Reliable Contracting Group, LLC v. Department of Veterans Affairs

779 F.3d 1329, 2015 U.S. App. LEXIS 3548, 2015 WL 968105
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 6, 2015
Docket2014-1326
StatusPublished
Cited by15 cases

This text of 779 F.3d 1329 (Reliable Contracting Group, LLC v. Department of Veterans Affairs) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliable Contracting Group, LLC v. Department of Veterans Affairs, 779 F.3d 1329, 2015 U.S. App. LEXIS 3548, 2015 WL 968105 (Fed. Cir. 2015).

Opinions

Before NEWMAN, CLEVENGER, and DYK, Circuit Judges.

Opinion for the court filed by Circuit Judge DYK. Dissenting, opinion filed by Circuit Judge NEWMAN.

DYK, Circuit Judge.

Reliable Contracting Group, LLC (“Reliable”) appeals from a decision by the Civilian Board of Contract Appeals (“Board”). The Board denied Reliable’s claim for an equitable adjustment of a Department of Veterans Affairs (‘VA”) contract which required the installation of three backup generators for a VA medical center. Reliable contends that the VA improperly rejected the generators on the ground that they were not “new” as required by the contract. Because we hold that the Board erred in its interpretation of the contract, we vacate the Board’s decision and remand for further proceedings.

BACKGROUND

On February 10, 2003, the VA awarded a contract to Echo Construction Company (“Echo”) for the design and construction of electrical improvements at a VA medical center. On March 31, 2003, Echo, the VA, and Reliable entered into a novation agreement, effectively replacing Echo with Reliable.

The contract required that three backup generators be installed. Section 1.47 of the contract, entitled “MATERIAL AND WORKMANSHIP,” required that “[a]ll equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract.” J.A. 79. That section did not define “new.” Separately, § 1.79 incorporated Federal Acquisition Regulation (“FAR”) 52.211-5 by reference. FAR 52.211-5 contained a separate requirement that supplies called for by the contract be “new, reconditioned, or remanufactured,” and it defined “new” to require that the supplies be “composed of previously unused components.” See 48 C.F.R. § 52.211-5.

[1331]*1331Reliable sub-contracted the procurement of the electrical generators to Fisk Electric Company (“Fisk”), which in turn contracted with DTE Energy Technologies, Inc. (“DTE”) to provide the generators. On June 26 and 27 of 2004, DTE delivered two Cummins Power Generation (“Cum-mins”) generators to the construction site. Upon delivery, the VA’s senior resident engineer, Leonard Romano, inspected the two generators and determined that they were, in his view, not “new.” He wrote to Reliable, stating:

I am concerned that [the two generators that were delivered] are not “new” as required by [§ 1.47(a)]. They show a lot of wear and tear including field burns to enlarge mounting holes. Are they new and will you certify them as such? I cannot pay you for these as planned in this month’s payment without that certification.

J.A. 2.

This letter initiated a flurry of letters between Romano, Reliable, Fisk, and DTE, with Fisk and Reliable initially expressing agreement that the generators did not meet the contract specification. For example, on June 28, Fisk wrote to DTE, stating: “[m]y foreman noted that the units were in ‘BAD CONDITION’ and proceeded to install the units.” J.A. 102. Similarly, on June 29, Reliable wrote to Fisk, stating: “[a]s we discussed with you, the equipment on site is clearly unacceptable by anyone’s standards.... ” J.A. 109. On that same day, Reliable wrote to Romano, stating:

Representatives of Fisk have assured us that they were as surprised as anyone at the condition of the equipment delivered to the site. We have been working closely with Fisk personnel to investigate the matter and per our conversation have directed them to remove the nonconforming generators from the project site. J.A. 303. Both Fisk and Reliable personnel continued to investigate the matter, and Romano continued to assert his belief that the generators were not conforming.
After investigation, Reliable and Fisk came to the conclusion that the generators, which were manufactured in 2000, had been previously purchased by others but never used. Reliable presented this information to Romano on July 9, but Romano nonetheless rejected the generators, asserting that “[p]revious ownership makes them used.” J.A. 6. Subsequently, Fisk obtained different generators, which were accepted by the VA and installed.

On April 3, 2007, Reliable submitted a claim to the VA, alleging that the VA had violated the contract and seeking roughly $1,100,000 for additional costs incurred as a result of the VA’s rejection of the three original génerators. The VA failed to timely respond, so Reliable appealed to the Board. On November 27, 2013, the Board denied Reliable’s claim, finding that the generators were not “new” because they were not capable-of being factory' tested. Reliable appealed to this court.

We have jurisdiction pursuant to 41 U.S.C. § 7107(a)(1)(A).

DISCUSSION

We review questions of law, including interpretations of contracts, de novo. Rockies Express Pipeline LLC v. Salazar, 730 F.3d 1330, 1335-36 (Fed.Cir. 2013). We review factual questions for substantial evidence. Id. at 1335.

The parties’ dispute centers around the contract’s requirement that the generators be “new.” The Board held, and the VA presently argues, that “new” requires that each generator be “capable of being tested at the factory.” J.A. 8. This definition comes from the language of § 1.79, which incorporates FAR 52.211-5’s requirement that the generators’ supplies [1332]*1332“meet contract requirements” to be considered “new,” 48 C.F.R. § 52.211-5, and § 16208, which requires that the generators be capable of factory testing.1 Because the generators left the factory in 2000, the Board reasoned, they were incapable of being factory tested in 2004 and therefore not “new.” On the other hand, Reliable argues that the contract is clear on its face because § 1.79 provides an express definition of “new”: “new” means comprised of unused parts. According to Reliable, because the generators had never been used, they were “new” even though previously owned and damaged by improper storage. We reject both interpretations.

We reject the VA’s and the Board’s interpretation for two reasons. First, the VA never contemporaneously argued that the generators were non-conforming because they were incapable of being factory tested. Generally, evidence of contemporaneous beliefs about the contract is particularly probative of the meaning of a contract. See Blinderman Constr. Co. v. United States, 695 F.2d 552, 558 (Fed.Cir. 1982) (“It is a familiar principle of contract law that the parties’ contemporaneous construction of an agreement, before it has become the subject of a dispute, is entitled to great weight in its interpretation.”); Max Drill, Inc. v. United States, 427 F.2d 1233

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ECC International Constructors, LLC
Armed Services Board of Contract Appeals, 2025
ECC International LLC
Armed Services Board of Contract Appeals, 2021
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
Professional Management Consulting Services, LLC
Armed Services Board of Contract Appeals, 2020
Canpro Investments, Ltd v. United States
130 Fed. Cl. 320 (Federal Claims, 2017)
Shell Oil Company v. United States
130 Fed. Cl. 8 (Federal Claims, 2017)
Saighi v. General Services Administration
645 F. App'x 993 (Federal Circuit, 2016)
Raytheon Company
Armed Services Board of Contract Appeals, 2016

Cite This Page — Counsel Stack

Bluebook (online)
779 F.3d 1329, 2015 U.S. App. LEXIS 3548, 2015 WL 968105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliable-contracting-group-llc-v-department-of-veterans-affairs-cafc-2015.