Granite Construction Company v. The United States

962 F.2d 998, 37 Cont. Cas. Fed. 76,290, 1992 U.S. App. LEXIS 12548, 1992 WL 62127
CourtCourt of Appeals for the Federal Circuit
DecidedMay 29, 1992
Docket91-5107
StatusPublished
Cited by71 cases

This text of 962 F.2d 998 (Granite Construction Company v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Granite Construction Company v. The United States, 962 F.2d 998, 37 Cont. Cas. Fed. 76,290, 1992 U.S. App. LEXIS 12548, 1992 WL 62127 (Fed. Cir. 1992).

Opinion

COWEN, Senior Circuit Judge.

In this Wunderlich Act case, Granite Construction Company (Granite) appeals from the decision of the United States Claims Court, 22 Cl.Ct. 831, which affirmed the decision of the Corps of Engineers Board of Contract Appeals (Board), ENG BCA No. 4496, 89-1 B.C.A. (CCH) ¶ 21,447, 1988 WL 143116. The Board denied Granite’s claim for recovery of costs incurred in the removal and replacement of waterstop in a lock and dam construction project. For the reasons to be set forth, we reverse and remand.

*1000 BACKGROUND

On October 26, 1976, Granite entered into a $36,263,924 contract with the U.S. Army Corps of Engineers (Corps) for the construction of a lock and dam near Aberdeen, Mississippi. 1 The dam and lock walls consist of a series of concrete monoliths that are 60 feet high, 42 feet long, and 30 feet wide. The contract required Granite to embed polyvinylchloride (PYC) water-stop in the vertical joints between each monolith in order to prevent water leakage.

After approximately 10 percent of the waterstop was permanently embedded in the monoliths, the Corps tested the water-stop, determined that it did not meet the contract requirements, and required Granite to remove and replace virtually all of the installed waterstop.

After removing and replacing the water-stop, Granite sued its suppliers Alpha Ex-truders (Alpha), Vimco Concrete Accessories (Vimco), Saf-T-Grip Specialties (STG), and Stafford in a United States district court and recovered $400,000 from Vimco and Stafford by settlement. In addition, Granite obtained a default judgment against Saf-T-Grip and Alpha for $894,750. Granite assigned its rights against the latter two suppliers to insurers, and agreed to pursue a claim against the Corps. Granite also agreed to furnish one-half of any recovery to Vimco and Stafford or their insurers.

Granite filed a $3.8 million claim with the contracting officer. On appeal, the Board conducted a trial on liability in May of 1983. On December 19, 1988, the Board issued a split decision denying Granite’s claim in its entirety. 2 The Board majority determined that the contract required Granite to inspect and test the waterstop to ensure that it met contract specifications. The Board further determined that the government had a right to insist upon strict compliance with the contract specifications and to require the complete removal of the embedded STG waterstop. One judge concurred and dissented in part, concluding that Granite was entitled to delay damages for the Corps’ failure to periodically test the waterstop. The dissenting judge also found that the Corps arbitrarily and capriciously failed to evaluate the adequacy of the waterstop for the Aberdeen project.

Pursuant to the Wunderlich Act, 41 U.S.C. §§ 321-22 (1978), Granite sought judicial review of the Board’s decision with the United States Claims Court. Upon review of the Board’s decision in accordance with the standards provided in the Wunder-lich Act, the Claims Court agreed with the Board and granted the government’s motion for summary judgment.

DISCUSSION

I.

The Standard of Review

Because Granite entered into the Aberdeen lock and dam contract prior to the effective date of the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 601 et seq. (1988), and did not elect CDA coverage, the disputes provisions of the Wunderlich Act govern this appeal. Essex Electro Eng’rs, Inc. v. United States, 702 F.2d 998, 1002-03 (Fed.Cir.1983). The Wunderlich Act provides;

§ 321. Limitation on pleading contract provisions relating to finality; standards of review *1001 No provision of any contract entered into by the United States, relating to the finality or conclusiveness of any decision of the head of any department or agency or his duly authorized representative or board in a dispute involving a question arising under such contract, shall be pleaded in any suit now filed or to be filed as limited judicial review of any such decision to cases where fraud by such official or his said representative or board is alleged: Provided, however, That any decision shall be final and conclusive unless the same is fradulent [sic] or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence.
§ 322. Contract provisions making decisions final on questions of law
No Government contract shall contain a provision making final on a question of law the decision of any administrative official, representative, or board.

Board decisions under the Wunderlich Act are subject to two stages of appellate review, first by the Claims Court and then by this court. The Claims Court reviews the legal conclusions of the board de novo and factual findings under the substantial evidence test. Although Granite appeals from the decision of the Claims Court, we essentially review the underlying decision of the board under the same standards applied by that court. Cf. Matsushita Electric Indus. Co. v. United States, 929 F.2d 1577, 1578 (Fed.Cir.1991); American Permac, Inc. v. United States, 831 F.2d 269, 273 (Fed.Cir.1987), ce rt. dismissed, 485 U.S. 901, 108 S.Ct. 1067, 99 L.Ed.2d 229 (1988); See also Vista Scientific Corp. v. United States, 808 F.2d 50, 52 (Fed.Cir.1986).

II.

The Waterstop Testing Issue

A.

The first issue presented is whether the government is liable for the failure to periodically test the waterstop. Granite argues that the Corps was required under the inspection provisions of the contract to perform a specified number of tests on the waterstop to determine whether the material complied with the specifications. Granite contends that the government’s failure to test the waterstop before it was permanently embedded in the structure caused the contractor to incur costs exceeding $3.8 million. Had the government conducted periodic testing of the waterstop in a timely fashion, Granite argues, the nonconforming waterstop would have been discovered prior to installation and remedied by Granite at a much lower cost.

B.

The provisions of the contract pertaining to the inspection and testing of the water-stop are set forth in the decisions of the Board and the Claims Court, to which the reader is referred for a complete statement of these terms. It will suffice for our purpose to paraphrase the pertinent sections of the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sage Acquisitions LLC v. Hud
119 F.4th 973 (Federal Circuit, 2024)
Apple Inc. v. Corephotonics, Ltd.
81 F.4th 1353 (Federal Circuit, 2023)
Superior Maritime Services, Inc.
Armed Services Board of Contract Appeals, 2023
Auld v. United States
Federal Claims, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2021
Noaa Maryland, LLC v. Gsa
Federal Circuit, 2021
Premier Office Complex of Parma, LLC v. United States
134 Fed. Cl. 83 (Federal Claims, 2017)
Dobyns v. United States
118 Fed. Cl. 289 (Federal Claims, 2014)
Cardiosom, L.L.C. v. United States
58 Cont. Cas. Fed. 305,043 (Federal Claims, 2014)
Sufi Network Services, Inc. v. United States
755 F.3d 1305 (Federal Circuit, 2014)
Mata v. United States
114 Fed. Cl. 736 (Federal Claims, 2014)
Davis Wetlands Bank, LLC v. United States
114 Fed. Cl. 113 (Federal Claims, 2013)
SUFI Network Services, Inc. v. United States
108 Fed. Cl. 287 (Federal Claims, 2012)
Ponthie v. United States
98 Fed. Cl. 339 (Federal Claims, 2011)
Redland Co. v. United States
97 Fed. Cl. 736 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
962 F.2d 998, 37 Cont. Cas. Fed. 76,290, 1992 U.S. App. LEXIS 12548, 1992 WL 62127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/granite-construction-company-v-the-united-states-cafc-1992.