Charles F. Day & Associates LLC

CourtArmed Services Board of Contract Appeals
DecidedNovember 29, 2018
DocketASBCA No. 60211, 60212, 60213
StatusPublished

This text of Charles F. Day & Associates LLC (Charles F. Day & Associates LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles F. Day & Associates LLC, (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Charles F. Day & Associates LLC ) ASBCA Nos. 60211, 60212, 60213 ) Under Contract No. WlSQKN-11-C-0157 )

APPEARANCES FOR THE APPELLANT: Jeffrey L. Roth, Esq. Allen L. Anderson, Esq. Ryan G. Blount, Esq. F&B Law Firm, P.C. Huntsville, AL

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ Stephen P. Smith, JA CPT Meghan E. Mahaney, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE PROUTY

This appeal involves employees of appellant, Charles F. Day & Associates LLC (CFD), performing services for the United States in Iraq above and beyond the written requirements of the above-captioned contract (the contract) during a critical moment of our war effort. For this, CFD may be owed recognition but not additional compensation. A significant portion of the evidence presented by CFD was not presented to the contracting officer when CFD submitted its claims and we do not possess jurisdiction over appeals resting upon such new factual bases. Moreover, we cannot compensate the company for expenses that it would have incurred even had it not performed out of scope work, and must deny it the damages it seeks in this appeal.

FINDINGS OF FACT

I. The Award of the Contract and its Terms

The United States Army's Picatinny Contracting Center of the Picatinny Arsenal in New Jersey (the government) released the solicitation for the contract on April 7, 2011 (supp. R4, tab 564) 1• The contract which came from this solicitation was generally for providing support personnel relating to artillery - much of it overseas in Iraq and Afghanistan (see R4, tab 1). The appeal before us involves two contract line

1 The solicitation number was WlSQKN-11-R-COOl (R4, tab 2 at 5). item numbers (CLINs) in this larger contract. The first of these CLINs, CLIN 0005 (CLIN 5), was for the provision of three field service representatives (FSRs) to do work in Iraq on M109A5 self-propelled 155mm howitzers (the self-propelled howitzers) (R4, tab 1 at 8, 36). The second CLIN at issue, CLIN 0006 (CLIN 6). was for ten FSRs to do work on M198 towed 155mm howitzers (the towed howitzers). also in Iraq (id. at 9, 36). Of note, the contract included two option years for the FSRs I referenced in CLINs 5 and 6 (id. at 15-16 (option year 1), at 22-23 (option year 2)).

A. The Work Required of the FSRs

Several contract provisions described the work to be performed by these FSRs. Section 6 of the performance work statement (PWS) provided in part that the contractor would provide the 13 FSRs set forth by CLINs 5 and 6:

[W]ith primary focus on providing technical assistance; over-the-shoulder training; and onsite maintenance support of 24 [self-propelled howitzers] refurbished by the Maine Military Authority (MMA) and 120 [towed howitzers] refurbished by Joint Manufacturing & Technology Center (JMTC), Rock Island Arsenal. (24 [self-propelled] Howitzers are scheduled to arrive in Iraq by March 2011. [Deliveries of the towed howitzers] ... are scheduled to commence February 2011 with deliveries of 8 howitzers per month thru April 2012)[.]

(R4, tab 1 at 36)

Section 6.1.1 of the PWS provided that the three FSRs working on the self-propelled howitzers would primarily be located in Taji, Iraq, in support of the Iraqi 9th Mechanical Division, though they would also support the howitzers during live fire exercises in Besmaya, Iraq (R4, tab I at 36). Section 6.1.2 of the PWS provided that the FSRs working on the towed howitzers would also have a primary location of Taji, along with supporting their howitzers during live fire exercises in Besmaya (id.).

The PWS also included a section on "deprocessing" the towed howitzers (R4, tab 1 at 36-37). "Deprocessing," in this context, simply means taking howitzers that were packed for shipment to Iraq and received there and making them operational (tr. 1/19-20, 22-23, 2/60-61 ). It is generally not considered to be a particularly difficult process (id.), and Mr. Andrews, one of CFD's lead FSRs, testified that, nominally, the howitzers covered by the CLINs could each be deprocessed by one FSR working one day, although it could take longer if they were in poor condition (tr. 2/60-61). In any event, section 6.2 of the PWS provided that the FSRs would

2 deprocess 80 2 towed howitzers at Camp Taji as they arrived from their refurbishment by the Rock Island Arsenal (R4, tab 1 at 36). This section of the PWS repeated the anticipated schedule from paragraph 6, noted above, with 8 towed howitzers to be delivered a month from February 2011 to April 2012 (id.).

The section of the PWS about deprocessing, section 6.2.1, entitled, "Specific FSR/Deprocessing Support Tasks," went into some detail about the actions that would be accomplished during the deprocessing and also included subparagraph g, that in full, stated: "Provide [self-propelled howitzer] and [towed howitzer] Technical Assistance" (R4, tab I at 36-3 7).

B. The Hours to be Worked by the FSRs

The hours to be worked by the FSRs were set forth in two locations in the solicitation. CLINs 5 and 6 both included the annotation "4680 hours/year/person when deployed" (R4, tab I at 8-9). The PWS states, in section 5.1, "Hours of Duty":

On-site FSRs shall provide support as required to support the mission, including working extra hours, after-hours, and on weekends. The Contractor shall allocate 90 hours per work week for the FSRs deployed in .. .Iraq ....

The 90-hour workweeks for deployed FSRs (4,680 hours per year in the CLINs also equates to 90 hours per week multiplied by 52 weeks in a year) caused a potential contractor (not CFD (see tr. 1/44-45)) to submit a question to the contracting officer (CO) prior to contract award:

REF PWS paragraph 5.1 page 33 - Hours of Duty requires FSR's [sic] to perform a 90-hour work week. This would require working 13-hour days seven days per week. Sustained performance at this rate is extremely difficult. Our experience is that most everyone works a 72 hour week, 12 hours a day 6 days a week. Please clarify the anticipated work schedule for those deployed in Afghanistan and Iraq.

2 We cannot reconcile the PWS referring to 80 towed howitzers needing to be deprocessed, while other portions of the PWS refer to FSRs being responsible for 120 towed howitzers and the delivery schedule references 15 months of deliveries at 8 towed howitzers per month, which multiplies to 120 towed howitzers. Fortunately, we need not resolve this seeming conflict.

3 (App. supp. R4, tab 23 7 at 4) In response, the CO wrote: "Answer: The 90 hour work week allows for FSRs to be on call to provide support to units as necessary" (id.). This question and response joined all other questions and responses submitted by contractors as part of the solicitation process and were formally incorporated into the solicitation as a modification to the solicitation dated April 25, 2011 (app. supp. R4, tab 257 at 2, item 5). Other questions and answers incorporated into the solicitation included one that asked what would happen to the FSRs after they had deprocessed the howitzers and whether they would "remain on [the] ground to continue FSR support to other M 198 Howitzers." The response to this question was, "Yes. The FSRs remain on the ground." (App. supp. R4, tab 237 at 8) The response to another question stated that the self-propelled and towed howitzer mission in the contract was "to train Iraqi forces" (id.); and, in response to a question inquiring about "essential contracting tasks which are not clearly delineated in Para. 4.2.1.1," the CO responded that "[t]he essential tasks are 'supporting fielded L W 15 5 howitzers in Iraq and Afghanistan'. As indicated in 4.2.1.1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Sundance, Inc. v. DeMonte Fabricating Ltd.
550 F.3d 1356 (Federal Circuit, 2008)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Fruhauf Southwest Garment Co. v. United States
111 F. Supp. 945 (Court of Claims, 1953)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Zafer Taahhut Insaat Ve Ticaret A.S. v. United States
833 F.3d 1356 (Federal Circuit, 2016)
Lee's Ford Dock, Inc. v. Secretary of the Army
865 F.3d 1361 (Federal Circuit, 2017)
Inclusive Cmtys. Project, Inc. v. Lincoln Prop. Co.
920 F.3d 890 (Fifth Circuit, 2019)
Hunkin Conkey Construction Co. v. United States
461 F.2d 1270 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Charles F. Day & Associates LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-f-day-associates-llc-asbca-2018.