amatea/grimberg Jv v. Secretary of the Navy

CourtCourt of Appeals for the Federal Circuit
DecidedJune 25, 2025
Docket24-1006
StatusUnpublished

This text of amatea/grimberg Jv v. Secretary of the Navy (amatea/grimberg Jv v. Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
amatea/grimberg Jv v. Secretary of the Navy, (Fed. Cir. 2025).

Opinion

Case: 24-1006 Document: 37 Page: 1 Filed: 06/25/2025

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

AMATEA/GRIMBERG JV, Appellant

v.

SECRETARY OF THE NAVY, Appellee ______________________

2024-1006 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in Nos. 60426, 60427, 60428, 60689, 60690, 60691, 61252, 61402, 61715, Administrative Judge J. Reid Prouty, Administrative Judge Elizabeth Witwer, Administrative Judge Richard Shackleford. ______________________

Decided: June 25, 2025 ______________________

ARNIE MASON, Williams Mullen, PC, Tysons, VA, ar- gued for appellant. Also represented by ZAHRA RIZVI SYED.

BRYAN MICHAEL BYRD, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, STEVEN JOHN GILLINGHAM, PATRICIA M. MCCARTHY. Case: 24-1006 Document: 37 Page: 2 Filed: 06/25/2025

2 AMATEA/GRIMBERG JV v. SECRETARY OF THE NAVY

______________________

Before MOORE, Chief Judge, PROST and HUGHES, Circuit Judges. HUGHES, Circuit Judge. Amatea/Grimberg Joint Venture appeals the decision of the Armed Services Board of Contract Appeals that de- nied AGJV’s constructive acceleration claim and work hours claim. Because we conclude that the Board applied the correct legal standards and substantial evidence sup- ports the Board’s conclusions, we affirm. I In July 2009, the Navy issued a request for proposals seeking a contractor to design and build the Energetics System and Technology Laboratory Complex for the Naval Surface Warfare Center in Indian Head, Maryland. J.A. 1–2. In September, the Navy awarded the contract to AGJV with a contract completion date of March 31, 2011. J.A. 3. In May 2010, the parties agreed to bilateral contract modifications that provided for enhancements to increase the building’s energy efficiency. J.A. 3. Because of this mod- ification and other delays, the contract completion date was changed from March 31, 2011, to March 29, 2012. J.A. 3–4, 39. But AGJV did not complete the project within this ex- tended time frame. The Navy eventually found that the project was ready for beneficial occupancy six months later, on September 29, 2012. J.A. 62. The contract contained the standard liquidated dam- ages clause found in the Federal Acquisition Regulation (FAR) at section 52.211-12 entitled “Liquidated Damages – Construction (SEP 2000),” which, modified to include a spe- cific dollar amount, provides in part that: “[i]f the Contrac- tor fails to complete the work within the time specified by the contract, the Contractor shall pay liquidated damages to the government in the amount of $5,250 for each calen- dar day of delay until the work is completed or accepted.” Case: 24-1006 Document: 37 Page: 3 Filed: 06/25/2025

AMATEA/GRIMBERG JV v. SECRETARY OF THE NAVY 3

J.A. 3. The Navy originally assessed liquidated damages from March 29, 2012, until September 29, 2012, but later released a portion of the damages. J.A. 36–38. AGJV submitted a claim for constructive acceleration costs because AGJV had to direct its subcontractors to work overtime and add resources after its time extension request was denied. AGJV contended that the government demanded it complete additional work on an electronic se- curity system (ESS) and fire sprinklers without extending the performance period or granting it night or weekend work, so AGJV had to “accelerate its work to minimize the government’s imposition of liquidated damages.” J.A. 63. The contracting officer (CO) denied this claim, and AGJV appealed to the Board. AGJV also submitted a claim to the CO seeking a deci- sion that the Navy’s denial of AGJV’s request to work out- side of regular work hours was a breach of contract. J.A. 23. The contract stated that regular working hours on the pro- ject would be from 7:00 am to 3:30 pm, Monday through Friday, and that work outside of regular hours required CO approval. J.A. 17. In pertinent part, the contract stated, “[b]ased on the justification provided, the Contracting Of- ficer may approve work outside regular hours . . . .” J.A. 17 (emphasis added). Because AGJV was running behind schedule, it requested approval to work outside of regular hours. J.A. 16. The Navy denied AGJV’s request to work every Saturday until the end of the job, but it did extend the work hours on Monday through Friday to 6:30 am to 6:30 pm and granted AGJV’s request to work on three Sat- urdays to resolve utilities issues. J.A. 20–21. The Navy did not decide this breach of contract claim within 60 days, so it was deemed denied, and AGJV appealed to the Board. The Board denied this claim. AGJV timely filed its notice of appeal. We have juris- diction under 41 U.S.C. § 7107(a)(1) and 28 U.S.C § 1295(a)(10). Case: 24-1006 Document: 37 Page: 4 Filed: 06/25/2025

4 AMATEA/GRIMBERG JV v. SECRETARY OF THE NAVY

II We review the Board’s determinations on questions of law, including questions of contract interpretation, de novo. Reliable Contracting Grp., LLC v. Dep’t of Veterans Affs., 779 F.3d 1329, 1331 (Fed. Cir. 2015). The Board’s fac- tual determinations may not be set aside unless they are “(A) fraudulent, arbitrary or capricious; (B) so grossly erro- neous as to necessarily imply bad faith; or (C) not sup- ported by substantial evidence.” 41 U.S.C. § 7107(b)(2); see also Rockies Express Pipeline LLC v. Salazar, 730 F.3d 1330, 1335 (Fed. Cir. 2013). “Substantial evidence is such relevant evidence as a reasonable mind might accept as ad- equate to support a conclusion.” Braun v. Dep’t of Health & Hum. Servs., 983 F.3d 1295, 1301 (Fed. Cir. 2020) (internal quotation marks and citations omitted). III AGJV appeals two issues: (1) the denial of its construc- tive acceleration appeal and (2) the denial of its work hours appeal. We discuss each issue in turn. A “Constructive acceleration often occurs when the gov- ernment demands compliance with an original contract deadline, despite excusable delay by the contractor.” Zafer Taahhut Insaat ve Ticaret A.S. v. United States, 833 F.3d 1356, 1562 (Fed. Cir. 2016). The five elements of construc- tive acceleration are: (1) the contractor encountered an ex- cusable delay; (2) the contractor made a timely request for an extension of time to complete the contract; (3) the gov- ernment denied the request or did not act on it in a reason- able period of time; (4) the government insisted on completion of the contract in a lesser period of time than the excusable delay would have permitted; and (5) the con- tractor incurred added expense to compensate for the lost time and remain on schedule. Id. at 1362 (citing Fraser Constr. Co. v. United States, 384 F.3d 1534, 1360–61 (Fed. Cir. 2004)). An excusable delay results from Case: 24-1006 Document: 37 Page: 5 Filed: 06/25/2025

AMATEA/GRIMBERG JV v. SECRETARY OF THE NAVY 5

“unforeseeable causes beyond the control and without the fault or negligence of the Contractor.” FAR 52.249-10(b)(1). The unforeseeable cause must also affect the “critical path of performance,” delaying contract completion. Sauer Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
amatea/grimberg Jv v. Secretary of the Navy, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amateagrimberg-jv-v-secretary-of-the-navy-cafc-2025.