Watts Constructors, LLC

CourtArmed Services Board of Contract Appeals
DecidedMarch 19, 2020
DocketASBCA No. 61493
StatusPublished

This text of Watts Constructors, LLC (Watts Constructors, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watts Constructors, LLC, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Watts Constructors, LLC ) ASBCA No. 61493 ) Under Contract No. W91238-14-C-0040 )

APPEARANCES FOR THE APPELLANT: Jason R. Thornton, Esq. Jeffrey B. Baird, Esq. Daniel P. Scholz, Esq. Finch, Thornton & Baird, LLP San Diego, CA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney A.L. Faustino, Esq. Robert W. Scharf, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Sacramento

OPINION BY ADMINISTRATIVE JUDGE PROUTY

Before us is a dispute about whether the terms of the above-captioned contract (the contract) for the construction of several buildings required appellant, Watts Constructors, LLC’s (Watts), electrical subcontractor to run electrical power lines in the buildings through rigid conduit as opposed to using more economical integrated metal clad (MC) cable. 1 Watts’s electrical subcontractor, Helix Electric, Inc. (Helix), saw what it wished to see when it reviewed the contract’s plans and specifications and used MC cable extensively in the construction. This was visible to quality assurance inspectors from the contracting agency, the United States Army Corps of Engineers (the Corps), but not objected to by the Corps until relatively late in the game. As will be discussed at length below, standard contract interpretation supports the Corps’ reading of its contract, requiring the exclusive use of conduit, not MC. Moreover, though it would have been far better for the quality assurance inspectors from the Corps to have recognized and halted Helix’s divergence from the requirements of the contract, their inaction did not change the meaning of the contract and was insufficient to support a finding of waiver of contractual compliance by the government.

1 The reader has likely seen MC cable in their experience: it’s an electrical power conductor surrounded by flexible grey metal as a single assembly (tr. 20; see also R4, tab 61 (photo) and tr. 165-66 (describing photo)). It comes in spools (tr. 91). FINDINGS OF FACT

I. Contract And Subcontract Awards

In the mid-2000s, the United States Army decided to build a facility for satellite communications on Camp Roberts, California near the town of Paso Robles (tr. 131 2 (inception of project in 2006)). The contract to accomplish this goal encompassed the construction of four buildings: a satellite communications operations center (by far, the largest of the buildings); a command/administrative support center; a repair and utilities building; and a covered storage shed (R4, tab 2 at 1). This contract, in the amount of $38,914,500, was awarded to Watts on September 3, 2014 (R4, tab 2 at 2). Shortly thereafter, Watts executed a subcontract agreement with Helix to perform all of the electrical work on the project (R4, tab 52 at 14-35; tr. 17-19).

The contract contained the standard Changes clause, to be found in Federal Acquisition Regulation (FAR) Part 52.243-4 providing authority of the contracting officer to change the terms of the contract (R4, tab 2 at 15-16).

II. The Contractual Requirements Relating To Wiring

The Corps has an institutional preference for utilizing rigid conduit to run electric power cable in buildings that it has constructed (tr. 150, 175). This is because the Corps believes that conduit-installed power lines will last longer (tr. 175-76). Helix personnel were well aware of this general desire (tr. 79), but held their own preference for power cabling, which was the use of flexible MC (tr. 22, 35, 81). As we will explain in Section III, below, although MC shares some of its characteristics, MC is not conduit.

Despite their concerns that the Corps would not permit the use of MC, Helix personnel involved in planning the construction found portions of the contract’s specifications that, they believed, permitted the use of MC cable throughout and which we note below (tr. 22-24).

Part 2 of the Interior Distribution System section of the Electrical portion of the contract’s specifications 3 is titled “Products” and lists required specifications for several dozen identified electrical distribution products. One of these products is MC, and the applicable subsection provides, in its entirety:

2 The hearing for this matter was held on a single day, thus there is only a single transcript volume in the record. 3 Unless stated otherwise, all references to contract sections in this opinion will be to the Interior Distribution System section of the Electrical section. 2 2.8.6 Metal-Clad Cable

UL 1569, 4 NFPA 70, 5 Type MC cable.

(R4, tab 4 at 1886 (footnotes not in original))

A government witness characterized this portion of the contract as “boilerplate” (tr. 150). Supporting this characterization, there are at least two other products listed in the Products category that were not applicable to the project: armored cable and flat conductor cable (tr. 177-78; R4, tab 4 at 1887 (Section 2.8.7, Armored Cable; Section 2.8.9, Flat Conductor Cable)).

The other location that MC is mentioned in the contract is in Part 3 of the specifications, labelled, “Execution.” Section 3.1, “Installation,” includes direction about how to install different items. MC is included in this section and the applicable subsection provides, in its entirety:

3.1.3.2 Metal Clad Cable

Install in accordance with NFPA 70. Type MC cable.

(R4, tab 4 at 1900) 6

Neither party has pointed to any other reference to MC in the contract (see app. br.; app. reply br.; gov’t br.), the government assertion that nothing in the contract drawings depicts anything other than electrical conduit (gov’t br. at 2-3, citing R4 tab 6 at 474-575 7) has never been fully rebutted by Watts (we discuss its one attempt to find MC in the drawings below), and we have reviewed the salient drawings 8, ourselves, and never found any depiction of MC for wiring.

4 “UL” refers to the Underwriter’s Laboratory (tr. 27). 5 “NFPA” refers to the National Fire Protection Agency, and the NFPA cited here is a national electric code (tr. 27-28). 6 By contrast, the specifications include approximately four pages governing means and methods of conduit installation in the subsections under subsection 3.1.4 (see R4, tab 4 at 1900-03). 7 The documents at tab 6 only go up to page 575, but the drawings referenced are within that smaller set. 8 Namely, drawings E-102, E-103, E-104, E-105, E-106, E-108, E-109, E-110, E-111, E-112, E-120, E-121, E-130, and E-131, which all may be found in tab 6 of the Rule 4 file, ranging from pages to 492-510. 3 Instead, the drawings accompanying the specifications refer only to conduit. The drawings included a legend for “Circuiting.” This legend referenced “wiring,” though not MC. One legend depiction shows a horizontal line with three angled lines crossing it. Next to this are the words:

CROSSLINES INDICATE NUMBER OF #12 CONDUCTORS EXCEPT NEUTRAL CONDUCTOR FOR MULTIWIRE BRANCH CIRCUIT SHALL BE #10 CONDUCTOR. EQUIPMENT GROUNDING CONDUCTOR IS NOT SHOWN. NO CROSSLINES INDICATES 2 - #12, ½” CONDUIT; OTHER CONDUCTOR AND CONDUIT SIZES AS INDICATED.

(R4, tab 6 at 474)

When examined about the meaning of these words by government counsel, Helix’s project manager, Mr. Shane Doner, agreed that this legend applied to all electrical lines to be installed under the contract (tr. 65-68). He further conceded that nothing in the drawings explicitly indicated the use of MC (tr. 65) and generally agreed that the drawings required the use of conduit (tr. 65, 67-68).

Watts argues that a portion of the drawings, nevertheless, allows for MC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
United States v. Santos Centeno
793 F.3d 378 (Third Circuit, 2015)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Hunkin Conkey Construction Co. v. United States
461 F.2d 1270 (Court of Claims, 1972)
Gresham & Co. v. United States
470 F.2d 542 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Watts Constructors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watts-constructors-llc-asbca-2020.