H.B. Mac, Inc. v. United States

41 Cont. Cas. Fed. 77,028, 36 Fed. Cl. 793, 1996 U.S. Claims LEXIS 197, 1996 WL 684183
CourtUnited States Court of Federal Claims
DecidedNovember 25, 1996
DocketNo. 93-79C
StatusPublished
Cited by1 cases

This text of 41 Cont. Cas. Fed. 77,028 (H.B. Mac, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H.B. Mac, Inc. v. United States, 41 Cont. Cas. Fed. 77,028, 36 Fed. Cl. 793, 1996 U.S. Claims LEXIS 197, 1996 WL 684183 (uscfc 1996).

Opinion

OPINION

ROBINSON, Judge:

H.B. Mac, Inc. (“plaintiff’ or “H.B. Mae”), is a self-certified, small, disadvantaged business (“SDB”). The claim it asserts arises out of a contract for construction of various operational and maintenance facilities at Ft. Shatter, an Army installation in Honolulu, Hawaii. After the contracting officer’s denial of plaintiffs claim, H.B. Mae filed a timely complaint in this court under the Contract Disputes Act (“CDA”), 41 U.S.C. § 601 et seq. .Trial was held in Honolulu, Hawaii during the week commencing September 19, 1994. Over plaintiffs objections, the court granted defendant’s two separate motions to amend its answer to assert the affirmative defense of fraud and later to interpose four counterclaims for fraud, arising under the False Claims Act (“FCA”), 31 U.S.C. §§ 3729 et seq. as well as the common law remedies of rescission and unjust enrichment. The fraud trial took place in San Diego, CA, during the week commencing May 22, 1994. For the reasons explained fully below, the court has determined that it is necessary to dispose of the issues presented by defendant’s First and Second Amended Answers before resolving the issues presented in plaintiffs contract claims suit. Thus, the court subsequently stayed consideration of plaintiffs contract [796]*796claim to permit resolution of defendant’s fraud claims, since a determination that defendant’s fraud claims had merit could result in forfeiture of plaintiffs contract claim. See Forfeiture of Fraudulent Claims Act (“FFCA”), 28 U.S.C. § 2514. After concluding the trial of defendant’s fraud claims, the court issued a preliminary bench ruling in plaintiffs favor and lifted the stay. Thereafter, the parties submitted post-trial briefs and presented closing arguments in Washington, D.C. on September 20, 1995. After an exhaustive review of the evidence, consideration of said briefs, and hearing of the parties’ oral arguments, the court iterates its finding that defendant’s counterclaims are without merit. With respect to plaintiffs contract claim, the court finds, in part, for plaintiff for the reasons set forth below.

Factual Background

On or about July 31, 1991, plaintiff entered into a contract with the Department of the Army (“Army”) wherein plaintiff was to perform certain construction work known as the OMS/DS/GS Maintenance Facility (“Maintenance Facility”), and other work (collectively “Project”) at Ft. Shafter, Oahu, Hawaii, under Contract No. DACA83-91-C-0029 (“Contract”). The Contract documents required plaintiff inter alia to furnish all plant, labor, equipment, appliances, and material, and to perform all work as required to construct a 35.000 square-foot reinforced concrete masonry unit as a motor vehicle repair facility with associated site work and structures, the Maintenance Facility, and a separate wash rack facility. The wash rack facility consisted of a wash rack with mechanical equipment to wash vehicles, one or more concrete slabs, an adjacent sedimentation basin to receive the effluent from the washing operation and to separate solids from liquids, and an oil/water separator consisting of a prefabricated 15.000 gallon steel tank, associated pipes and other equipment. The sedimentation basin and oil/water separator were approximately 130 feet apart. However, the entire wash rack facility, i.e, the washing facilities, the sedimentation basin and the oil/water separator unit, were located about 300 yards from the Maintenance Facility. The Project site lies near the Pacific Ocean and Keehi Lagoon. Both are about 700 yards away from the Project site. Also, various small streams flow through the area, one of which, Kahauki Stream, is located only a short distance away from the Project site but does not actually flow through the Project site. There are also other streams flowing through the area. Groundwater levels at the Project site are affected by those streams, by tidal fluctuations of the Pacific Ocean, and by precipitation.

Ft. Shafter is located on an alluvial plain containing a variety of soils typical of sedimentary soils deposited at various times during the area’s geologic development and a mixture of surface soils disturbed to some extent by past construction activity. However, as the court noted during its pretrial site visit, the site contains no significant above ground indications of subsurface soil conditions such as geologic outcroppings. Accordingly, bidders had to rely almost entirely upon Army-supplied soil boring logs for indications of subsurface conditions. The Maintenance Facility is located between the Pacific Ocean and the wash rack facility and, therefore, is closer to the ocean than is the wash rack facility. The entire area varies little in elevation, and groundwater levels throughout the Project site are approximately the same.

Bidders were provided with Contract specifications and drawings, including eight logs of sofl borings, all of which were located at or near the Maintenance Facility. One of the borings went to a depth of twenty-four feet. Three of the eight borings showed that the ground water table was at approximately mean sea level (“MSL”) or about twelve feet. However, the ground water table could vary upward or downward by as much as two feet, i.e., between ten and fourteen feet below ground surface depending upon tidal fluctuations, nearby stream flows and amounts of local precipitation. The other five borings did not extend to the depth of the water table. The Army provided no other subsurface information to the bidders such as geologic data or soil reports.1

[797]*797After reviewing the Contract documents and conducting a routine site visit, H.B. Mac submitted its competitive bid, pursuant to the Army’s solicitation for competitive bids. These solicitations went to only small disadvantaged businesses because the procurement was a “set aside.”2 Subsequently, plaintiff, as an SDB, was awarded the Contract in the amount of $6,281,000. The Contract required commencement of the work within seven days after receipt of the Army’s notice to proceed (“NTP”), which was issued August 13, 1991 and received August 19, 1991, and completion within five hundred fifty calendar days or on or before February 25,1993.

By October 17, 1992, H.B. Mae had excavated and completed work on a part of the wash rack including the sedimentation basin. H.B. Mac successfully performed the excavation work for the sedimentation basin using temporary aluminum/wood safety shoring (no sheet pile shoring) to a depth of approximately fourteen feet. H.B. Mac excavated one of two side walls using a vertical cut and the other using a sloped wall method of excavation. The vertical wall maintained its face for approximately three to four months after excavation until construction of a vertical concrete wall was completed notwithstanding rain and other weather conditions which could cause or contribute to wall failure. Only nuisance water was encountered in the sedimentation basin during its construction which was easily removed by a small pump. The subsurface soils H.B. Mac encountered during construction of the sedimentation basin did not vary significantly from those shown in the borings.

On or about October 17, 1992, H.B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
41 Cont. Cas. Fed. 77,028, 36 Fed. Cl. 793, 1996 U.S. Claims LEXIS 197, 1996 WL 684183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hb-mac-inc-v-united-states-uscfc-1996.