McCormick Construction Co. v. United States

34 Cont. Cas. Fed. 75,319, 12 Cl. Ct. 496, 1987 U.S. Claims LEXIS 105
United States Court of Claims·Decided June 19, 1987·No. No. 714-85C·Published·Cited by 2 cases

Opinion

[497] OPINION

MOODY R. TIDWELL, III, Judge:

This contract dispute comes before the court on defendant’s motion for summary-judgment. Plaintiff requests an equitable adjustment as the result of alleged Type I differing site conditions and also alleges concealment of information regarding site conditions by defendant. Defendant’s motion for summary judgment is denied because there are genuine issues of material fact, which render summary judgment inappropriate.

FACTS

The claim is brought by plaintiff, McCormick Construction Company, Inc. (McCormick) on behalf of its subcontractor, Western Well & Pump, Inc. (Western). On February 14, 1984, Contract No. DACA63-84-C-0064, in the amount of $1,876,507.50, was awarded to McCormick by the United States Army Corps of Engineers (Corps). The contract, in part, required the drilling of three water wells, Frenchy 1, Frenchy 2, and Escondido 1 (FI, F2 and El) at a site 15 miles southwest of the Holloman Air Force Base, Alamogordo, New Mexico. Plaintiff subcontracted with Western to do the drilling of the three water wells to depths of 900 feet, 725 feet and 1,025 feet respectively, for a contract price of $478,-450.

Plaintiff alleges that Western experienced unforeseen difficulties at the site as the result of alleged Type I differing site conditions encountered while drilling the wells. Under Paragraph 4 of the contract General Provisions, a contractor is entitled to an equitable adjustment for Type I differing site conditions when “subsurface or latent physical conditions ... diff[er] materially from those indicated in the contract.” General Provisions ¶ 4(a). The bidder’s site investigation and adequacy of the contract documents both go to the heart of the conflict in determining whether plaintiff encountered Type I materially differing site conditions. The site investigation revealed an alluvial fan formed by erosion and outwashes from the Sacramento mountains. Numerous rock outcrops and boulders were also visible on the surface. The alleged deficient contract bid documents included a driller’s log prepared by R.L. Guffey & Co. (Guffey) and six boring logs prepared by Daniel Engineering, Inc. and Rady & Associates. The Guffey driller’s log that appeared in the contract bid documents was one of two required in a contract awarded Guffey by the Holloman Air Force Base Engineers’ Office to drill test holes at the FI, F2 and El sites. Guffey was also required to furnish a geophysical (electric) log. Mr. Roy F. Senior, Jr., President of Western, reviewed the driller’s logs, the boring logs and undertook a site investigation prior to submitting his bid for the drilling subcontract. Plaintiff anticipated it would take 24 days to drill the wells, instead it took seven weeks. Plaintiff's drilling difficulties are represented by the 22 “twist-offs” experienced while drilling when trade standards suggest that one per 10,000 feet drilled is extraordinary.

Plaintiff also claims that defendant actively concealed or had superior knowledge of information that would have alerted plaintiff to the subsurface conditions. Despite plaintiff’s requests, certain logs were not made available until after bids were submitted. Plaintiff states that he was told by defendant that such records did not exist. Defendant contends there was no conscious effort to conceal test drill information, and further asserts that any unob-tained information was not essential for an adequate evaluation of subsurface conditions.

On November 20, 1984, plaintiff submitted a formal claim to the Corps requesting reimbursement of the $451,254.38 for additional costs resulting from differing site conditions. On May 17, 1985, plaintiff’s claim was denied.

DISCUSSION

The present case comes before this court on defendant’s motion for summary judgment. Summary judgment is appropriate where there are no genuine issues of material fact in dispute and the moving parly is entitled to judgment as a matter of law. South Louisiana Grain Services, Inc. v. [498] United States, 1 Cl.Ct. 281, 289 (1982); RUSCC 56(c).

A. Type I Differing Site Condition

In order to prevail upon its Type I differing site condition claim, plaintiff must demonstrate that the conditions indicated in the contract documents differ materially from those encountered by Western during performance. P.J. Maffei Building Wrecking Corp. v. United States, 732 F.2d 913, 916 (Fed.Cir.1984); Clark v. United States, 5 Cl.Ct. 447, 452 (1984), aff'd. 770 F.2d 180 (Fed.Cir.1985); Mojave Enters. v. United States, 3 Cl.Ct. 353, 356 (1983). In order to determine, as a matter of law, whether Western’s interpretations of the contract indications are reasonable, the court must place itself “into the shoes of a ‘reasonable and prudent’ contractor.” P.J. Maffei at 917 (citing H.N. Bailey & Assocs. v. United States, 196 Ct.Cl. 156, 163, 449 F.2d 387, 390 (1971), and Hegeman-Harris & Co. v. United States, 194 Ct.Cl. 574, 589, 440 F.2d 1009, 1016 (1971)). At this point, the court is of the opinion that it is unclear as to whether a pre-bid site investigation should have indicated, to a “reasonable and prudent” contractor, the subsurface conditions encountered by plaintiff. Each party has offered its own interpretation of the site investigation for evaluating subsurface conditions, which is supported by affidavits and documentation. Defendant contends that surface conditions are determinative of subsurface conditions and that as a “reasonable and prudent” contractor, plaintiff had notice to anticipate difficult conditions, particularly in view of the presence of numerous rock outcrops and boulders in the alluvial fan. Plaintiff counters that it is reasonable for a contractor not to rely on the existence of surface boulders to indicate subsurface conditions even in the alluvial fan. The plaintiff further asserts that even if surface boulders indicated subsurface boulders, the extraordinary drilling difficulties resulted from concentrations of nested and overlapping boulders which could not have been anticipated from a site investigation. In view of the parties’ conflicting affidavits, the court needs to consider expert testimony and other relevant information before ruling on this matter.

Free access — add to your briefcase to read the full text and ask questions with AI

McCormick Construction Co. v. United States, 34 Cont. Cas. Fed. 75,319, 12 Cl. Ct. 496, 1987 U.S. Claims LEXIS 105 (cc 1987).

34 Cont. Cas. Fed. 75,319 (McCormick Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.