Mojave Enterprises v. United States

31 Cont. Cas. Fed. 71,507, 3 Cl. Ct. 353, 1983 U.S. Claims LEXIS 1631
CourtUnited States Court of Claims
DecidedSeptember 15, 1983
DocketNo. 74-82C
StatusPublished
Cited by19 cases

This text of 31 Cont. Cas. Fed. 71,507 (Mojave Enterprises v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mojave Enterprises v. United States, 31 Cont. Cas. Fed. 71,507, 3 Cl. Ct. 353, 1983 U.S. Claims LEXIS 1631 (cc 1983).

Opinion

OPINION

WOOD, Judge:

In this action, before the court on cross-motions for summary judgment, plaintiff1 seeks review, under the familiar standards of the Wunderlich Act, 41 U.S.C. §§ 321-22 (1976), of a decision of the Department of Agriculture Board of Contract Appeals (“the Board”) denying three claims to additional compensation based primarily upon allegedly erroneous “express and detailed representations of the nature and extent of [the rock and blasting] work to be performed * * *” by plaintiff under a contract with defendant.2

[355]*355Plaintiff contends that the Board’s denial of the said claims is unsupported by substantial evidence and erroneous as a matter of law. Defendant’s response is that the Board decision is free from any vitiating defect. For the reasons hereinafter appearing, it is concluded that the Board decision is supported by substantial evidence and legally correct, and is therefore deserving of finality. Accordingly, plaintiff’s motion for summary judgment is denied, and defendant’s cross-motion is granted. Plaintiff’s complaint will be dismissed pursuant to RUSCC 58.

I

The facts stated herein were found by the Board or are otherwise properly derived from the administrative record. See Ordnance Research Inc. v. United States, 221 Ct.Cl. 641, 609 F.2d 462 (1979).

On October 3, 1972, the United States Forest Service, Department of Agriculture, issued an invitation for bids (IFB), together with instructions to bidders, for the construction of a 4.68 mile segment of the Pacific Crest Trail. The proposed construction site was within the Marble Mountain Wilderness Area of the Klamath National Forest, in northern California.

Among other things, the IFB advised prospective bidders that the proposed construction work was in very rough terrain, that they “should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, and the general and local conditions which can affect the work or the cost thereof,” and that “Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work.”3

The IFB also reflected that access to the construction site was by trail only to the beginning and ending of the project, and that it would take two days to complete a tour of the job site. Bids for trail tread and drainage excavation on the basis of a unit price per linear foot were requested. The measurement and payment provisions for trail tread and drainage excavation4 to be included in the contract when awarded were as follows:

3. Method of Measurement
3.1 The linear footage of trail tread and drainage excavation, regardless of classification or volume of material encountered, to be paid for shall be the actual number of linear feet between the points of beginning and end, completed and accepted.
4. Basis of Payment
4.1 The linear footage measured as provided above, shall be paid for at the contract unit price per linear foot for Item T-51, ‘Trail Tread and Drainage Excavation.’ Payment therefore [sic] shall constitute full compensation for all materials, labor, equipment, tools and incidentals necessary to complete the item.

The IFB included “Plans for Construction Kidder Creek Segment.” Those plans included a vicinity map and three sheets reflecting certain information about the proposed construction site beginning at Station 0 + 00 and extending to the end of the project at Station 247 +15.5 Among other things, the plans contained a number of columns, opposite which appeared, in horizontal line diagram (or bar graph) form, certain data concerning the proposed construction work. The columns included “Side Slope” and “Trail Grade” (in percentages); “Min. Trail Tread” (in inches); “Drainage Dips, Rock Drainage, [and] Switchbacks”; “Select Borrow, Trails, and [356]*356Structures”; “Clearing”; “Topography, Streams, Etc.”; and “Remarks.”

Without any inspection of the proposed construction site, or even any inquiry to anyone connected with the project concerning existing site conditions, but rather solely from a review of the plans attached to the IFB, plaintiff calculated and timely submitted to defendant a bid based (in pertinent part) on the amount of “rock work” it thought the proposed construction would require. Its estimate as to the amount of such “rock work” was derived from the “Topography, Streams, Etc.” and “Remarks” columns.6 Plaintiff’s bid was the lowest of the seven bids received, and on November 21, 1972, it was awarded Contract No. 39-4524 (“the contract”) for the construction of the 4.68 mile segment at a contract price of $83,240.05.

Had plaintiff made any site inspection, the rocky nature of the proposed construction site would have been readily apparent to it. Plaintiff’s estimate as to the amount of “rock work” required to complete construction of the trail fell considerably short of the actual amount of such work it performed under the contract. Plaintiff asserted administratively that as a result of unanticipated rock work and blasting, and a consequent increase in transportation of materials, equipment and supplies to and from the construction site, its cost of performing the contract had increased by some $28,000 (not including overhead, burden, and profit).

Prior to the commencement of construction, government engineers had relocated the centerline stakes of a portion of the trail near Station 32 + 50. In doing so, however, flagging used to identify the trail route apparently was not moved. Plaintiff subsequently constructed a short portion of the trail by following the flagging, only to discover thereafter that the trail had in fact been relocated. The contracting officer allowed plaintiff as an equitable adjustment part, but not all, of the sum claimed for the trail relocation work.7

II

A. The Rock Work and Blasting Claim

Before the Board, plaintiff asserted that it had reasonably relied on the plans as defining in detail the nature and extent of the rock work and blasting required under the contract, and that those plans had erroneously misrepresented the nature and extent of such work, thereby entitling plaintiff to the equitable adjustment claimed. The Board denied the “rock work” claim, holding in essence that the plans did not purport to show the amount of the rock work required to complete contract performance and therefore did not misrepresent the amount of such work to be performed; and that, if plaintiff were “misled it was because [it] unreasonably assumed that [the plans] adequately showed the rock work to be performed.” Mojave Enterprises, supra, 77-1 BCA (CCH) ¶ 12,337 at 59,-660.8 The rock work claim was accordingly denied in its entirety.9 Ibid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Constructors, LLC v. United States
95 Fed. Cl. 26 (Federal Claims, 2010)
Jay Cashman, Inc. v. United States
88 Fed. Cl. 297 (Federal Claims, 2009)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Dan Nelson Construction, Inc. v. Nodland & Dickson
2000 ND 61 (North Dakota Supreme Court, 2000)
Hoffman Construction Co. v. United States
42 Cont. Cas. Fed. 77,247 (Federal Claims, 1998)
H.B. Mac, Inc. v. United States
41 Cont. Cas. Fed. 77,028 (Federal Claims, 1996)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Sergent Mechanical Systems, Inc. v. United States
40 Cont. Cas. Fed. 76,860 (Federal Claims, 1995)
Ralph L. Jones Co. v. United States
33 Fed. Cl. 327 (Federal Claims, 1995)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,240 (Court of Claims, 1991)
Edwards v. United States
36 Cont. Cas. Fed. 75,822 (Court of Claims, 1990)
Dawco Construction, Inc. v. United States
35 Cont. Cas. Fed. 75,755 (Court of Claims, 1989)
Weeks Dredging & Contracting, Inc. v. United States
34 Cont. Cas. Fed. 75,356 (Court of Claims, 1987)
McCormick Construction Co. v. United States
34 Cont. Cas. Fed. 75,319 (Court of Claims, 1987)
Johns-Manville Corp. v. United States
12 Cl. Ct. 1 (Court of Claims, 1987)
Clark v. United States
32 Cont. Cas. Fed. 72,563 (Court of Claims, 1984)
J.F. Shea Co. v. United States
31 Cont. Cas. Fed. 71,811 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,507, 3 Cl. Ct. 353, 1983 U.S. Claims LEXIS 1631, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mojave-enterprises-v-united-states-cc-1983.