Zafer Taahhut Insaat Ve Ticaret A.S. v. United States

833 F.3d 1356, 2016 U.S. App. LEXIS 15077, 2016 WL 4375654
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 17, 2016
Docket2015-5083
StatusPublished
Cited by39 cases

This text of 833 F.3d 1356 (Zafer Taahhut Insaat Ve Ticaret A.S. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zafer Taahhut Insaat Ve Ticaret A.S. v. United States, 833 F.3d 1356, 2016 U.S. App. LEXIS 15077, 2016 WL 4375654 (Fed. Cir. 2016).

Opinion

Lourie, Circuit Judge.

Zafer Taahhut Insaat ve Ticaret A.S. (“Zafer”) appeals from the U.S. Court of Federal Claims’s (“Claims Court”) (1) grant of summary judgment that the Ü.S. Army Corps of Engineers (“USACE”) did not constructively change the terms of its contract with Zafer; and (2) denial of Zafer’s motion to supplement the record with several newspaper articles. Zafer Taahhut Insaat ve Ticaret A.S. v. United States, 120 Fed.Cl. 604, 612 (2015). For the reasons that follow, we affirm.

BACKGROUND

Zafer is an experienced construction contractor located in Ankara, Turkey. In May 2011, USACE entered into a firm-fixed-price contract with Zafer, No. W912BU-11-C0017, to construct the MIL-CON Consolidated Community Support Facility at the Bagram Air Force Field in Afghanistan. Under the terms of the contract, Zafer was responsible for delivering construction materials to the project’s site, and assumed the risk “for all costs and resulting loss or profit.” See 48 C.F.R. § 16.202-1. Further, the contract incorporated several standard Federal Acquisition Regulation (“FAR”) provisions, such as a Changes clause, FAR 52.243-4, a Default clause, FAR 52.249-10, and an F.O.B. Destination clause, FAR 47.303-6.

The Default clause is of particular relevance here. It provides, in pertinent part:

(b) The Contractor’s right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if—
(1) The delay in completing the work arises from unforeseeable causes beyond *1359 the control and without the fault or negligence of the Contractor.... ; and
(2) The Contractor, within 10 days from the beginning of any delay ..., notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay. If, in the judgment of the Contracting Officer, the findings of fact warrant such action, the time for completing the work shall be extended....

48 C.F.R. § 52.249-10(b) (2007).

In June 2011, Zafer received a notice to proceed with the contract, with a contract completion date in November 2012. USACE later recognized that it could not make the project site available until June 2012, and it accordingly issued a bilateral modification that increased the contract price and set a new completion date in October 2013.

In November 2011, the government of Pakistan closed its border from the seaport city of Karachi along the land routes into Afghanistan (“the Karachi/Afghan route”) in response to a combat incident with the U.S. and the North Atlantic Treaty Organization (“U.S./NATO incident”) that allegedly killed twenty-four Pakistani citizens. The route remained closed for 219 days, until July 2012.

By letter dated March 20, 2012, Zafer notified USACE that the closure of the Karachi/Afghan route would greatly impact its delivery of materials, as required under the contract. See Joint App. (“J.A.”) 29-30. Specifically, Zafer noted that the “unexpected closure” of the Karachi/Afghan route grossly affected its logistics because a “considerable amount of project materials/equipment are stuck at the Pakistan border.” J.A. 29. As Zafer indicated, “[njineteen (19) of [the twenty-four] shipments are already at Karachi and have not been allowed to move for a long time.” J.A. 29. Zafer then requested direction on how to-proceed, e.g., if it should ship via another route with increased shipping time and associated costs. J.A. 30.

USACE replied on June 27, 2012, acknowledging the difficulties arising from the closure of the Karachi/Afghan route. J.A. 31. It informed Zafer, however, that because the closure was “purely the act of Pakistan governmental authorities,” and the U.S. government was “not responsible for these sovereign acts of a foreign nature,” Zafer was nevertheless obliged to deliver the materials and supplies by “any means necessary,” without further compensation. J.A. 31. USACE then stated that its contract with Zafer allows for a non-compensable time extension in the event of an unforeseeable delay. See J.A. 31 (referencing the Default clause, FAR 52.249-10). And, if Zafer “believe[s] that [it is] entitled to a non-compensable extension of time to perform ... [, it] may submit a request to the [contracting officer].” J.A. 31. USACE specified that any request “must fully explain why the delay was unforeseeable” and “include documentation of the date when the materials or equipment were shipped and when the delay began at the Pakistan border.” J.A. 31.

Soon thereafter, on July 11, 2012, Zafer responded to USACE’s letter. Zafer acknowledged that, by July 11, the Karachi/Afghan route had reopened, but stated: “We want to put [USACE] on notice of Zafer’s entitlement to additional time, but also several additional entitlements for increased costs occasioned by the border closing.” J.A. 32. Zafer then outlined several categories of costs, including constructive acceleration costs, port detention and demurrage, and extended overhead. J.A. 32. It finally concluded its letter by challenging USACE’s position that USACE was not responsible for any additional costs incurred. See J.A. 33-34.

USACE did not immediately respond to Zafer’s July 11, 2012 letter. So, on October *1360 24, 2012, Zafer sent another letter to USACE with an update, indicating that the materials and equipment held at the Karachi port “have now begun the process of being released back into normal distribution,” and that the Pakistan government demands “extra payment before [it] will release these shipments.” J.A. 36. Zafer asked for payment to cover the additional costs, and for direction on how to proceed. J.A. 36.

That same day, October 24, USACE replied, repeating its earlier, June 27, 2012 letter. USACE stated that Zafer remains responsible for delivering all materials “by whatever means necessary,” and that USACE “will not assume responsibility for any increased costs of delivering construction material and equipment.” J.A, 37. USACE last noted that, under the terms of the contract, Zafer could request a non-compensable time extension, and that any request should “explain why the delay was unforeseeable” and “include documentation of the date when the materials or equipment were shipped and when the delay began.” J.A. 37.

Zafer replied on October 31, 2012, challenging whether USACE should bear responsibility for increased costs. In particular, Zafer argued that the border closure was not solely the result of “acts of a sovereign not under the control of the US,” but rather a result “of US/NATO firing accident.” J.A. 38. It reiterated that it “wishe[d] to put USACE on notice of Zafer’s entitlement to additional time and also additional entitlement for increased costs.” See J.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al Ghanim Combined Group W.L.L.
Armed Services Board of Contract Appeals, 2026
Shoreline Foundation, Inc.
Armed Services Board of Contract Appeals, 2026
David Boland, Inc.
Armed Services Board of Contract Appeals, 2024
Targe Logistic Services Company
Armed Services Board of Contract Appeals, 2024
Sheffield Korte Joint Venture
Armed Services Board of Contract Appeals, 2023
Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023
Frazier Investments, Inc. d/b/a Optimum Construction
Armed Services Board of Contract Appeals, 2023
Heart & Core LLC
Armed Services Board of Contract Appeals, 2023
Ace Electronics Defense Systems
Armed Services Board of Contract Appeals, 2022
ACC Construction Co., Inc.
Armed Services Board of Contract Appeals, 2022
Wilwood Engineering Inc.
Armed Services Board of Contract Appeals, 2022
Jones v. United States
Federal Circuit, 2022
Skanska USA Building, Inc.
Armed Services Board of Contract Appeals, 2021
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
GSC Construction Incorporated
Armed Services Board of Contract Appeals, 2019

Cite This Page — Counsel Stack

Bluebook (online)
833 F.3d 1356, 2016 U.S. App. LEXIS 15077, 2016 WL 4375654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zafer-taahhut-insaat-ve-ticaret-as-v-united-states-cafc-2016.