court on the issues of liability and without the necessity for proof by the plaintiff on the issue of damages, which issue was not reached or determined by the Armed Services Board of Contract Appeals in the decision herein referenced.

The parties offered, and the trial commissioner received in evidence joint exhibits consisting of the full record of proceedings before the Board, comprised of the transcript of the hearing and testimony of witnesses before the Board, exhibits received in evidence by the Board, and other pertinent papers and documents forming the framework of the administrative record, including among others, the written decision of the Board after submission of the briefs of the parties on the merits, and also its decision on plaintiff’s motion for reconsideration. Proof was closed without any de novo evidence offered or presented in this case in this court. The facts set forth in this opinion and thereafter in the formal findings of fact are necessarily derived only from the Board’s record of proceedings.

The contract provides that CRES Assembly No. 1 was to consist of “lower strap, sub-assembly ‘1-A’, and upper strap, sub-assembly ‘1-B’. Dimensions to be in accordance with table on plan * * * ” CRES Assemblies Nos. 2 and 3 were described in the same language, except their respective sub-assemblies were designated as 2-A and 2-B, and 3-A and 3-B. All of the coupling straps were to be made in accordance with Bidder Data Plan No. CVA 702-1062956, Revision A, hereinafter called the contract drawing.

The quick-coupling securing strap consists in part of two flat stainless steel bands. At the coupling end of each band, there are attached one or more components of a latching mechanism by which the two bands may be locked together to form one coupling strap. When performed to specified curvátive requirements, this strap in locked position forms a figure roughly semicircular in shape, as shown by the “Stowage Assembly” side view of the strap on the contract drawing. By means of anchor holes perforated near the uncoupled ends, the strap is affixed to a rack on board ship to secure a military missile until the latching mechanism is disengaged for removal of the missile. Prior to the award of the contract in this case, plaintiff was advised of the intended use of the contract items by Navy personnel.

The table on the contract drawing, mentioned in the above-quoted contract description of CRES Assembly No. 1, set forth dimensions in a column headed “LG. IN INCHES,” showing 9.10 for “ASSEM NO 1-A” and 6.30 for “AS-[978]*978SEM NO 1 — B.” The like data for ORES Assemblies Nos. 2 and 3 were set forth in the table in the same manner, except that the figures varied, due to intended differences in the lengths of the three contract items.

In addition to the previously mentioned “Stowage Assembly” view, there was also set forth on the contract drawing an “Expanded View,” showing the strap extending in a flattened position with its bands locked together by the latching mechanism. Neither of the two views is drawn to scale, as they both apply to three straps of varying lengths. Both views contained general terminology designating the “lower strap” sub-assembly as “Assembly A” and the “upper strap” sub-assembly as “Assembly B,” not described as Assemblies Nos. 1-A, 1-B, etc., because of general applicability of both views to the three ORES Assemblies.

Six reference lines are drawn out from various parts of this flattened view of the locked coupling strap, representing in succession the (1) lower end of the lower strap, (2) the center line of the anchor hole of the lower strap, (3) the center line of the locking pin attached to the lower strap, (4) the center line of the toggle pin attached to the upper strap, (5) the center line of the anchor hole of the upper strap, and (6) the upper end of the upper strap.

In succession between the above-described reference lines, there are five successive dimensional lines extending along the length of the “Expanded View.” Each dimensional line starts and ends with an arrowhead, and the point of each arrowhead touches a reference line, so that each dimensional line extends between two successive reference lines.

In conjunction with each dimensional line, there is set forth either a longitudinal dimension, expressed in inches, or certain explanatory language, as hereinafter set forth in parentheses in this paragraph. The first dimensional line (%") extended from the uncoupled end of the lower strap to the center line of the anchor hole of the lower strap.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Watts Constructors, LLC
Armed Services Board of Contract Appeals, 2020
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
Carpenter v. United States
4 Cl. Ct. 705 (Court of Claims, 1984)
B. D. Click Co. v. United States
614 F.2d 748 (Court of Claims, 1980)
Gresham & Co. v. United States
470 F.2d 542 (Court of Claims, 1972)
Max Drill, Inc. v. The United States
427 F.2d 1233 (Court of Claims, 1970)
Pacific Far East Line, Inc. v. The United States
394 F.2d 990 (Court of Claims, 1968)
Maxwell Dynamometer Company v. United States
386 F.2d 855 (Court of Claims, 1967)
Maxwell Dynamometer Co. v. United States
386 F.2d 855 (Court of Claims, 1967)
Bishop Engineering Co. v. United States
180 Ct. Cl. 411 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
366 F.2d 975, 177 Ct. Cl. 108, 1966 U.S. Ct. Cl. LEXIS 88, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gus-kraus-doing-business-as-condor-machine-works-v-the-united-states-cc-1966.