amatea/grimberg Jv v. Secretary of the Navy

Court of Appeals for the Federal Circuit·Decided June 25, 2025·No. 24-1006·Unpublished

Opinion

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

AMATEA/GRIMBERG JV,

Appellant

v.

SECRETARY OF THE NAVY,

Appellee

2024-1006

Appeal from the Armed Services Board of Contract Appeals in Nos. 60426, 60427, 60428, 60689, 60690, 60691, 61252, 61402, 61715, Administrative Judge J. Reid Prouty, Administrative Judge Elizabeth Witwer, Administrative Judge Richard Shackleford.

Decided: June 25, 2025

ARNIE MASON, Williams Mullen, PC, Tysons, VA, argued for appellant. Also represented by ZAHRA RIZVI SYED.

BRYAN MICHAEL BYRD, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington , DC, argued for appellee. Also represented by BRIAN M. BOYNTON, STEVEN JOHN GILLINGHAM, PATRICIA M. MCCARTHY.

2 AMATEA/GRIMBERG JV v. SECRETARY OF THE NAVY

Before MOORE, Chief Judge, PROST and HUGHES, Circuit Judges.

HUGHES, Circuit Judge.

Amatea/Grimberg Joint Venture appeals the decision of the Armed Services Board of Contract Appeals that denied AGJV’s constructive acceleration claim and work hours claim. Because we conclude that the Board applied the correct legal standards and substantial evidence supports the Board’s conclusions, we affirm.

I

In July 2009, the Navy issued a request for proposals seeking a contractor to design and build the Energetics System and Technology Laboratory Complex for the Naval Surface Warfare Center in Indian Head, Maryland. J.A. 1–2. In September, the Navy awarded the contract to AGJV with a contract completion date of March 31, 2011. J.A. 3. In May 2010, the parties agreed to bilateral contract modifications that provided for enhancements to increase the building’s energy efficiency. J.A. 3. Because of this modification and other delays, the contract completion date was changed from March 31, 2011, to March 29, 2012. J.A. 3–4, 39. But AGJV did not complete the project within this extended time frame. The Navy eventually found that the project was ready for beneficial occupancy six months later, on September 29, 2012. J.A. 62.

The contract contained the standard liquidated damages clause found in the Federal Acquisition Regulation (FAR) at section 52.211-12 entitled “Liquidated Damages – Construction (SEP 2000),” which, modified to include a specific dollar amount, provides in part that: “[i]f the Contractor fails to complete the work within the time specified by the contract, the Contractor shall pay liquidated damages to the government in the amount of $5,250 for each calendar day of delay until the work is completed or accepted.”

AMATEA/GRIMBERG JV v. SECRETARY OF THE NAVY 3

J.A. 3. The Navy originally assessed liquidated damages from March 29, 2012, until September 29, 2012, but later released a portion of the damages. J.A. 36–38.

AGJV submitted a claim for constructive acceleration costs because AGJV had to direct its subcontractors to work overtime and add resources after its time extension request was denied. AGJV contended that the government demanded it complete additional work on an electronic security system (ESS) and fire sprinklers without extending the performance period or granting it night or weekend work, so AGJV had to “accelerate its work to minimize the government’s imposition of liquidated damages.” J.A. 63. The contracting officer (CO) denied this claim, and AGJV appealed to the Board.

AGJV also submitted a claim to the CO seeking a decision that the Navy’s denial of AGJV’s request to work outside of regular work hours was a breach of contract. J.A. 23. The contract stated that regular working hours on the project would be from 7:00 am to 3:30 pm, Monday through Friday, and that work outside of regular hours required CO approval. J.A. 17. In pertinent part, the contract stated, “[b]ased on the justification provided, the Contracting Officer may approve work outside regular hours . . . .” J.A. 17 (emphasis added). Because AGJV was running behind schedule, it requested approval to work outside of regular hours. J.A. 16. The Navy denied AGJV’s request to work every Saturday until the end of the job, but it did extend the work hours on Monday through Friday to 6:30 am to 6:30 pm and granted AGJV’s request to work on three Saturdays to resolve utilities issues. J.A. 20–21. The Navy did not decide this breach of contract claim within 60 days, so it was deemed denied, and AGJV appealed to the Board. The Board denied this claim.

AGJV timely filed its notice of appeal. We have jurisdiction under 41 U.S.C. § 7107(a)(1) and 28 U.S.C § 1295(a)(10).

4 AMATEA/GRIMBERG JV v. SECRETARY OF THE NAVY

II

We review the Board’s determinations on questions of law, including questions of contract interpretation, de novo. Reliable Contracting Grp., LLC v. Dep’t of Veterans Affs., 779 F.3d 1329, 1331 (Fed. Cir. 2015). The Board’s factual determinations may not be set aside unless they are “(A) fraudulent, arbitrary or capricious; (B) so grossly erroneous as to necessarily imply bad faith; or (C) not supported by substantial evidence.” 41 U.S.C. § 7107(b)(2); see also Rockies Express Pipeline LLC v. Salazar, 730 F.3d 1330, 1335 (Fed. Cir. 2013). “Substantial evidence is such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.” Braun v. Dep’t of Health & Hum. Servs., 983 F.3d 1295, 1301 (Fed. Cir. 2020) (internal quotation marks and citations omitted).

III

AGJV appeals two issues: (1) the denial of its constructive acceleration appeal and (2) the denial of its work hours appeal. We discuss each issue in turn.

A

“Constructive acceleration often occurs when the government demands compliance with an original contract deadline, despite excusable delay by the contractor.” Zafer Taahhut Insaat ve Ticaret A.S. v. United States, 833 F.3d 1356, 1562 (Fed. Cir. 2016). The five elements of constructive acceleration are: (1) the contractor encountered an excusable delay; (2) the contractor made a timely request for an extension of time to complete the contract; (3) the government denied the request or did not act on it in a reasonable period of time; (4) the government insisted on completion of the contract in a lesser period of time than the excusable delay would have permitted; and (5) the contractor incurred added expense to compensate for the lost time and remain on schedule. Id. at 1362 (citing Fraser Constr. Co. v. United States, 384 F.3d 1534, 1360–61 (Fed. Cir. 2004)). An excusable delay results from

AMATEA/GRIMBERG JV v. SECRETARY OF THE NAVY 5

“unforeseeable causes beyond the control and without the fault or negligence of the Contractor.” FAR 52.249-10(b)(1). The unforeseeable cause must also affect the “critical path of performance,” delaying contract completion. Sauer Inc. v. Danzig, 224 F.3d 1340, 1345 (Fed. Cir. 2000).

The Board denied AGJV’s constructive acceleration claim because “there was no excusable delay for most of the work on the project (e.g., the roof, the HVAC system, and the windows), and that was the work that dragged completion of the project out to September 18, 2012.” J.A. 64. The Board underscored that AGJV did not provide an expert’s critical path analysis, stating “there has been zero evidence presented by AGJV that work on the ESS or the fire sprinklers caused a delay in the critical path to project completion and certainly nothing on the order of the amount of time that the Navy ultimately granted.” J.A. 64. The Board noted that, even accounting for the extension associated with the ESS, AGJV was still almost four weeks late in completing the project. J.A. 64. Thus, the Board found that AGJV failed to prove the first element of a constructive acceleration claim: excusable delay.

Free access — add to your briefcase to read the full text and ask questions with AI

amatea/grimberg Jv v. Secretary of the Navy, (Fed. Cir. 2025).

amatea/grimberg Jv v. Secretary of the Navy (amatea/grimberg Jv v. Secretary of the Navy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related