Joseph Sternberger, Trustee in Bankruptcy for Spenco, Inc. v. The United States

401 F.2d 1012, 185 Ct. Cl. 528, 1968 U.S. Ct. Cl. LEXIS 158
CourtUnited States Court of Claims
DecidedOctober 18, 1968
Docket223-60
StatusPublished
Cited by77 cases

This text of 401 F.2d 1012 (Joseph Sternberger, Trustee in Bankruptcy for Spenco, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Sternberger, Trustee in Bankruptcy for Spenco, Inc. v. The United States, 401 F.2d 1012, 185 Ct. Cl. 528, 1968 U.S. Ct. Cl. LEXIS 158 (cc 1968).

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Com- • missioner David Schwartz with directions to make findings of fact and recommendation for conclusions of law under the order of reference and the rules of the court. The commissioner has done so in an opinion and report filed August 16, 1968, on plaintiff’s assignment of errors, under Rule 99 (c) . * Plaintiff has filed no exceptions to or brief on this report and the time for so filing pursuant to the rules of the court has expired. Since the court agrees with the commissioner’s opinion, in which necessary facts and recommended conclusion of law are stated, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case, without oral argument. Therefore, plaintiff’s assignment of errors by the Board of Contract Appeals is denied, plaintiff is not entitled to recover and the petition is dismissed.

OPINION OF COMMISSIONER

SCHWARTZ, Commissioner:

The plaintiff is by suit in this court for breach of contract in effect seeking review of the decision of the Armed Services Board of Contract Appeals awarding him $5,161.88 on his claims for some $60,000 under a standard disputes clause in plaintiff’s 1955 contract with the Navy. (The contractor-claimant before the Board will be treated interchangeably with its trustee in bankruptcy, the substituted plaintiff.) Plaintiff’s assignment of errors by the Board is in substance a motion for summary judgment under Rules 94-100, and this opinion reports determinations and conclusions of law pursuant to Rule 99(c).

The contract was one for the production of a quantity of gun chargers and extra parts, at a fixed price of $83,510.91. Plaintiff sought costs attributable to a partial termination for 'the convenience of the government; costs of delays from alleged double inspection by the government, said to be a change under the changes clause; costs of allegedly improper inspection and rejections; and finally, costs of extras arising out of changes in the specifications. The Board held claimant entitled to an equitable adjustment of $232.83 on the claim for costs resulting from partial termination for convenience by reason of the government’s failure to order the spare parts contemplated by the contract, and an equitable adjustment of $4,929.05 for the remaining claimed costs and extras.

The questions in dispute in this court concern onljr the amount of the awards. The contention, presented by plaintiff’s assignment of errors committed by the Board, is that the Board decision is not supported by substantial evidence and thus not entitled to finality under the Wunderlich Act, 41 U.S.C. § 321. Plaintiff prays that the Board decision be held not binding, that the claims to costs in addition to those awarded be upheld, and that the case be remanded to the Board for negotiation of damages.

The first challenge to the Board’s decision is based on the omission of the government to present any witnesses on the issues of damages. The plaintiff urges that its evidence of damages and its claim for $60,000 were thus uncon-troverted, and that the award may therefore not vary materially from the amount of the claim.

Plaintiff took the position, before the Board, that it could not show precisely the costs incurred as the result of the several government actions complained of, and it thus sought what it termed a “jury verdict” by the Board upholding a claim for the total costs of the alleged *1015 combined government delays and extras. Plaintiff’s evidence primarily took the form of an overall presentation, primarily presented through an expert witness, of what its costs should have been and what they actually were. The entire difference of $60,000 between estimated and actual costs (both estimates) was attributed to the government’s termination, delays, changes and extras. Plaintiff has thus combined the “jury verdict” approach to damages with the “total cost” method for the determination of damages, both discussed recently by this court in WRB Corporation et al. v. United States, 183 Ct.Cl. 409, 425-426 (1968).

Both “jury verdict” and “total cost” standards are not favored, and are permitted to be used to compute damages only upon strict conditions, recently stated by the court in WRB Corporation et al., supra. Some of these conditions are that the nature of the losses must be such that they cannot be determined with reasonable accuracy; that a showing must be made that the bid — the basis for the estimate of what costs should have been — was realistic; that the actual costs must be reasonable; and, finally, that the additional costs must be attributable only to the government’s changes and delays. These conditions are no more than just if the contractor is to meet his “essential burden of establishing the fundamental facts of liability, causation, and resultant injury.” Wunderlich Contracting Co. v. United States, 351 F.2d 956, 968, 173 Ct.Cl. 180, 199 (1965).

Little if any effort was made to meet these conditions, and such testimony as was given does not meet any of them. The Board justifiably found fault with such evidence as was presented.

Proof of damages or costs was made by testimony of the president of the contractor at the time of performance of the contract, by testimony of the mentioned expert on damages and by a “Summary of Claim” prepared by.a certified public accountant.

The president’s testimony was general and imprecise. Where it verged on the specific it was in response to leading questions, and entitled to and given little weight.

The expert, an industrial consultant who had made a study of the contractor’s costs and operations, testified at some length. He identified various exhibits and schedules embodying his analyses of costs, as the basis for his various intermediate and ultimate conclusions. He had, he said, relied upon records of the company, conversations with the president of the company, figures he had received from others as derived from the books, and on his own experience and background. He had relied, at least in part, on correspondence files which were not part of the record, on the experience of the president and others not named, on various estimates, and on “the experience of the people who made the estimate, which includes myself.” He identified work papers as prepared by him but “not necessarily” in his writing. He had included a profit figure of 12 percent “mainly because the president had established this in some little document I had seen somewhere relative to this case.” Some of his exhibits, as will appear below in discussions of individual awards, contained errors in arithmetic and errors in their summary of the underlying data. In one case, the underlying data was directly contrary to the point made in his summary. In others, increases in cost for a small number of the required parts were assumed to be an increase for every such part. The Board found his testimony “so inaccurate and so grossly exaggerated as to make it unreliable.”

The “Summary of Claim” by the accountant served primarily to detract from the expert’s testimony.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Bank National Association
Armed Services Board of Contract Appeals, 2023
Passamaquoddy Tribe v. United States
82 Fed. Cl. 256 (Federal Claims, 2008)
Franconia Associates v. United States
61 Fed. Cl. 718 (Federal Claims, 2004)
J.L. Simmons Co. v. United States
60 Fed. Cl. 388 (Federal Claims, 2004)
First Nationwide Bank v. United States
56 Fed. Cl. 438 (Federal Claims, 2003)
Yanco v. United States
45 Fed. Cl. 782 (Federal Claims, 2000)
Exxon Corp. v. United States
45 Fed. Cl. 581 (Federal Claims, 1999)
Doyon, Ltd. v. United States
42 Fed. Cl. 175 (Federal Claims, 1998)
H.B. Mac, Inc. v. United States
41 Cont. Cas. Fed. 77,028 (Federal Claims, 1996)
Apollo Computer, Inc. v. United States
32 Fed. Cl. 334 (Federal Claims, 1994)
Hearst Corp. v. United States
28 Fed. Cl. 202 (Federal Claims, 1993)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Aeron Marine Shipping Co. v. United States
26 Cl. Ct. 946 (Court of Claims, 1992)
Granite Construction Company v. The United States
962 F.2d 998 (Federal Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
401 F.2d 1012, 185 Ct. Cl. 528, 1968 U.S. Ct. Cl. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-sternberger-trustee-in-bankruptcy-for-spenco-inc-v-the-united-cc-1968.