Hunkin Conkey Construction Co. v. United States

461 F.2d 1270, 198 Ct. Cl. 638, 1972 U.S. Ct. Cl. LEXIS 79
CourtUnited States Court of Claims
DecidedJune 16, 1972
DocketNo. 170-70
StatusPublished
Cited by5 cases

This text of 461 F.2d 1270 (Hunkin Conkey Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hunkin Conkey Construction Co. v. United States, 461 F.2d 1270, 198 Ct. Cl. 638, 1972 U.S. Ct. Cl. LEXIS 79 (cc 1972).

Opinion

Dueeee, Senior Judge,

delivered the opinion of the court:

Plaintiff, the Hunkin Conkey Construction Company [hereinafter referred to as either the contractor or plaintiff], entered into Contract No. DA-36-058-CIVENG-62-109 on October 16, 1961 with the United States, acting through the Army Corps of Engineers. The contract provided, inter alia, that the contractor would furnish all labor, materials and equipment, except for certain Government-furnished property, and perform all work necessary for the construction of Kinuza Dam, to be located on the Allegheny River in northern Pennsylvania.

During performance of the contract, it was discovered that the alluvial foundation materials in the embankment area [640]*640included alternate strata of fine sand and coarse open gravel. Unless corrective measures bad been taken, the high pressure heads from the water which would permeate these layers could have caused the foundation of the embankment to fail, and the dam to collapse. By letter dated March 26, 1963, the contractor formally notified the resident engineer of this condition, which the contractor thought to be a “changed condition.” This claim is pending bef ore the Corps of Engineers Board of Contract Appeals (Eng. BCA No. 2945) and is not in any way involved in this litigation. Following the notice of a possible changed condition, the Corps of Engineers began an intensive investigation of the permeable soils problem. Various test borings were made and the Corps began to contact various contractors who specialized in the construction of cut-off walls. At the same time, the Corps was urging the contractor to consider the possibility of an alternative method of cut-off, such as a concrete blanket or a slurry trench. In addition to considering the feasibility of an alternative method, the contractor solicited proposals for the construction of a cut-off wall from Spencer, Rodio & Soletanche, Inc., Icanda, Limited, and the Petrifond Foundation Company, Limited. By letters dated October 31 and November 7, 1963, the contractor forwarded two tentative proposals to the Corps of Engineers which incorporated estimates received from Spencer, Rodio & Soletanche, and Icanda, respectively. Subsequently, the Government decided to utilize a concrete cut-off wall, and at a meeting with Government representatives on January 31, 1964, the contractor was furnished with preliminary drawings showing the various sections of the wall and its proposed location. A work and payment schedule was also discussed. The contractor was told that the final plans and specifications were being prepared in such a manner that if the negotiations with the contractor proved to be fruitless, the work could be immediately advertised for bids.

In March 1964, the Government’s plans and specifications were sent to three specialty firms and to plaintiff with the request that plaintiff submit a proposal for the work, as prime contractor. The Government and plaintiff were unable to agree on the price for this additional work and therefore, [641]*641on May 9,1964 Government representatives sought, and subsequently obtained, authority to procure the construction of the cut-off wall by negotiation pursuant to 10 U.S.C. § 2804 (a) (2) and 32 C.F.E. § 3.202. Accordingly, in the latter part of May 1964, the contract for the construction of the cut-off wall (Contract No. DA-3 6-058-CI VEN G-64-692) was awarded to Icanda, Limited. The estimated amount of this contract was $2,374,086.00 as contrasted with plaintiff’s initial proposal of approximately $2,700,000.00, which was subsequently reduced by $75,000.00.

Plaintiff has completed performance on its contract for the construction of the Kinuza Dam, and this work has been accepted by the Government. The same is true with regard to the contract awarded to Icanda for the construction of the cut-off wall. Plaintiff contends that the Government breached its contract for the construction of the dam by awarding the contract for the cut-off wall to another contractor. As a matter of law, plaintiff must fail in this contention.

The construction of the cut-off wall was not provided for by the terms of the contract between plaintiff and the Government. Plaintiff contends, however, that since it was within the “general scope” of the contract, as that term is used in Article 3 of the general provisions, the “changes” clause,1 the Government was foreclosed from awarding a separate contract for the construction of this wall to another contractor. It is plaintiff’s position that this work should have been accomplished through a change order, with the disagreement over the price being resolved by the disputes procedure.

Even assuming that the “changes” clause, standing alone, is susceptible to the interpretation urged by plaintiff such [642]*642an interpretation is untenable in light of the “other contracts” clause, also contained in the subject contract, which provides that,

[t]he Government may undertake or award other contracts for additional work, and the Contractor shall fully cooperate with such other contractors and Government employees and carefully fit his own work to such additional work as may be directed by the Contracting Officer. The Contractor shall not commit or permit any act which will interfere with the performance of work by any other contractor or by Government employees.

If at all possible, a contract should be read as a whole and effect should be given to all of the contract terms. See, e.g., Trans International Airlines v. United States, 173 Ct. Cl. 312, 351 F. 2d 1001 (1965). Additional work as used in the above quoted provision simply means work not covered by the terms of the contract. See, John A. Johnson Contracting Corp. v. United States, 132 Ct. Cl. 645, 660, 132 F. Supp. 698, 708 (1955). Consequently, when the subject contract is read as a whole it provides that the Government may issue change orders for work within the general scope of the contract; however, the Government may instead award other contracts for such work. The case at bar does not present a situation in which the contractor was delayed or in any way hindered in its performance by the award of additional work to another contractor, and there is no need to determine what the result might be if either of these additional factors were present.

Plaintiff has cited Lovell v. United States, 59 Ct. Cl. 494 (1924) as holding that “the Government breached its agreement with plaintiff when it went ‘into the market’ to have additional sewer work performed.” In Lovell, the Government “deprive[d] the contractor of doing work clearly within the terms of the contract.” Lovell, supra at 516. The contract expressly provided that if a certain sewer were to be constructed, plaintiff would do the work; however, notwithstanding this provision, the Government had the work performed by another contractor. This is not the situation presented in the case at bar. The construction of the cut-off wall was not within the terms of the subject contract. In contending that the contractor should not be deprived of work which should [643]*643be performed pursuant to the agreement, plaintiff merely states a tautology.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2026
Goodloe Marine, Inc.
Armed Services Board of Contract Appeals, 2023
H2L1-CSC, JV
Armed Services Board of Contract Appeals, 2021
Watts Constructors, LLC
Armed Services Board of Contract Appeals, 2020
Charles F. Day & Associates LLC
Armed Services Board of Contract Appeals, 2018
North American Landscaping, Construction and Dredge, Co., Inc.
Armed Services Board of Contract Appeals, 2018

Cite This Page — Counsel Stack

Bluebook (online)
461 F.2d 1270, 198 Ct. Cl. 638, 1972 U.S. Ct. Cl. LEXIS 79, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hunkin-conkey-construction-co-v-united-states-cc-1972.